This statement of work outlines requirements for gas detection units and confined space training to support regulatory compliance at Hoover Dam. The Bureau of Reclamation seeks ten gas detection monitors with dual infrared sensors to detect five gases. Accompanying equipment includes tubing, probes, filters, and two charging stations. Drager equipment is specified and service must be provided through Drager. Initial delivery within eight weeks is requested with optional yearly training and maintenance through the five-year period of performance. Training involves confined space entry certification for up to sixty personnel annually. Performance will be at Hoover Dam facilities.

View the file

Other files for this federal contract opportunity

Other files attached to Gas Detection units with Confined Space training, newest first.
File Type Posted
Attachment_3_-_Brand_Name_Justification.pdf PDF
Exhibit_2_-_Confined_Space_EAS_Training_Course_Outline.pdf PDF
Sol_140R3023Q0019.pdf PDF
Exhibit_1_-_HDP-06_-_Hoover_Dam_Confined_Space_Program.pdf PDF
140R3023Q0019_RFQ.pdf PDF
Attachment_2_-_WD_2015-5593.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Purchase Requisition Gas Detection Units Regulatory required Life-Saving Equipment

Gas Detection Units

1. Introduction

The Bureau of Reclamation (BOR), Lower Colorado Dams Office, Hoover Dam has a need for regulatory required lifesaving equipment used during confined space operations. The vendor shall provide hand-held multiple-gas detection air monitoring equipment to include supporting charging calibration system, accessories and support services including:

Hoover Dam personnel must regularly access confined spaces to complete daily tasks and duties.

Routine and non-routine activities are completed as required in confined spaces. The current hand-held multiple gas detection monitors are at the end of their life cycle. Existing gas detection units do not provide adequate detection capability to facility identified hazards, which may lead to potential exposure during common confined space work. Considerations for confined space work comprise of identified Permit-Required Confined Spaces exceeding 141Ft (43m) in length or depth. Personal and area monitoring is necessary as a preventative measure to avoid inadvertent employee exposure to hazards.

1.1 Regulations

Applicable Occupational Safety Health Administration (OSHA), General Industry Standard (29CFR 1910) and Construction standard (29CFR1926) regulations, Reclamation Safety and Health Standards (RSHS) with select American National Standards Institute (ANSI), National Fire Prevention Association (NFPA) and specified National Institute for Occupational Safety and Health (NIOSH) guidelines pertain to this Statement of Work.

a. The RSHS handbook can be downloaded electronically at http://www.usbr.gov/ssle/safety/RSHS/rshs.html for no charge for use in connection with the specifications in accordance with the notice titled “Notice of Safety and Health Requirements and of Safety Handbook Availability – Reclamation”.

b. Procedures to limit building entry or exit may be coordinated with the Contracting Officer’s Representative (COR).

1.2 Work Coordination

The Contractor shall coordinate the schedule through the COR. The initial schedule coordination shall be accomplished within 14 Calendar days after receipt of the Notice of Award.

1.3 Brand Name:

Vendor shall meet the specified requirements to include Dräger-branded equipment (See table below), Dräger equipment operation and Dräger Safety Consulting Solutions Confined Space operation training referred to as Confined Space Entrant Attendant & Supervisor (CSE) for up to http://www.usbr.gov/ssle/safety/RSHS/rshs.html a 5-year period (if all options are exercised). Sustainment system shall be provided through Dräger.

2. Scope:

This requirement acquisition of configured lifesaving equipment with support and accessories for confined space work. Hoover Dam complex contain confined spaces with associated hazards accessed by dam personnel weekly as part of their tasks and duties. The scope of this work includes for delivery of gas detection units with manufacturer ‘service and support, and also confined space operations training.

3. Objectives:

3.1 Contractor shall provide evidence for the required services and equipment through:

3.1.1 Manufacturer certification for the lifesaving equipment.

3.1.2 Manufacturer certification for the lifesaving equipment technical specialty support for maintenance and care of the items.

3.1.3 Certified by the manufacturer as an approved instrumentation training and training servicer for the manufactured equipment.

3.2 Any repair work identified during maintenance and servicing will be communicated to the COR or assigned designee.

3.3 Duration. Delivery of the equipment preferred within eight weeks; Confined Space

Entrant, attendee, supervisor (CSE) training to take place minimum once a year; one base year with four optional years.

3.4 Start of work on-site will be determined per the duration terms and scheduled with the Contracting Office Representative (COR).

3.5 Physical Security. Comply with physical security requirements, including escort coordination requirements.

4. Gas Detection Units:

4.1 Equipment. The handheld air monitoring gas detection equipment will contain a complete setup package for use of device, bump test, and calibration with appropriate accessories, for clearing confined space through sampling and continuous wear in the confined space by end-users. The technical services and training support, in addition to the technical specifications, are required for acceptance of the deliverable equipment.

