This purchase description outlines requirements for a bulk gas system for Building 230 at Rock Island Arsenal. The project requires installing piping in preparation for moving bulk gas service and multiple lasers, including relocating a large 9,000 gallon bulk tank to the building courtyard. Phase 1 involves utilizing existing piping for oxygen and nitrogen supply, installing approximately 450 feet of new oxygen pipework with drops and connections, and fitting ball valves at each drop. The contractor must inspect the site, address any issues with the proposed location, and comply with various safety, security and environmental standards as specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENAL RIPD: E4000-18-1-16

PURCHASE DESCRIPTION DATE: 16-Feb-2021

BULK GAS SYSTEM FOR B230

GENERAL SYSTEM DESCRIPTION

1. STANDARDS AND PUBLICATIONS

1.1 Clarification

1.2 National Standards and Specifications

2. DESIGN

2.1 General Design Standards

2.2 Safety, Security and Environmental

2.3 Responsibilities

3. COMPONENT SPECIFICATION

3.1 Dimensions:

3.2 Current System Design

3.3 Phase 1

3.4 Phase 2

4. APPROVAL/SHIPPING

4.1 Shipping

4.2 Installation

4.3 Completion

5. SERVICE

5.1 Service/Support Requirements

GENERAL SYSTEM DESCRIPTION

This project requires the contractor to install piping in Bldg. 230 in preparation for the movement of bulk gas service and installation of multiple lasers. This will include the installation of the piping as well as modification of the piping to utilize multiple bulk storage tanks. This shall be a phased installation with the eventual relocation of a large 9,000 gallon bulk tank to the courtyard of Bldg. 230.

1. STANDARDS AND PUBLICATIONS

1.1 Clarification

Any ambiguities, questions, requests for clarification or discrepancies between sections of this purchase description, drawings, national or industry standards discovered by the contractor in reviewing this purchase description shall be reported by the bidder in writing to the contracting officer BEFORE THE DATE SCHEDULED FOR CLOSE OF BIDDING/receipt of proposal.

Submission of a proposal or bid shall be construed as evidence that such examination has been made. Therefore, later claims for labor, material, or equipment required, or for difficulties encountered, which could have been foreseen had such reasonable examination been made, may be denied.

1.2 National Standards and Specifications

The following specifications in effect on the Date of Invitation for Bid/Request for Proposal form a part of this purchase description. In the case of conflicting requirements, the more stringent shall apply.

1.2.1 Occupational Safety and Health Act of 1970 (OSHA).

1.2.2 American Society of Testing and Materials (ASTM).

1.2.3 American Society of Mechanical Engineers (ASME).

1.2.4 American National Standards Institute (ANSI).

1.2.5 National Electrical Manufacturers Association Standards (NEMA).

1.2.6 Electronic Industries Association (EIA).

1.2.7 Institute of Electrical and Electronics Engineers (IEEE).

1.2.8 American Welding Society (AWS).

1.2.9 National Fire Protection Association (NFPA).

1.2.9.1 NFPA-70 National Electrical Code

1.2.9.2 NFPA-79 Electrical Standard for Industrial Machinery.

2. DESIGN

2.1 General Design Standards

2.1.1 DEVIATION FROM PRODUCT: Modifications to the manufacturer’s standard design to achieve requirements as specified in this document are only permissible as dictated by good design practice. For example, mounting a 20-hp motor in a power train designed and normally using a 10-hp motor would not be acceptable.

2.1.2 UNITS OF MEASURE: Dimensions and capacities in this purchase description are given in the English-US (in-lb) system. All dials, gauges, and drawings shall be in the English-

US system or both the English-US and the metric systems, unless otherwise specified in this document.

2.1.3 ID DATA PLATE: The equipment shall include a main data plate which will include the following data as a minimum requirement (additional information is acceptable):

Manufacturer Name, Manufacturer’s Dunns and Bradstreet Number, Manufacturer’s Model

Number, Manufacturer’s Serial Number, Year of Manufacture, Contract Number, Machine

Weight. This information is necessary for compliance with the governments Unique

Identification Program (UID).

