Attachment_1_Statement_of_Work.pdf

PDF 501 KB Posted

Attached to
SEVEN LAKE FENCE PHASE II
Solicitation number
140L6223Q0023
Issued by

About this file

This statement of work and related documents outline requirements for a federal contract to construct approximately 15,893 linear feet of new 4-wire wildlife-friendly fence and remove 15,893 linear feet of existing 3-wire fence in Sweetwater County, Wyoming. The work will be performed on Bureau of Land Management land for the Department of the Interior. Products and services required include furnishing materials and labor to install steel t-posts, wood line posts and set posts, barbed and smooth wire, wood stays, and a single gate. The contractor will also remove the existing fence and properly dispose of all debris. Bid submissions are due based on the included bid schedule. The pre-bid conference, performance period, and inspection requirements are also defined.

View the file

Other files

File Type Posted
Attachment_2_Drawings.pdf PDF
Attachment_4_Bid_Schedule.xlsx XLSX spreadsheet
Attachment_6__SF_1442_Completion_Instructions.pdf PDF
Attachment_5_Wage_Determination_WY20230032.docx DOCX document
Sol_140L6223Q0023.pdf PDF
Attachment_7_Limitations_on_Subcontracting_Breakout.pdf PDF
Attachment_3_Maps.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Seven Lakes Fence Phase II 2023 STATEMENT OF WORK

SOW - 1

Statement of Work:

Seven Lakes Fence Phase II 2023

Introduction

The Seven Lakes Fence project is located in Sweetwater County, WY. The work includes removing 3.01 miles of existing barbed 3-wire lay-down fence with cedar posts and installing a wildlife friendly four-wire fence with 3 barbed wires, 1 smooth bottom wire, wood stays and metal t-posts. The fence is accessible via County Road 23 (Wamsutter - Crooks Gap Road).

Then west on BLM Road 3217 (Hadsell Road). The project location is located 1.24 miles to the east of the Hadsell Road and is accessible via existing two-track roads.

The fence is located along a section lines and therefore several corner markers/monuments can be seen along the fence line. Some are marked by a t-post and some are not. It is the contractor’s responsibility to not damage these monuments and it is recommended that they are flagged for greater visibility.

Location

From the town of Wamsutter, take County Road 23 North for approximately 25 miles. Turn west on BLM road 3217 (Hadsell Road) and an additional travel 10.27 miles. The project area is then located eats via established two-track roads approximately 1.24 miles. Alternately, from

Rawlins, Mineral Exploration Road (Carbon County) off Highway 287, which turns in to

Sweetwater County Road 63, can be taken to reach the project area.

T25N R94W (the north boundaries of) Sections 21, 22, 23.

Deliverables

Bids will be accepted based on bid schedule attached. All work shall follow specifications and drawings.

Seven Lake Fence Phase II 2023 GENERAL INFORMATION AND REQUIREMENTS

01009 - 1

SECTION 01009

GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.1 SUMMARY:

A. Description of Work: Furnishing material, labor and equipment, to construct approximately 15,893

Linear Feet (LF) of 4-wire wildlife friendly fence, with wood stays. Work also includes removal and disposal of 15,893 LF of existing 3-wire lay-down fence with wood posts.

B. Location: Work under this Contract is in Sweetwater County, Wyoming. Work locations are shown on the maps.

C. Work Data Sheet: Designates the type and quantity of work required at the project location, and dimensions required for typical drawings.

D. Debris: Debris consisting of wood posts, poles, steel posts, and wire shall become the property of the Contractor and shall be removed from the work site. The Contractor shall be responsible for disposal of construction debris in a legal manner, and for payment of any fees required. Burning of debris is not permitted on any federal or state owned property.

