Attachment 1 - IHS Dark Fiber Lease Specification Statement-FINAL(red betaSAM).pdf

PDF 220 KB Posted

Attached to
IHS OIT Single Mode Fiber (SMF-28) Federal contract opportunity
Solicitation number
IHS-OIT-06302020
Issued by
Department of Health and Human Services Indian Health Service

View the file

Other files for this federal contract opportunity

Other files attached to IHS OIT Single Mode Fiber (SMF-28), newest first.
File Type Posted
Attachment 2 - MRAS Sources_Sought for IHS Dark Fiber Pair- FINAL (betaSAM).doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work for

Dark Fiber connections for IHS in Rockville Maryland

1. BACKGROUND

The mission of the Indian Health Service (IHS), Office of Information Technology (OIT) is to provide a highly reliable and efficient health information system to support the delivery of health care to the American Indian and Alaska Natives that IHS serves.

All information technology (IT) infrastructure for the IHS in Rockville MD is located at the headquarters facility data center located on the 3rd floor at 5600 Fishers Lane, Rockville MD 20857. Legal support for the mission is provided by the Office of General Council (OGC) staff located on the 3rd floor at 12501 Ardennes Ave, Rockville MD 20850. The Indian Health Service requires a point-to-point fiber pair between these two locations to facilitate OGC staff IT connectivity to all HHS and IHS information technology resources and services. Existing connectivity currently interfaces with IHS managed switches at both locations.

2. SCOPE

The Contractor shall provide only certified fiber optic technicians to install a dedicated dark fiber pair of Single Mode Fiber (SMF-28) between the 3rd floor network closet located at 12501 Ardennes Ave, Rockville MD and the IHS data center located on the 3rd floor room 3E-03 at 5600 Fishers Lane, Rockville MD. The handoff must be provided in a fiber distribution panel that meets EIA/TIA 568A standard Subscriber Connector (SC) at both locations. This fiber is noted as dark fiber because it will be lighted with existing IHS equipment and SC patch cables at both locations. The contractor must provide a test report to indicate the fiber optics are installed to industry standards.

Connectivity is required on or before August 31, 2020.

3. OBJECTIVE

The objective of this procurement is to lease fiber connectivity between the IHS data center and the IHS OGC staff location for compute and data connectivity. This fiber is described as dark fiber because it will be lit using existing IHS equipment and SC patch cables at both locations.

4. SPECIFIC REQUIREMENTS

Single Mode Fiber pair (SMF-28) between the 3rd floor network closet located at the 12000 block of Ardennes Ave, Rockville MD and the IHS data center located on the 3rd floor room 3E-03 at 5600 block of Fishers Lane, Rockville MD. The door-to-door proximities between both of the point-to-point installation/service locations are roughly estimated to be 2400 ft/.05 miles in proximity. The fiber pair handoff shall be delivered via a rack mounted fiber distribution panel that meets EIA/TIA 568A standard Subscriber Connector (SC) at both locations.

5. DELIVERABLES

The contractor shall provide the following deliverables:

Item Deliverable Name Due Date

1 Quantity 2 SMF-28 fibers between two IHS locations at demarcation points noted above with SC connection handoff in rack mounted fiber panels

NLT August 31, 2020

2 Test Report Due to COR Immediately upon installation and conducting technical testing 3 Invoice of leased fiber pair Monthly

6. PERIOD OF PERFORMANCE

The base year period of performance for this contract shall be one year from the award date plus

(3) 12-month option years.

BASE Year - Services Base Year

Unit Quantity Unit Price Amount

1. Dark Fiber Pair MO 12

Services

OPTION YEAR 1 - Services Option Year 1

Unit Quantity Unit Price Amount

OPTION YEAR 2 - Services Option Year 2

Unit Quantity Unit Price Amount

Total Estimated Contract Value Base + 2 options

7. DELIVERY INSTRUCTIONS

To ensure no loss of OGC staff connectivity, contract deliverables shall be delivered between both locations identified above and confirmed by the agency technical point of contact, TBD on or before August 28, 2020.

2. SCOPE
3. OBJECTIVE
4. SPECIFIC REQUIREMENTS
5. DELIVERABLES
6. PERIOD OF PERFORMANCE
7. DELIVERY INSTRUCTIONS