2.1.4 DATA PLATES: All instruction, data, and identification plates and labels attached to this equipment and its controls shall be manufactured of corrosion and oil resistant metal or plastic material. All wording shall be in the English language using plain, bold face lettering.

Lettering shall be permanent and have a contrasting background.

2.1.5 ITEM UNIQUE IDENTIFICATION (IUID) REGISTRATION: The contractor shall register the equipment in the IUID Registry (as one single system). IUID registration requires the contractor to input Cage Code, Model Number, and Serial Number into a Government

Database to allow for asset and inventory tracking. IUID Registry of the equipment shall be performed at http://dodprocurementtoolbox.com/site/uidregistry/. Training for IUID is available in https://wawftraining.eb.mil. IUID registration of this equipment is required prior to final payment in the Wide Area Work Flow (WAWF). The contractor shall also affix a machine readable 2-dimensional (2-D) matrix representing the IUID registry to the machine. The IUID

2-D matrix may be included on the ID Data Plate outlined in paragraph 3.2.4.

2.1.6 UTILITY CONNECTION: Equipment supplied to the Rock Island Arsenal will have single point shut-off for each utility supplied to a system. This means that equipment constituting a single system shall be wired to a single main electrical disconnect point, plumbed to a single pneumatic shut-off valve, etc… This will be referred to as the “point of first connection”. Each type of power source may have only one point of first connection. E.g. (1) pneumatic shut-off valve, (1) water supply shut-off valve, (1) electrical disconnect, etc… Each point of first connection shall be clearly labeled on the system and shown in the safety lockout portion of the documentation package. These points must be located on a stationary component and positioned such that they will not create a hazard to personnel during normal operation of the system. The first connection points shall be accessible from the shop floor without the use of ladders, steps, or stools. Access cannot be hampered by operation of the system.

2.1.7 UTILITY CONNECTION LABOR: Rock Island Arsenal shall provide only such labor and materials as will be needed to connect facility utilities to each point of first connection of the system. The supplier will be responsible for all connections beyond the point of first connection for each utility.

2.1.8 UTILITIES AVAILABLE: Rock Island Arsenal shall be responsible for providing the following:

2.1.8.1 Connection of 460-V, 60-Hz, 3-Ph AC electrical power to the fused or breaker type disconnect switch required in the ELECTRICAL DISCONNECT paragraph of this purchase http://dodprocurementtoolbox.com/site/uidregistry/ https://wawftraining.eb.mil/ description. Connection does not include filters, surge protection, or any peripheral equipment necessary to make the equipment functional.

2.1.8.2 Connection of approximately 80-psi compressed air to a single point for each system, if needed. Connection does not include filters, dryers, or any peripheral equipment necessary to make the equipment functional.

2.1.8.3 Connection of 1.5-in diameter natural gas pipe to a single point for each system, if needed. Connection does not include filters or any peripheral equipment necessary to make the equipment functional.

2.1.8.4 If, due to contractor caused problems, the equipment or components of the equipment must be moved or removed and replaced, by RIA after initial placement, the contractor shall be billed for such work at current RIA labor and overhead rates.

2.1.9 COMPONENT ENVIRONMENT: Under no circumstances shall a component be used in an application not recommended by the component manufacturer. Components shall not be subjected to conditions of operation beyond the recommendations of the manufacturer, such as excessive heat, lack of lubrication, over-loading.

2.1.10 REPLACEMENT COMPONENTS: All replaceable components shall be manufactured to definite standards for tolerance, clearance, and finish, enabling components to be field installed without further machining.

2.1.11 FILTRATION/REGULATION: Equipment requiring filtered or regulated energy sources shall be supplied with the components necessary to perform this function. E.g. the equipment shall be supplied with a Filter, Regulator, Lubricator (FRL) device, if filtered, lubricated, regulated pressurized air is required for the efficient, proper operation of the equipment. These devices shall be located on the equipment side of the lockout devices at the points of first connections.

2.1.12 DIALS AND GAUGES: All scales, dials, and gauges shall be manufactured of corrosion and oil resistant material. All wording shall be in the English language using plain, bold face lettering. Lettering shall be permanent and have a contrasting background.

