Attachment 1 - Performance Work Statement_Landscaping Services.docx
DOCX document 57 KB Posted
- Attached to
- Landscaping Services
- Solicitation number
- 1240BG24Q0062
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Performance Work Statement for landscaping services at the Pacific Southwest Research Station, USDA Institute of Forest Genetics in Placerville, CA. The purpose is to provide a professional lawn mowing service and maintain a clean roadway area free from organic debris and weeds in high-use areas. The base performance schedule includes weekly services from March through November and monthly services December through February, for a total of 39 services per calendar year. Key requirements include mowing grass to a height of 1.5 to 2.5 inches, edging driveways and curbs, removing organic debris from roadways, and maintaining a weed-free environment. The government will provide electric power and water. A site visit is scheduled for July 29, 2024, and quotes are due by August 9, 2024. The contract will have a base period with four option periods.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - IFG Landscaping Map.pdf | ||
| Attachment 3 - Wage Determination 2015-5631.txt | TXT text file | |
| Solicitation 1240BG24Q0062 - Copy.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
ATTACHMENT 1
Performance Work Statement
Contents
| Project Title | 3 |
| General Information | 3 |
| 1.0 Background and Purpose | 3 |
| 2.0 Definitions | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Deliverable / Schedule | 3 |
| 5.0 Government Furnished | 4 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 - Electronic and Information Technology Standards | 4 |
| 11.0 Performance Requirement Measures | 4 |
| Attachment | 5 |
Project Title Pacific Southwest Research Station Institute of Forest Genetics Landscape Services
General Information
1.0 Background and Purpose
Background: The Institute of Forest Genetics is a historic site. Any damage to existing features of the site while providing the service listed in this contract must be repaired and restored to its original historic condition.
Purpose: To provide a professional lawn mowing service and a clean roadway area that is free from organic debris and small weeds. To maintain areas of high use from employees, visitors, and the general public.
2.0 Definitions
High Use: All areas that are highlighted in the attachment are considered areas of high use.
Organic Debris: Leaves, Pine needles, flowers and dirt.
Professional: Working and behaving in such a way that the Contracting Officer/ Contracting Officer Representative think of them as competent, reliable and respectful.
Manicured: Neatly cut or trimmed
3.0 Technical Requirements
Contractor Requirements
Weekends and all Federal Holidays services will not be provided see Federal Holidays below:
Federal Holidays:
June 19th, 2024 July 4th, 2024 September 4th. 2024 November 10th. 2024 November 23rd.2024 December 25th. 2024 January 1st, 2025 January 15th.,2025 February 19th. 2025 May 27th.2025
Tasks: The base performance schedule includes weekly services March through November (4 times per month), and monthly services December through February (1 times per month for a total of 39 services in a calendar year). The Contractor must submit an annual schedule for services described in this Performance Work Statement for acceptance at the pre-work meeting, identifying facilities by title and approximate time services will occur. The Contractor must be allowed 30 days to adjust work schedules based on inspections. If necessary, this second work schedule must be submitted to the contracting officer/contracting officer representative for acceptance within 10 days after the first contract month period. The Contractor must not deviate from the accepted schedule without prior written approval from the contracting officer/contracting officer representative. Any permanent changes must be submitted 10 days before implementation and receive contract officer written acceptance before the Government allows the proposed changes.
Mowing. Grass must be cut according to the schedule for each month. Grass cutting on ground must be so that height of grass is between 1-1/2-inches - 2-1/2-inches. Grass clippings must be removed after each mowing.
Edging. Driveways, curbs, and other stone wall or asphalt edges located on the grounds. Areas must be edged on every lawn mowing service.
Blowing. Contractor must remove organic debris from roadways that are designated high use areas. All organic debris must be hauled to an organic debris pile located on the facility.
Weeding. Contractor must remove weeds and maintain a weed free environment at all high use areas. All chemical products must be approved by contract officer/contract officer representative before use.
4.0 Deliverable / Schedule
Key Deliverables
| Item No. |
| Deliverable |
| Objective |
| Due |
| 1 |
| Lawn mowing |
| To have a manicured lawn |
| On each servicing. |
| 2 |
| Street Cleaning |
| To have a weed and organic debris free roadway |
| On each servicing. |
5.0 Government Furnished
Insert Government Furnished Here
The Government will provide the following:
Electric Power and water at existing outlets.
6.0 Travel
Identify any travel requirements, locations involved, number of trips (if known), and duration of anticipated travel. Specify
7.0 Contractor’s Key Personnel
The work shall be supervised by a foreman who shall be available in person at the job site with a copy or knowledge of the work plan and specifications for verbal discussions about the conduct of the work with the COR.
8.0 Security Requirements
The government will give the contractor a code for gates to enter the facility. That number should not be given out to anyone other than the employees working for the contractor.
9.0 Data Rights
Insert Data Rights Here
10.0 Section 508 - Electronic and Information Technology Standards Insert Section 508 Here
11.0 Performance Requirement Measures
| Performance Objective |
| Required Task or Deliverable |
| Performance Standard |
| Method of Surveillance |
| Positive/Negative Incentive |
% for NOT meeting the Task
| To have a manicured lawn and an organic debris/ weed free roadway. |
| Mow lawn area, remove organic debris and weeds, along designated high use areas. |
| No more than three complaints in a given month for the same issue. |
| (COR) will perform a visual inspection |
| +/- 1% of total monthly price for each variance of +/- 1% variance from standard. |
Insert Performance Requirement Measures Here
Attachment If applicable, include an Attachment stating Evaluation Factors and significant Subfactors representing the key areas of importance and emphasis to be considered in the source selection decision.