1.2 REFERENCES

A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/ standards referred to herein may be procured by the Contractor, from the following:

ALSC American Lumber Standards Committee

PO Box 210

Germantown, MD 20875

ANSI American National Standards Institute

11 W 42nd St.

New York, NY 10036

AWPA American Wood Preservers' Association

P.O. Box 286

Woodstock MD 21163

AWPA C 1-95 All Timber Products, Pressure Treatment

AWPA C 5-95 Fence Posts, Pressure Treatment

AWPA M 4-95 Care of Pressure Treated Wood Products

AWPA P 5-95 Waterborne Preservatives

AWPA P 8-95 Oil-Borne Preservatives

AWPA P 9-92 Solvents for Organic Preservative Systems

CFR Code of Federal Regulations (Available from the Government Printing Office)

N. Capitol St. between G and H St., NW

Washington, DC 20402

01009 - 2

FS Federal Standard

General Services Administration

Specifications Branch

Room 6039, GSA Building

7th and D Streets, S.W.

Washington, DC 20407

GSA General Services Administration

F St. and 18th St., NW

Washington, DC 20405

OSHA Occupational Safety and Health Administration

US Department of Labor

200 Constitution Ave., NW

Washington DC 20210

OSHA 2207-91 Construction Industry

WWPA Western Wood Products Association

522 SW 5th Avenue, Yeon Bldg

Portland, OR 97204-2122

1.3 SUBMITTALS

(There are no applicable requirements)

1.4 DELIVERY, STORAGE, AND HANDLING:

A. Delivery: The Contractor shall protect products incorporated into the work from damage while in transit to the site.

B. Storage: The Contractor shall provide temporary storage facilities for products. Storage shall comply with the manufacturer’s instructions. The storage area shall permit access for inspection and handling.

C. Handling: The Contractor shall load and unload products in such a manner that protects them from damage.

1.5 QUALITY ASSURANCE:

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

1.6 PROJECT/SITE CONDITIONS:

A. Access to the Work:

1. The work locations are shown on the drawings.

2. Access to the work shall be provided by and at the Contractors expense. No roads shall be constructed by the Contractor or off road driving permitted without prior written

01009 - 3 permission from the Contracting Officer.

3. Contractor shall exercise care to prevent unnecessary surface disturbance to existing grass, vegetation, and to existing roads and two-tracks.

4. Public, State, or private access roads damaged by the Contractor shall be restored, at the

Contractor’s expense, to the same condition they were in at the commencement of work.

B. Environmental Considerations:

1. No blading will be allowed.

2. Avoid disturbing all corner markers or monuments marking section lines along the fence line.

3. The contractor is responsible for doing a utility One-Call for safety. Tickets may be entered at: https://www.onecallofwyoming.com/

1.7 SEQUENCING AND SCHEDULING:

A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the

Contractor shall submit an updated schedule within three calendar days. As a minimum, the estimated start and completion dates shall be shown in the schedule.

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

3.1 PROJECT MEETINGS:

A. Pre-Work Conference:

1. A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.

3. The Contractor shall be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. Meetings shall be held at the project site, or as determined by the Contracting Officer.

2. Meetings may be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.

C. Final Inspection:

1. Meeting shall be held at the project site, or as determined by the Contracting Officer.

https://www.onecallofwyoming.com/

01009 - 4

2. The Contractor shall notify the Contracting Officer in writing at least 3 working days before the completion date so the Government can schedule final inspection.

3. The Contractor shall require the superintendent to be present during this inspection.

3.2 PREPARATION

A. Work Limits and Control Points: Will be established by the Contracting Officer.

3.3 SALVAGEABLE ITEMS

A. Requirements: Salvaged items consisting of wire and wood shall become the property of the

Contractor and shall be disposed of properly. Fence staples and clips shall be disposed of by the contractor. All steel t-posts removed and remaining in good condition will remain the property of the Federal Government Rawlins BLM Field Office. These t-posts will be neatly piled in location at either end of the project site.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: Work described in this section will not be measured for payment.

4.2 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made. The

Contractor shall include consideration for this item in the bid price for other items of the Contract.