2.1.13 HANDWHEELS: Hand-wheels turned in a clockwise rotation shall produce a linear motion, of the controlled component, to the right, away, or upwards. If rotary motion is produced by the hand-wheel, clockwise rotation of the hand-wheel shall produce clockwise movement of the controlled component.

2.1.14 CONTROL LEVERS: Control levers shall move in the same direction as the motion of the controlled component.

2.2 Safety, Security and Environmental

2.2.1 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safeguards, various precautions, and plant protection measures. All of the below requirements will be necessary of contractors visiting RIA to satisfy requirements of this purchase description; Additional requirements will be placed on contractors requiring access to the Army

Network, or Common Access Card (CAC), as specifically detailed below. At all times during the execution of this work, contractor personnel will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the island.

2.2.1.1 Access and General Protection/Security Policy and Procedures: The contractor and any associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Director of Emergency Services. All contractor employees must comply with all personal identity verification requirements (IAW FAR clause 52.204-9) as directed by

Department of Defense (DoD), Headquarters Department of the Army (HQDA), and any local policy. If the Force Protection Condition (FPCON) changes, the Government may require changes in contractor installation access, security matters, or security processes.

2.2.1.1.1 Access to RIA: Contractor and all subcontractor employees performing work at

RIA shall comply with adjudication standards and procedures using the National Crime

Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening

Database (TSDB) and any applicable installation, facility access screening and local security policies and procedures. The COR shall provide guidance to complete the

Access Control Records Check request Form though the Rock Island Arsenal Directorate of Emergency Services.

2.2.1.1.2 Random Antiterrorist Measures Program (RAMP) participation: Contractor personnel are subject to RAMP security program (i.e. vehicle searches, wearing of ID badges, etc.). Contractor shall comply with any, and all instructions issued by the Rock

Island Arsenal Police Department. The RAMP is discussed in the RIA-JMTC Anti-

Terrorism Training.

2.2.1.1.3 During FPCONs levels of Charlie or Delta, services may be discontinued/postponed due to a higher National or local security threat. Services will resume when FPCON Level is reduced to Bravo, or lower. FPCON levels are described in Anti-Terrorism Level I Training.

2.2.1.1.4 Contractor personnel shall return all Installation Badges and access passes as soon as possible prior to contract completion. RIA-JMTC electronic keys and access passes are accountable items, shad shall be returned within 24-hours of no longer being needed. Items will be returned to the COR, or paced in a drop box at a RIA-JMTC access point.

2.2.1.2 Security Training: The contractor shall complete the following training:

2.2.1.2.1 Anti-Terrorism, Level I: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete Anti-Terrorism (AT) Level I Awareness training. The COR will be provided a copy of the Rock Island Arsenal –Joint Manufacturing and Technology Center

(RIA-JMTC) AT Level I Awareness Training and assure that the training is complete.

The contractor shall sign a memorandum of record for each contractor employees and subcontractor employee to the RIA-JMTC Operations Center prior issuing any electronic keys, or access pass being authorized.

2.2.1.2.2 iWatch (See Something, Say Something) Training: The Contractor and all associated subcontractors shall complete iWatch Training. iWatch Training shall be provided during the Anti-Terrorism Training.

2.2.2 FEDERAL MARIJUANA LAWS REMAIN UNCHANGED: Note: Rock Island

Arsenal is under the exclusive federal jurisdiction of the United States. Under federal law, marijuana is still defined as a Schedule I drug, and possession and use of marijuana is still illegal. Any person using or in possession of marijuana on Rock Island Arsenal may be criminally prosecuted in federal district court. In addition, such individuals may be permanently barred from entering Rock Island Arsenal.

2.2.3 REAL ID: Starting 01-Oct-2021 all personnel entering Rock Island Arsenal will be required to show a Real ID form of identification.

2.2.4 FIRE PREVENTION AND PROTECTION: The contractor shall comply with all fire prevention measures prescribed in the installation Fire Regulations, a copy of which is on file in the office of the Contracting Officer. A written fire permit shall be obtained from the installation

Fire Marshall for use of open flame devices, such as torches, portable furnaces, tar kettles, or gas and electric welding and cutting equipment, in, on, or within 15-ft of the building. The contractor shall be liable for any fire loss to the Government properly attributable to negligence on the part of the contractor, including failure to comp1y with fire prevention measure described by the terms of this purchase description.

