This document is a Statement of Work (SOW) detailing the requirements for the installation of commercial cable television service in three buildings located on Fort Belvoir, VA. The contractor is responsible for providing all necessary materials and labor to install the service, including assembling hardware, installing software, and running cabling. The contractor must also provide training, labeling, and documentation. The period of performance for the one-year cable services contract is September 2024 through September 2025.
The related federal contract opportunity is a pre-solicitation for the Commercial Cable Television Service, solicitation number W50NH9-24-R-0035. The Department of the Army is seeking responses from interested parties by 4:00PM EST on 19 August 2024. Responses should be capability statements demonstrating the ability to provide the services outlined in the attached SOW, and should be no more than two pages in length.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement Of Work (SOW) Commercial Cable Television Service Scope The contractor is responsible for the installation of all related items and equipment required to establish cable television service in Bldg. 766, 193, and 712 located on Fort Belvoir, VA. 22060 1.Cable Television Service for Bldg. 193 2.Cable Television Service for Bldg. 712 3.Cable Television Service for Bldg. 766 4.Standard Installation Fee/Charge for Service (One-time Fee) Tasks/Requirements The contractor is required to provide all necessary materials and labor to install cable television service. This includes assembling all hardware to the existing infrastructure and installing required software. Additionally, the vendor must provide all necessary cabling for the commercial cable installation. The cable will then be connected to racks inside the facility.
The vendor will provide a Commercial Cable Service order detailing all costs and explanations. The agreement will include the following notes:
-All areas will be restored upon completion of construction if any.
-Necessary cores will be repaired upon completion of construction if any.
-Riser molding will be placed over the top of the coax to protect and conceal the cable outside if needed.
-Notice will be given if the surface of the asphalt requires disturbance to install the coax, and any necessary disturbance will be restored upon completion.
-Asphalt areas will be bored underneath and will require some Removal & Replacement of the asphalt to bring the coax across from the greenspace to the building if needed.
Plant extension may be required, and the contractor shall set up, program, and test all equipment to ensure that the cable television systems are working in accordance with industry-established guidelines. Additionally, the contractor is responsible for labeling all -Patch panels, termination hardware, cables, faceplates, and jacks. Training on customer-based equipment shall be provided to personnel, and all work shall be performed during normal working hours (0800 – 1700, Monday through Friday). The contractor is also responsible for ensuring the work area is cleaned up at the end of each workday and for providing all operating manuals in accordance with industry standards.
Delivery Schedule/Service Period of Performance All items shall be delivered within 30 days from award. Services to set up equipment, provide training, and certify the system shall be accomplished within 60 days of award. The Cable Services contract will be for one year for a Period of Performance of September 2024-September 2025.