A total of 10 units with two (2) charging calibration docking station system with all components are required. One charging docking calibration station with eight (8) unit cradles and all components, a second charging docking calibration station with two (2) cradles and all components. This comes to a total of 10 units, two (2) docking test stations with integrated charging capability of the recharge Nickel Metal Hydride (NiMH) power supply kit.

4.2 Technical Specification:

4.2.1 Gas Monitor Units (devices) must meet the ASTRO Accredited Program for

Excellence (APEx) standards for Mine Safety Health Administration (MSHA) certification and have MSHA Approval or the manufacture must provide a written equivalency letter for APEx sections meeting MSHA standards on manufacture letterhead.

4.2.2 The devices must meet the above plus the following approvals at a minimum: APEx:

I M1 Ex da ia I Ma, II 1G Ex da ia IIC T4/T3 Ga. CSA: Class I Div. 1 Group A, B, C, D, E, F, G T.-Code T4/T3 A/Ex da ia IIC T4/T3/ Ga. Protection Class: IP67.

4.2.3 A pump capable of providing capability to sample at least 141ft (43M) of tubing.

Diffusion and pump mode capability The item must contain 360-degree alarm notification capability, with visual, audible, and vibration alarms.

4.2.4 Alarm settings will be set to NIOSH guidelines.

4.2.5 Capable of 5-Gas detection (CO, CO2, O2, LEL, H2S) using a dual Infrared-sensor

(IR) as part of sensor configuration.

4.2.6 The device T4 power supply NiMH rechargeable power pack and charging set.

4.2.7 Manufacturer certified calibration gas media.

4.2.8 The devices must have a removable pump assembly capable of drawing samples at

147ft (45m), minimum, with the ability to operate in diffusion and pump modes.

4.2.9 The devices must be able to operate without the pump attached.

4.2.10 In diffusion mode with the pump removed, the device shall not exceed

1.85x5.08x1.22in in total size with the battery installed.

4.2.11 The detection unit should have an approximate weight of 7.8 oz.

4.2.12 The device shall easily insert into the pump and will not be screwed together for expedient switchover between diffusion and pump modes.

4.2.13 The device sensors will have sensor T-90 time for Dual IR CO2/ LEL, CO, O2, H2S of less than or equal to 15 seconds in diffusion mode, with applicable pump mode the average shall be 7-10 seconds.

4.2.14 The electrochemical sensors will have internal pressure compensation within the range of 700 to 1300 mbar to avoid electrolyte leakage.

4.2.15 The sensors must be capable of valid operation at temperatures of -4°F to 122°F.

4.2.16 The devices recommended times for the certified calibration sensors will be 6 months or180 days, with calibration required once every 12 months or365/66 days, per manufacture guarantee of sensors for holding calibration vitality.

4.2.17 The device will have upgrade capability through sensor arrangement to add OV/OVA sensor within the devices.

4.2.18 The devices must maintain the current gas detection plus the ability to upgrade sensors in the device dimensions.

4.2.19 Area monitoring upgrade, the personal Gas Detection device shall have the option to be placed into an alarm amplifying area monitor device with distinct 360° visible and audible evacuation alarms.

4.3 Tubing and Probe:

4.3.1 Only manufacturer approved, branded, tubing is authorized for use with equipment.

4.3.2 Sample tubing in various lengths with adaptors are solicited as accessories.

4.3.3 The following required items must have adaptor connectors for the specific brand devices provided and meet manufacture requirements.

4.3.4 Required are 8 of the following items: 59in ES Telescoping probes with adaptors, transparent float probes with luer adapter (5mm). Require 16 filter sets with 3mm/5mm hose connectors.

4.3.5 Quantity of 4 of 5m (16ft) FKM (3mm) hose with adapters and 4 of 10m (32ft) FKM hose (3mm) with adaptor

4.3.6 Quantity of 1, 20m (65ft) FKM hose (3mm) with adapter.

4.3.7 The manufacture must have available a 45m (147ft) hose length.

longer lengths may be purchased at later time to meet site needs.

4.4 Test and Calibration Station

4.4.1 An automated test system shall be available, “docking station”. The system should be able to calibrate and bump test all the units in parallel. Documentation for bump test, calibration and documentation shall be possible with optional mobile print system or compatible desk top printers. The test station shall have a means to store results. The docking station independently without any external power bump/calibration station will test the warning functions of the devices using manufacturer specific gas.

4.4.2 Comply with RSHS Section 14, 14.8.2.6.1 “All air monitoring equipment must be calibrated and maintained according to manufacturer’s specifications.”