2.2.5 INDUSTRY AND REGULATIONS: The equipment shall comply with the most current of all local, state, and federal laws and regulations listed in Standards and Publications.

2.2.6 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl

(PCB), ozone depleting substances (Class I or Class II), or asbestos materials.

2.2.7 SAFETY REGULATION COMPLIANCE: The contractor shall comply with standard

OSHA and RIA safety standards, including conforming to confined space work requirements when applicable.

2.2.8 SAFETY LOCKOUTS: Each point of first connection shall be designed and constructed to allow the utility to be completely isolated from the equipment. This isolation shall be insured by application of a standard key locking padlock. The device(s) shall only be lockable in the de-energized (OFF) condition.

2.2.9 LOSS OF PRESSURE: Hydraulic and pneumatic circuits shall be designed such that loss of pressure, or pressure surges, shall not cause a hazard. Means shall be provided to prevent operation of the equipment with insufficient pressure, if such operation could cause a hazard.

2.2.10 TRAPPED ENERGY: Means shall be provided for the controlled release of stored energy. This energy may be in the form of, but not limited to, air and hydraulic pressure accumulators, capacitors, springs, counter balances and flywheels. When appropriate, a label shall be affixed to the stored energy source to identify the hazard.

2.2.11 WORKING RANGE: Hydraulic and pneumatic components shall be selected, which cannot be adjusted outside the safe working range of the circuit and/or equipment.

2.2.12 ACCUMULATORS: Gas charged accumulators operating above 200-psi charging pressure shall be charged with inert gas.

2.2.13 EMERGENCY STOP: The system will incorporate a clearly identified, red, mushroomed, control button with a yellow backing plate at every operator work station. Upon momentary operation, any emergency stop button shall de-energize all machine motions and override all other controls without creating additional hazards. All motion stopped shall be restarted by the deliberate action of the operator (requiring manual reset). No other red mushroomed buttons shall be allowed on the equipment. It is preferred that there is no other red buttons of any type.

2.3 Responsibilities

2.3.1 SITE INSPECTION: A site inspection must be performed prior to bidding. It is not possible to responsibly bid on this turn-key project without first examining the existing equipment and determining the existence of other potential obstacles. All site inspections and/or measurements, which must be taken in order to determine the suitability of the proposed location or to perform the design of the system, are the sole responsibility of the contractor.

Rock Island Arsenal will support this function through the POC (point of contact) by guiding personnel, facilitating security registration, and providing general assistance. The contractor will be responsible for providing any and all equipment necessary for this process.

2.3.2 SITE CONDITIONS: Rock Island Arsenal will be responsible for additional costs incurred by unforeseen, but controllable manmade issues with the location of the system.

Examples would include, but are not limited to, buried sewer lines, standing water, and so forth.

The contractor will be responsible for all costs associated with correcting foreseeable conditions, including but not limited to low hanging electrical lines which are clearly visible, encountering rock during excavation, inclement weather, interference with established machines or structures by components not shown on the footprint drawing, etc.

3. COMPONENT SPECIFICATION

Equipment: The supplier shall furnish all equipment normally considered by him to be standard for his machine unless identified in this requirement to be of specific manufacture. The following equipment shall be provided in addition to the equipment specified in other sections of this purchase description, which may not be standard. The inclusion of standard equipment in this paragraph is inadvertent and should not be construed to allow duplication.

3.1 Dimensions:

3.1.1 DOOR ACCESS: The equipment shall be shipped either assembled or disassembled to pass through a door 12-ft wide by 12-ft high, and shall not exceed 25-ft in length.

3.1.2 COMPONENT WEIGHT: The maximum weight of any one piece shall not exceed

25,000-lbs.

