Attachment 1 MOVERS Governance and Replan.pptx
PPTX presentation 3 MB Posted
- Solicitation number
- 300000263931333
- Issued by
- Missouri
About this file
This governance and project planning document outlines the MOVERS (a financial and human capital management system) implementation structure and phased rollout schedule for a state or government entity. The document establishes three governance bodies: an Oversight Committee responsible for executive oversight and strategic direction; a Change Control Board that approves material changes to program baseline elements including scope, schedule, budget, and delivery; and a Program Team managing day-to-day project activities, stakeholder management, and resource allocation. The implementation follows a four-release schedule spanning calendar years 2026 through 2028, with Release 1 (Recruit and Core HR functionality) scheduled to go live on March 1, 2027; Release 2 (comprehensive ERP modules including General Ledger, Fixed Assets, Accounts Payable/Receivable, Inventory, Purchasing, Budget Control, and Manufacturing) on July 1, 2027; Release 3 (HCM functions including Payroll, Time & Labor, Compensation, Benefits, and Talent Management) on January 1, 2028; and Release 4 (Narrative Reporting and 1099 functionality) also on January 1, 2028.
The governance framework establishes escalation thresholds with approximately 75 percent of decisions handled at the operational level, 20 percent at the tactical level, and 5 percent at the strategic level. Following the post-implementation support period for each release, the project transitions to ongoing Maintenance & Operations support, which includes JIRA and ServiceNow ticket triage, quarterly and monthly updates, and Oracle service request management. The document references a pending Proof of Concept approval for a MoBGT restructuring initiative and notes the implementation of a custom solution to synchronize balances between MOVERS and SAMII systems. Planning and Budgeting, Solicitation, and Learn modules will continue operating in the MOVERS production environment throughout the implementation timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4 - SOW Requirements.docx | DOCX document | |
| Attachment 3 SOW Project Management.pdf | ||
| Attachment 2 SOW Secondary IV&V.pdf | ||
| MOVERS IVV RFP.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Governance Structure Overview
Governance Chart Oversight Committee Deliver executive oversight, establish strategic direction, and champion the project Resolve high-impact issues Approve key project milestones and changes Ensure resource commitment Change Control Board Approve material changes to the program baseline (scope, schedule, budget, delivery) Provide recommendations to Oversight Committee for strategic decisions Program Team Oversees day-to-day project activities including managing scope, schedule, budget Manage stakeholders and project resources Escalate issues as needed
Governance Escalation Thresholds
Strategic ~5% of decisions Tactical ~20% of decisions Operational ~75% of decisions
RePlan Schedule
| CY2026 | CY2027 | CY2028 | ||
| FY26 | FY27 | FY28 |
Release 2 (ERP): GL, Fixed Assets, AP, AR, Inventory, Costing, Purchasing, Budget Ctrl, Expenses, Manufacturing, Order Management, Cash Mgmt. Reporting, PPM COA, Leasing, PPM, Custom solution to keep balances in sync between MOVERS and SAMII (FCCS or Acct Hub), MoBGT Restructure (Pending Proof of Concept Approval)
Release 3 (HCM): Payroll, Time & Labor, Comp, Benefits, Absence Mgmt, Talent, Employee Self-Service, Remaining Core HR, Knowledge Center
Release 1: Recruit, Core HR, EDMCS
Release 4: Narrative Reporting (ACFR), 1099
Go Live March 1, 2027
Go Live July 1, 2027
Go Live January 1, 2028
Go Live January 1, 2028
Maintenance & Operations (M&O) Ongoing support for Planning & Budgeting, Solicitation, Learn (MOVERS Production) including JIRA/ServiceNow Ticket Triage, Quarterly/Monthly Updates & Oracle SR Triage. Will begin for each release following the post go-live support period.