This statement of work outlines plumbing installation requirements for an insectary building at the USDA Agricultural Research Service Pacific Basin Agricultural Research Center in Hilo, Hawaii. Key requirements include installing exterior spigots, interior sinks and faucets, a 240V 5 GPM water heater, supply lines to a washing machine and shipping container, and a spigot near environmental chambers. The contractor must provide all necessary labor, materials, equipment, permits and safety plans to complete the turnkey project within 30 calendar days of award according to federal, state and local codes. The solicitation number for this opportunity is 12905B24Q0009 and it was issued by the USDA Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
INSECTARY PLUMBING INSTALLATION
USDA-ARS
ARS-PBARC-DKI
64 Nowelo St, Hawaii 96720
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Title:
Insectary Plumbing Installation
b. Project Location:
USDA-ARS-DKI
Pacific Basin Agricultural Research Center
2.0 PROJECT CONTACT PERSONS:
a. CENTER DIRECTOR (CD):
Marisa Wall Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo Hi 96720 E-mail: marisa.wall@usda.gov
b. ADMINISTRATIVE OFFICER (AO):
Carlee Wehrsig
Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 932-2120 E-mail: carlee.wehrsigi@usda.gov
d. LOCATION CONTRACTING OFFICER REPRESENTATIVE (COR):
Pernell Hanoa
Facilities Manager Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 959-4356 Cell: (808) 896-4523 E-mail: pernell.hanoa@usda.gov
e. SAFETY OFFICER (CDSO) Scott Geib PhD
USDA-ARS Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo, Hawaii 96720 808-959-4335 E-mail: scott.geib@usda.gov mailto:carlee.wehrsigi@usda.gov mailto:pernell.hanoa@usda.gov mailto:scott.geib@usda.gov
3.0 SCOPE OF WORK
The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required service shall be in accordance with the requirements as described herein and on attached contract documents.
3.1 Background: The USDA/DKI-PBARC located at 64 Nowelo St in Hilo
Hawaii 96720 requires the turn-key plumbing installation of a 50’ x100’ metal research building. Plumbing includes (4) exterior spigots located on the corners of the building, Install (2) sinks and faucets (interior & exterior), (1) interior faucet to service a washing machine, (1) interior spigot with shut-off valve near environmental chambers/ equipment, (1) exterior supply line to connect to an exterior shipping container and (1) 240V- 5 GPM tankless water heater to provide hot water service to all sink faucets. Installation will include all necessary water supply lines, ABS waste lines, drains, vents, fittings, strut supports, insulation, materials, and all associated hardware. Note: See attachment (A) for project details and location.
3.2 Contractor shall install/plumb exterior spigots.
3.2.1 Contractor shall install supply lines for (4) exterior spigots to be located at each corner of the building.
3.2.2 Contractor shall ensure spigots are installed approximately 1’ from the corners of the building and 16” above the finished walkway.
3.2.3 Spigots will be securely fastened to building.
3.3 Contractor shall install (2) government furnished sinks and faucets.
3.3.1 Contractor shall install (2) new government supplied sinks and faucets to include hot and cold supply lines, all connections, shut off valves, waste lines and vents as required to make sinks operational.
3.4 Contractor shall install (1) 240V- 5 GPM on demand water heater.
3.4.1 Contractor shall supply and install (1) 240V-5GPM on demand water heater.
3.4.2 Contractor shall ensure that the water heater supplies hot water to all sink faucets and (1) already installed (exterior) water spigot.
3.5 Contractor shall install (1) interior water faucet to supply cold water to a washing machine.
3.5.1 Contractor shall install a wastewater drain to service the washing machine.
3.6 Contractor shall install supply line from exterior of building to shipping container
(approximately 45 ft from existing water line).
3.7 Contractor shall install supply line with spigot faucet (interior) with shut-off valve to area near existing environmental chamber equipment (approximately 30 ft from an existing water line).
3.8 All plumbing locations will be properly identified and marked.
4.0 PROJECT REQUIREMENTS:
a. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction and services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
d. This project falls under the DAVIS BACON Wage Act.
4.1 Background & Site Description:
The project site is located at the Daniel K. Inouye, Pacific Basin Agricultural Research Center
4.2 Bid Schedule:
Item Description
Base Item Provide materials, labor, equipment, and all associated services necessary to complete project.
4.3 Description of Work:
a. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.
b. The Contractor will provide all the necessary materials and labor per
Section 3.0 and properly dispose of all material being replaced.
c. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during construction. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.
d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.
4.4 Government Furnished Equipment\Services
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/
a. The Government does not anticipate the need in this project, but the
Government will be available to assist with the identification/location of utilities as necessary.
b. The Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
a. Contractor shall furnish a Site-Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) upon request,10 days after contract award. SSSP / APP shall be reviewed by the Government before construction work commences. In addition to the usual components of a safety plan, the plan shall include specific procedures to address mold encountered during the project.
b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
d. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the COR 21 working days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
5.10 Warranty:
a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED
PRIOR TO FINAL PAYMENT (other documents may also be required):
a. General contractors minimum one (1) year warranty on work.
b. Operation and Maintenance Data
c. Release of liens.
d. Final Invoice
6.0 PROJECT SCHEDULE: 30 calendar days after award.
ATTACHMENT (A)
WASHER & DRYER LOCATION SINK FAUCETS (2) EA.
SINK 1 SINK 2
FRONT OF BUILDING
SIDE OF BUILDING APPROXIMATELY 100’ IN LENGTH. REQUIRES (1) SPIGOT AT EACH
CORNER OF THE BUILDING FOR A TOTAL OF 4.
FAUCETS
Existing Environmental Exterior of Building Chamber Equipment to Shipping Container