3.2 Current System Design

RIA-JMTC utilizes bulk gasses throughout the facility. The equipment described in this purchase description consists of the current Nitrogen and Oxygen supply in BLDG. 230 as well as a 6000 gallon bulk tank and trifecta that is currently being utilized in Bldg. 212. RIA-JMTC is in the process of relocating equipment and in doing so, will be removing weld operations from B230. As well as moving laser operations into the building. The current system in place does not allow for efficient supply of Oxygen and Nitrogen to the lasers being installed/ relocated. This project aims to move/ utilize onsite equipment where possible to provide bulk gasses for the laser operations moving into BLDG. 230. This will be a phased installation as some components cannot be completed until outside constraints are met.

3.3 Phase 1

3.3.1 PRE-EXISTING LOOP FOR OXYGEN: The contractor shall use the existing 0.75”

Argon/Oxygen shielding gas piping to service Oxygen supply to the lasers being installed.

There are already drops in place on this loop. This is dependent on the removal of the weld operation from BLDG. 230. It is the responsibility of the contractor to perform any necessary purging or cleaning of this line to prepare for service switchover.

3.3.2 PRE-EXISTING LOOP FOR NITROGEN: The contractor shall use the existing 0.75”

Argon/Helium shielding gas piping to service Nitrogen supply to the lasers being installed.

There are already drops in place on this loop. This is dependent on the removal of the weld operation from BLDG. 230. It is the responsibility of the contractor to perform any necessary purging or cleaning of this line to prepare for service switchover.

3.3.3 NEW OXYGEN PIPEWORK: In addition to utilizing the already existing piping loop, the contractor shall also install piping down the center columns of the building. This equates to approximately 450 ft. of pipe. The contractor shall be responsible for providing drops on the columns as well as connecting the newly installed pipe to the current loop and supply equipment. The inclusion of drops and supply line implementation equates to approximately

450 ft. of additional piping. It is the responsibility of the contractor to determine the accurate amount of piping needed to create a fully functioning system.

3.3.3.1 Piping shall be 0.75” Cu type “K” cleaned for Oxygen service and capped. “K” represents the tubing code for the copper tubing which signifies the thicker wall of tubing.

3.3.3.2 Ball Valves shall be installed at each drop. Ball valves shall have <0.5 dP at maximum flow. They shall be ¼ turn off ball valves of either brass, bronze, or stainless steel constructions and shall include copper tube extensions provided by the manufacturer. The ball valves shall permit in-line serviceability.

3.3.4 NEW NITROGEN PIPEWORK: In addition to utilizing the already existing piping loop, the contractor shall also install piping down the center columns of the building. This equates to approximately 450 ft. of pipe. The contractor shall be responsible for providing drops on the columns as well as connecting the newly installed pipe to the current loop and supply equipment. The inclusion of drops and supply line implementation equates to approximately

450 ft. of additional piping. It is the responsibility of the contractor to determine the accurate amount of piping needed to create a fully functioning system.

3.3.4.1 Piping shall be 0.75” Cu type “K” cleaned for nitrogen service and capped. “K” represents the tubing code for the copper tubing which signifies the thicker wall of tubing.

3.3.4.2 Ball Valves shall be installed at each drop. Ball valves shall have <0.5 dP at maximum flow. They shall be ¼ turn off ball valves of either brass, bronze, or stainless steel constructions and shall include copper tube extensions provided by the manufacturer. The ball valves shall permit in-line serviceability.

3.3.4.3 The contractor shall provide accumulators where needed to reduce pressure drop to ensure appropriate inlet pressures to the lasers.

3.3.5 FILTERS: The Oxygen and Nitrogen services supplied to the laser inlets must include filter assemblies made up of a pre-filter and a final filter. These filter assemblies must be included on every drop for the lasers.