END OF SECTION 01009

SECTION 01505

MOBILIZATION

Seven Lakes Fence Phase II 2023 MOBILIZATION

01505 - 1

1.1 SUMMARY:

A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site.

4.1 METHOD OF MEASUREMENT:

A. Units: Progress payments will be made as follows:

1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.

2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.

4.2 BASIS OF PAYMENT:

Payment: Prices and payment will be full compensation for the work described in this section.

Payment will be made under:

Pay Item Pay Unit

Mobilization Lump Sum

END OF SECTION 01505

Seven Lakes Fence Phase II 2023 WIRE FENCES AND GATES

02824 - 1

SECTION 02824

WIRE FENCES AND GATES

1.1 SUMMARY

A. Section Includes: Installing barbed wire, steel posts, double h-braces, and stress panels.

Remove existing wire fence and dispose of properly.

B. Related Sections:

General Information and Requirements Section 01009

1.2 SUBMITTALS

A. General: Submittals shall be according to Section 01009 - General Information and

Requirements.

1.3 QUALITY ASSURANCE

A. General: Contractor – All work will be inspected by the Contracting Officer’s

Representative before acceptance.

2.1 CONTRACTOR - FURNISHED MATERIALS

A. All building supplies and materials will be furnished by the Contractor including labor and equipment to install the fences.

3.1 PREPARATION

A. Clearing: No blading will be allowed. Cutting (i.e., mowing, chain sawing) of vegetation, along the established fence line route, shall be allowed. Dispose of cut and mowed brush by scattering it evenly adjacent to the fence line.

3.2 INSTALLATION

A. General:

02824 - 2

1. Steel posts shall not be used for end-panel, corner-panel, gate-panel, or stress-panel posts.

2. When treated posts must be bored or cut during construction, thoroughly swab untreated surfaces with copper naphthenate.

B. Driving Posts:

1. Wood Posts: Driving wood posts shall not be allowed.

2. Steel Posts: Drive into the ground to the depth shown on the drawings or until the anchor plate is slightly below the ground surface. Posts shall be driven plumb.

When rock formations prevent driving, remove anchor plate and excavate or drill holes a minimum of 18-inches deep and slightly larger than the diameter of the post. Place posts in the holes and grout the post solidly in position.

C. Setting Posts (set posts and line posts):

Dig holes for setting wood posts to the depth as shown on the Work Data Sheet. Set posts plumb and to the spacing and grades as shown on the drawings, unless staked otherwise. Space posts within 6-inches of the dimension shown on the drawings or specified on the Work Data Sheet. Holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Backfill with soil gradually and uniformly around each post. Holes shall be backfilled firmly, from the bottom of the hole to the top of ground surface.

D. Corner Post, Gate Post, Corner Panel, Brace, End Panel, and Stress Panel Assemblies:

Construct as shown on the drawings or as staked in the field. Rock jacks shall not be substituted for these items. Construct stress panels on crests of hills, and a maximum of

1320 feet center-to-center for barbed wire sections. In addition, stress panels are required at points between which wire is to be stretched. Construct end panels at the end of fence runs unless shown otherwise on the drawings.

E. Wire: Stretch tightly and staple to wood posts or securely attach to steel posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Drive staples crosswise with the grain of the wood. The wire shall be free to move through the staples as it expands and contracts. Terminate wire at each end post, gate post, corner post, or stress panel. Wrap wire around the post two times and tie off by wrapping around the incoming wire a minimum of four times.

F. Brace Wire: Twist tight with a lever. Leave one end of the lever long enough to fasten behind the horizontal brace to prevent wire from unwinding.

02824 - 3

1. The lever shall be a straight ridged rod, consisting of dimension wood ripped and cut to length or a minimum #4 rebar cut to length.

G. Spiking: For spikes larger than 40d, predrilled lead holes shall be used. The hole diameter shall be 3/4 the diameter of the spike and drilled to a depth no greater than 1/2 the length of the spike.

