Attachment (1)_Q and A.pdf

PDF 227 KB Posted

Attached to
Submarine Equipment Support Services in Guam
Solicitation number
N6824624Q0017
Issued by

About this file

This document contains questions and answers regarding a solicitation for submarine equipment support services in Guam. The Navy seeks a contractor to provide labor, materials, transportation, facilities, supervision and equipment to store and maintain government furnished submarine maintenance support equipment in Guam in a ready condition, including delivery, setup, onsite support and training. An amendment will remove references to man-hour deduction reports and oil filtration from the performance work statement, as those functions will no longer be responsibilities of the contractor. Equipment listed in the performance work statement tables will be modified, with some line items removed and others retained.

View the file

Other files

File Type Posted
Attachment (2)_Amend1_PWS.pdf PDF
Attachment (b)_Addendum 52.212-1.docx DOCX document
Attachment (c)_52.212-2.docx DOCX document
1.05 PWS.pdf PDF
Combined Synopsis-Solicitation N6824624Q0017.docx DOCX document
Attachment_Wage Determination 2015-5693 Rev. 19.pdf PDF
Attachment (a)_Quotation Sheet.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submarine Equipment Support Services in Guam

Notice ID N6824624Q0017

Question and Answer (Q and A)

Question 1: Previous Performance Work Statements (PWS) included Oil Filtration man-hours and Man-hours deduction report under Paragraph 3.5 Projected... Deliveries. This PWS does NOT list these items.

Yet, paragraph 3.6.1 states "If any submarine service equipment fails, Contractor SHALL provide onsite support and ANY necessary corrective maintenance to bring equipment immediately back to operation...

followed up with a man-hour deduction report..."

Without man-hours set aside, the PWS is directing action be taken without appropriate coverage. It is unclear why reference is made to a "man-hour deduction report" as the PWS is silent about man hours to set-aside. What assurances does the Contractor have to recoup additional coverage not included in the PWS?

Answer 1: An amendment will be made to the solicitation removing reference to a man-hour deduction report in paragraph 3.6.1 in the PWS.

Question 2: Table 3.2.2 Item 14 lists Parker Hannifin/CFC 200 and 2190 Oil. Previous PWS included statements about oil filtration and 2190 TEP oil under paragraph 3.6 Operations. This paragraph no longer exists. Please clarify who will filter the oil and confirm that this is no longer a Contractor function.

Answer 2: An amendment will be made to the solicitation removing line item 14 in 3.2.2 Table of Equipment in the PWS. Filtration of 2190 oil will not be a contractor function.

Question 3: What about line item 15 in 3.2.2 Table of Equipment in PWS?

Answer 3: Line item 15 in 3.2.2 Table of Equipment in PWS will remain.

Question 4: Will Paragraph 3.5 Line Item 10 in PWS be modified or deleted?

Answer 4: Line item 10 in Paragraph 3.5 in PWS will remain.