3.3.5.1 Oxygen Filter: The pre-filter and final filter shall be the same filter installed in series to minimize any potential particulate contamination

3.3.5.1.1 Filter shall have a .01 micron filter element with a minimum of 99.97% efficiency

3.3.5.1.2 Filter assembly inlet and outlet shall be 0.75”

3.3.5.1.3 Filter assembly shall have a maximum allowable working pressure of 500 psig

3.3.5.1.4 Filter and housing must be cleaned for Oxygen and suitable for Oxygen service.

3.3.5.1.5 Flowrate capability shall be 600 scfh or 10 scfm

3.3.5.1.6 Location of the filter assembly must be located near the laser inlet.

3.3.5.2 Nitrogen Filter: The pre-filter and final filter shall be the same filter installed in series to minimize any potential particulate contamination

3.3.5.2.1 Filter shall have a .01 micron filter element with a minimum of 99.97% efficiency

3.3.5.2.2 Filter assembly inlet and outlet shall be 0.75”

3.3.5.2.3 Filter assembly shall have a maximum allowable working pressure of 500 psig

3.3.5.2.4 Filter and housing must be cleaned for Nitrogen and suitable for Nitrogen service.

3.3.5.2.5 Flowrate capability shall be 6000 scfh or 100 scfm

3.3.5.2.6 Location of the filter assembly must be located near the laser inlet.

3.3.6 LOCATION: The location of the trunk line installation can be seen in Figure 1

Figure 1: B230 With Trunk Lines and Equipment Relocation

3.3.7 GAS SYSTEM REDUNDANT CONNECTION: The piping system shall be connected with valves that shall allow for use of both 3000 gallon nitrogen bulk tanks located on the west side of Bldg. 230 as well as the east courtyard. They shall be set up in a way that allows for the use of both systems as well as shutting off service from one bulk tank in the event of maintenance or service on one of the 3000 gallon tanks.

3.3.8 GAS REQUIREMENTS: The system shall be designed to provide 435 psig at the inlet of the building with a capability of a maximum flow rate of 9522 scfh. The maximum pressure drop shall be less than 11 psi.

3.4 Phase 2

Phase 2 involves the relocation of equipment that currently services BLDG. 212. The equipment cannot be relocated until all of the lasers have been moved from BLDG 212 and are being serviced by the current (2) 3000 gallon Nitrogen bulk tanks and (1) Oxygen bulk tank currently located at Bldg. 230. The reason for this is that the equipment servicing BLDG. 212 cannot be removed until all of the lasers consuming Nitrogen have left the building. Downtime for production must be kept to a minimum.

3.4.1 TRIFECTA CONVERSION: After all of the lasers have been relocated from BLDG

212, the Nitrogen Trifecta currently servicing the building shall be upgraded to a 600 psig model prior to being installed for service in BLDG. 230. The current set-up for the trifecta is for

500 psig. The trifecta is a Chart 2014 15K X Series with SN# 2394CX. The following components shall be installed to change the service from 500 to 600 psig. All labor and system components to ensure service changeover are the responsibility of the contractor. This may include wiring of the control box, transmitters, valves, and plumbing of all system components.

3.4.1.1 Trifecta Cans: The (2) trifecta cans shall be replaced with 600 psi cans. CHART P/N

20549351RPL or equivalent. This is to allow the trifecta to handle the higher pressure requirement.

3.4.1.2 Bypass Valves: The contractor shall install (5) Magnatrol MOE2962SC-

ACTZCYEXGRZP-01 or equivalent. These valves are used as a bypass.

3.4.1.3 Connectors: The contractor shall replace (8) Swagelock connectors P/N SS-810-1-8 or equivalent. To be considered equivalent means the connector must be a stainless steel male connector tube fitting ½ in. Tube OD x ½ in. Male NPT with no bulkhead.

3.4.1.4 The contractor shall replace (4) safeties with 600 psi ½” equivalents. Chart P/N

20547372 or equivalent. To be equivalent means that the relief valves must be Brass ASME

½ in. MPT 600psi relief valves.

3.4.1.5 Burst Discs: The contractor shall replace four (4) 800psi burst discs with Chart P/N:

20547371 or equivalent. To be considered equivalent means the burst discs must be rated for

800 psi and be composed of a brass body and inline 316SS Disc ½” MPT ASME.

3.4.1.6 Dial Gauge: The contractor shall install two (2) 2 in. dial gauges rated for 0-800 psi/bar. Chart P/N: 14954366 or equivalent. To be considered equivalent means that the dial gauge shall be ¼” NPT CBM PSI outer scale in black with a bar inner scale in red. The case material shall be brass with a polycarbonate window.