H. Minor Drainage Crossings: Additional steel posts shall be set at the top and bottom of breaks or the centerline of the drainage depending on the size and shape of the drainages. Additional wire shall start and end from the main fence. Shall be in locations staked in the field or as directed by the Contracting Officer.

I. Fence Stays: Wood fence stays shall be used in this Contract.

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will be measured and paid for by the job, each section, for fence constructed.

B. No direct payment will be made for drainage crossings or dead-men. The Contractor shall include consideration for these items in the bid price for other items of the contract.

C. Fence removal will be measured and paid for as incidental under this Section 02824.

4.2 BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Fence Construction Linear Foot

END OF SECTION

Seven Lakes Fence Phase II 2023 FENCE-DRAINAGE CROSSINGS

02826 - 1

SECTION 02826

FENCE-DRAINAGE CROSSINGS

A. Section Includes: Furnishing and installing drainage crossings at the locations shown on the drawings, or as staked in the field.

1.1 PROJECT/SITE CONDITIONS

A. Requirements: Access roads shall not be constructed along fence lines and to the construction site unless written approval is granted by the Contracting Officer. Cross country travel with wheeled or tracked vehicles shall be only to and along fence lines.

2.1 MATERIALS

A. Wire Fence Materials: Shall be according to Section 02824 - Wire Fences and Gates and as shown on the drawings.

3.1 PREPARATION

A. Clearing: Only vegetation that interferes with the fence, or immediately adjacent to the fence route (restricting travel along its route) shall be removed. All debris shall be disposed of in the immediate vicinity.

3.2 INSTALLATION

A. Type A: Construct Type A drainage crossings as shown on the drawings, with an auxiliary fence of wire, rock weights, and posts constructed under and independent of the main fence, so that when the crossing washes out, the main fence will not be damaged.

A. Units: The work described in this section will be measured and paid for as part of the fence and not a separate unit.

Seven Lakes Fence 2021 FENCE-DRAINAGE CROSSINGS

02826 - 2

Fence Construction Linear Foot

END OF SECTION

Seven Lakes Fence Phase II 2023 FENCE REMOVAL

02827 - 1

SECTION 02827

FENCE REMOVAL

A. Section Includes:

1. Removing fences: 3-wire lay down fence with cedar posts.

B. Requirements: Access roads shall not be constructed along fence lines or to the jobsite unless written approval is granted by the Contracting Officer. Cross-country travel with wheeled or tracked vehicles shall be only to and along fence lines.

2.1 MATERIALS

A. Requirements: Furnish labor and materials required to remove existing barbed wire/woven wire fence, and gates.

3.1 REMOVAL

A. Removal of Fence: Remove existing fence as directed by the contractors authorized representative on the project. All materials removed from the fence shall become property of the contractor. Disposal of debris shall be according to Section 01009 –

General Information and Requirements.

A. Units: Fence removal will be measured and paid for by the linear foot removed as measured along the ground surface next to the fence prior to removal, including distance across gate openings, end, stress, and corner panels and drainage crossings.

Seven Lakes Fence Phase II 2023 FENCE REMOVAL

02827 - 2

02827(1) Fence Removal Linear Foot

END OF SECTION 02827

Seven Lakes Fence Phase II 2023 Material Specifications

Material Specifications

A. Barbed Wire: A strand of two 12-1/2-gauge galvanized wires twisted together with

2-point barbs of 14-gauge wire spaced 4-inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbed wire shall conform to ASTM A 121.

B. Barbless Wire: A strand of two 12-1/2-gauge galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbless wire shall conform to ASTM A 121.

C. Wood Stays: Straight, sound single-stem members. Shall be 42” long, 2” (milled) in diameter made from Ponderosa pine, or Lodgepole Pine. Peeled and CCA treated.

D. Steel Fence Posts: ASTM A 702; painted green with white or silver tops "T" bar type, with a welded or riveted anchor plate. Furnish with clip-type wire fasteners (punched tabs for fastening wires are not acceptable). Steel posts shall be manufactured from wrought, rail, or new billet steel, and shall have a minimum weight of 1.33 lb/ft. The anchor plates shall weigh a minimum of 0.67 pounds +5 percent, be a minimum of 18 square inches in area, and be 18-inches from the bottom of the post. The posts shall be

5.5’ in length.