4.5 Table A: Equipment characteristics and specified equipment to be delivered.

Description Part # / conf. Quantity X-am 5600 w/ 6851880 DrägerSensor Dual IR Ex/CO₂ - CH4 CO2, 6812212 Carbon Monoxide (CO) XXS-E, 6812213 Hydrogen Sulfide (H₂S) XXS-E, 6812211 Oxygen (O₂) XXS-E, 8318704NiMH Battery Only

8321050 / D1091011020

Kit Pump with USB charger, wall plug and shoulder strap.

8327115

Case for X-am pump 8327104 8 Float probe (transparent), with Luer adapter (5 mm), 50 mm FKM hose (5 mm)

8327654

Telescopic probe ES 150, 59 inches 8316533 8 Filter set with 3mm/5mm hose connectors 8319364 16

5 m FKM hose (3 mm) with adaptor 8325705 4

10 m FKM hose (3 mm) with adaptor 8325706

20 m FKM hose (3 mm) with adaptor 8325707 1

Draeger X-dock 6300 Master With 3 test gas connections plus fresh air. (Master units will come assembled with 8x and 2x 125 cradles per request)

8321900

Draeger X-dock Module X-am 125+ Cradle module for one instrument of the Draeger X-am 125 series with an additional charging function

8321891 10

Pressure Regulator Dräger X-Dock 8324250 4 Power supply 100-240 V, 24 VDC / 6.25 A for up to 10 modules

8321850 2

Sampling hose, FKM Tubing, 5 ft (not for Cl₂) 4594112 2

50% LEL CH₄, 100 ppm CO, 25 ppm H₂S, 2.5% CO₂, 17% O₂ (Shelf Life= 24 months)

4597160 2

Nitrogen Calibration Gas 100% Vol. (Shelf life=60 months)

4594838 2

USB-IR Communication Cable 8317409 2 Calibration/PC Communication Cradle w/o USB- IR Interface (requires 8317409)

8318752 2

4.6 Alarm settings: Set to National Institute for Occupational Safety and Health (NIOSH) guidelines instead of OSHA standard guidelines.

4.7 Delivery: Gas Detection Units desired delivery 120 days ARO.

5. Training

5.1 Training. 8-Hour Confined Space Entrant, Attendant & Supervisor (CSE).

5.2 Dräger Safety Consulting Solutions Confined Space Entry (CSE) Training will consist of

8 hr. Certified Confined Space Entrant, Attendant & Supervisor (CSE) Training course using materials but not limited to OSHA 1910.146, relative ANSI and NFPA Standards, and internal Dräger technical documentation and support, for up to 30 persons on two separate dates to train personnel on the equipment provided and the proper use of equipment during confined space operations.

5.3 Two separate 8-hour classes over the course of the week, up to 30 participants each class

5.4 The training must incorporate LCDO protocols including individual Dam Confined Space

Program (See aexhibit -1: HDP-06 Hoover Dam Confined Space program).

5.5 An updated protocol will be provided to the contractor prior to each on-site training.

5.6 Provided training completion certificate valid for 3-years as issued by Dräger Safety Consulting Solutions.

5.7 On-site CSE training will be provided at a minimum once every 12-month period by contract option.

5.8 IRS /GSA Standard Mileage Rate 2023, per diem, meals, and accommodations, shall be included.

5.9 8-Hour Confined Space Entrant, Attendant & Supervisor training (See Exhibit-2: Course Outline for Permit-Required Confined Space Entrant, Attendant & Supervisor Level) will contain at a minimum the training listed in the training outline.

Description Quantity 8-hour CSE Training (8-hour confined space entrant, attendant, and supervisor training (3-year certification issued), two separate 8-hour classes over the course of the week, and up to 60 participants (30 participants per day) Hoover Dam Block training is currently during August for yearly.

Contractor provides training for 1 base year and up to 4 optional years.

6. Delivery

The contractor shall deliver all items to Central Warehouse-Hoover Dam, S. Hwy 93, SR 172 Boulder City, NV 89005

7. Government furnished Property

There will be no Government-Furnished property provided to the contractor.

8. Security

The acquisition of the equipment and associated service does not require unique security requirements. All applicable policies and procedures of the Bureau of Reclamation (BOR), Lower Colorado Dams Office (LCDO), and Hoover Dam shall be followed.

9. Place of Performance

All work performed on BOR property will be performed at the following physical locations (or appropriate alternate locations with prior arrangement due to unforeseen circumstances):

1. Hoover Dam powerhouse training location

2. Hoover Dam conference rooms

3. Hoover Dam training rooms

10. Period of Performance

Period of Performance begins upon receiving the Notice of Award email and will expire five years after execution, if all options are exercised.

Exhibit-1: HDP-06 Hoover Dam Confined Space program.

Exhibit-2: Course Outline: Confined Space Entrant, Attendant, and Supervisor Training