3.4.1.7 Control Box: The contractor shall install a control box onto the trifecta that is programmed for 600 psi service. Chart P/N: 21088438 or equivalent. To be considered equivalent means that the control box must be compatible with this make and model of trifecta as well as have the correct programming interface with programming in place to handle 600 psi service.

3.4.1.8 Muffler: The contractor shall install two (2) Mufflers on the trifecta. Chart P/N:

11731685 or equivalent. To be considered equivalent means the mufflers shall be ½” MPT

600 psi mufflers.

3.4.1.9 Diff Transmitter: The contractor shall install two (2) Differential Transmitters Chart

P/N: 13963691 or equivalent. To be equivalent means they must be compatible with the make and model of CHART Trifecta and be rated for 600 psi service.

3.4.1.10 Liquid Level Transmitter: The contractor shall install two (2) liquid level transmitters. Chart P/N: 20547373 or equivalent. To be considered equivalent means that the transmitters must be compatible with the make and model of CHART Trifecta and be rated for 600 psi service.

3.4.1.11 PLC: Within the Control Box, the contractor shall install a PLC programmed for

600 psi service. Chart P/N: 21323462. This component must be compatible with the make and model of CHART Trifecta as well as the control box that is being installed on the unit.

3.4.1.12 Check Valves: The contractor shall replace the eleven (11) check valves on the trifecta. Chart P/N: 13620233 or equivalent. To be considered equivalent means that the check valves must be brass ½” FPT x ½” FPT with a crack pressure of .5-1 psi.

3.4.1.13 5 psi Check Valve: The contractor shall replace the three (3) 5 psi check valves with Chart P/N: 11051090 or equivalent. To be considered equivalent means that the check valves must be brass ½’ FPT x ½” FPT 1000psi rated with 5psi crack pressure.

3.4.1.14 Economizer Regulators: The contractor shall replace the two (2) 525 economizer regulators with Chart P/N: 13774101 or equivalent. To be considered equivalent means that the regulators shall be ¼” NPT 525 psi FRM regulators.

3.4.1.15 Analog Cycle Counter: The contractor shall install a cycle counter Chart P/N:

21495759 or equivalent. To be considered equivalent means that the counter must be compatible with the X-series CHART trifecta.

3.4.1.16 Cryo Valve: The contractor shall replace the six (6) cryo valves with Equigas P/N

BK 9454 or equivalent. To be considered equivalent means that the cryo valves must be ½” extended stem cryo valves cleaned and rated for service on this model of CHART trifecta.

3.4.2 6000 GALLON TANK RELOCATION: Once the lasers have been relocated to Bldg.

230, the relocation of the 6000 gallon bulk tank (RIA34222) and its auxiliary equipment can take place. The auxiliary equipment includes the rehabbed trifecta, two (2) 15,000 scfh vaporizers VAP-AMP-15K FG02044 installed in series, and all final line gas regulation assemblies rated 200-600 psig with bypass. All piping, safeties, pressure relief valves, and components to connect liquid line from bulk vessel to trifecta, liquid lines to connect trifecta to vaporizers and then the gas line to connect to piping network shall be included and shall be the responsibility of the contractor.

3.4.2.1 The service in this system shall be designed so that the larger tank is supplying most of the service requirement.

3.4.3 ELECTRIC PRESSURE BUILDING VAPORIZER: The contractor shall install an electric pressure building vaporizer with a bypass so that the existing Trifecta ambient pressure building vaporizers can be utilized in the event that the electric pressure building vaporizer needs to be serviced.

3.4.4 CONCRETE: The contractor shall provide a concrete pad in the east courtyard of Bldg.

230 with the capabilities to hold an 11,000 gallon bulk gas tank. It is the responsibility of the contractor to determine specifications for this concrete pad and placement in the courtyard that does not impede current operations at RIA-JMTC or filling operations performed on the bulk gas systems currently in place. If necessary, this pad can be utilized for the 6000 gallon tank to sit after relocation.