E. Wood Line Posts: Straight, sound single-stem members. Shall be 72” long, 4” (milled) in diameter made from Ponderosa pine, or Lodgepole Pine. Peeled and CCA treated.

F. Wood Set Posts and Braces:

1. Acceptable Wood Posts: Sound single-stem members. A slight bend in one plane is acceptable. Posts may be full stem members, sawed members of square cross section, or split members (western red cedar only). Nominal diameter for treated posts shall be a minimum of 6-inches. The following species will be acceptable: Ponderosa pine, Lodgepole pine, fir, and tamarack. All treated posts shall be free of bark with ends cut square.

2. Basis for Rejection: Posts are not acceptable when sweep causes a straight line joining the center of the top to the center of the butt to fall outside the body of the post, or at point 2-inches or more from the center of the post. Posts that are charred, twisted, rotted, or excessively bent are not acceptable. Seasoning checks, Seven Lakes Fence Phase II 2023 Material Specifications single or opposite each other with a sum total equal to or more than 1/2 the thickness of the post is not acceptable.

3. Wood Treatment Practices: General: The following treatments may be used. Treatment method shall be in accordance with AWPA C 1.

1. Chromate Copper Arsenic Method: chromate copper arsenate, waterborne preservative (conforming to Type B in AWPA 5) shall be applied. Minimum net retention of solid preservative shall be 0.4 pounds per cubic foot (gauge only) using the full-cell pressure treatment process.

2. Assay Report: The Supplier shall furnish an assay report, for all treated wood products, from an independent testing laboratory to the Contracting Officer. A minimum of five-inch boring shall be taken from each bundle of 50 posts as samples for the assay report.

A written submittal for all materials shall be submitted for approval to COR/POC Rawlins

Wyoming BLM Field Office prior to shipping the products.

WORK DATA SHEET

For

SECTION 02824 - WIRE FENCES AND GATES

Fence type: 4-Wire Wildlife-Friendly Fence

Type of top wire: Barbed

Type of intermediate wires: Barbed

Type of bottom wire: Smooth/Barbless

Wire locations/dimensions in inches:

D: Barbed - TOP WIRE 42

C: Barbed 30

B: Barbed _24

A: Smooth_____ _18

GROUND LEVEL_________________

Ratio of wood to steel line posts: 4 steel to 1 wood (every 5th post is wood)

All Line post spacing (L): 16 ft 6 inches

Length of wood line posts (H1): 6 ft 0 inches

Depth of wood line posts in the ground (H1): 2 ft 6 inches

Type of Stays: 2.5-3” diameter x 4’ wood stays

Stay spacing (l): 16 ft. 6 inches (1 between each 16.5’ post section)

Length of wood set posts (H2): 6 ft 6 inches

Depth of wood set posts in ground (H2): 2 ft 6 inches

Length of steel posts (H3): 5 ft 6 inches

Depth of steel posts in ground (H3): 1 ft 6 inches

Number of gates: 1

Gate type: Wire

Number of mechanical gate closers: 1 each

1.SOW_7 Lakes Phase II.mvo.pdf
2. 01009 general_7 Lakes Phase II.mvo.pdf
3. 01505 Mobilization_7 Lakes Phase II.mvo.pdf
4. 02824 Wire Fence and Gates_7 Lakes Phase II.mvo.pdf
5. 02826 Fence-Drainage Crossings_7 Lakes Phase II.mvo.pdf
6. 02827 fence removal_7 Lakes Fence Phase II.mvo.pdf
7. Material Specifications_7 Lakes Fence Phase II.mvo.pdf
8. Work Data Sheet_7 Lakes Fence Phase II.wire.mvo.pdf

File details come from the government source that posted it. Updated .