3.4.5 FENCING: The contractor shall provide and install appropriate fencing where needed to ensure proper enclosure of the relocated system. This fencing shall not impede current operations or hinder the ability to have the bulk system refilled.

3.4.6 3000 GALLON NITROGEN TANK DISCONNECT: The 3000 gallon nitrogen tank currently connected on the west side of Bldg. 230 shall be disconnected from service.

3.4.7 ARGON TANK DISCONNECT: The Argon bulk tank in the courtyard of Bldg. 230 shall be disconnected from service and moved. This space can be used for the placement of the auxiliary equipment associated with the 6000 gallon bulk nitrogen tank.

4. APPROVAL/SHIPPING

4.1 Shipping

4.1.1 RESPONSIBILITY: The contractor is responsible for delivery of the equipment to the

Rock Island Arsenal. Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.

4.1.2 SHIPPING SCHEDULE: Be aware, the Rock Island Arsenal will only off-load equipment arriving between 6:00 am and 12:00 am (noon), local time on Mondays through

Thursdays except holidays. For information concerning holidays, the contractor should consult the contracting officer. There is no place to stage transporting vehicles awaiting the arrival of contractors. All equipment shall be delivered at the same time, meaning the same day (multiple trucks are acceptable) unless pre-authorized to deliver on multiple days by the RIA-JMTC contracting officer.

4.1.3 RECEIVER: All shipments to Rock Island Arsenal including installation tools and/or replacement parts, as well as the original shipment of the equipment, shall be marked “ATTN:

Mr. Joe Carpentier, TARA-IFF”. Items not correctly marked are subject to being returned at the vendor’s expense.

4.1.4 ARRIVAL INSPECTION: Upon receipt of equipment at Rock Island Arsenal, a preliminary inspection shall be performed to determine condition and/or count. This inspection shall be performed by Rock Island Arsenal personnel.

4.2 Installation

4.2.1 SITE PREPARATION REQUIREMENTS: The contractor shall be solely responsible for any necessary site inspections required for determining the specifications of work that must be completed prior to final system installation. The contractor will then provide detailed information of any preparation work that the vendor must perform prior to system installation to

Rock Island Arsenal.

4.2.2 SITE PREPARATION EXECUTION: The contractor will be solely responsible for site preparation except as specifically excluded in this document. This includes but is not limited to excavation, foundation work, and surface preparation. This work may be performed through the use of a sub-contractor, but the specification, supervision, and certification of the work remains the responsibility of the primary contractor.

4.2.3 PREPARATION EXECUTION SUPPORT: Rock Island Arsenal will support the preparation portion of the installation by providing utilities to the points of first connection.

4.2.4 LABOR AND MATERIAL: The supplier is solely responsible for providing all labor, materials, hardware, tools, and equipment necessary for complete installation of this system except as specifically listed in this document as being provided by the Rock Island Arsenal.

4.2.5 SUPERVISION: Supervision of the installation process will be the responsibility of the contractor. Rock Island Arsenal shall retain the right to periodic inspection and evaluation of the process, as it deems necessary.

4.2.6 OFF-LOADING/PLACEMENT: Off-loading of the equipment from the delivery vehicle, and placement of the equipment in position for the installation is the responsibility of the contractor. The contractor shall not be allowed to use government equipment to accomplish this work.

4.2.7 LIABILITY: In any case, the equipment remains the property of the contractor while being relocated and the contractor shall assume all responsibility and liability for the equipment and the work performed upon it. The government shall be held harmless for any damage done to the equipment at any time up until final acceptance of the equipment by Rock Island Arsenal, except in the case of intentional damage and/or gross negligence on the part of Rock Island

Arsenal personnel.

4.2.8 SET-UP: The contractor shall be responsible for set-up and connection of the equipment beyond connections of the utilities to the points of first connection.

4.2.9 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safe guards, various precautions, and plant protection measures. At all times during the execution of this SOW, the contractor will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal

Island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the Island.

4.2.10 Delivery Hours or Service Hours: Service calls, equipment installation, training, and equipment delivery (where the contractor offloads) will only be allowed from 0600 – 1530, Monday through Thursday, except for Government Holidays. Deliveries of items where the contractor has opted for Government “off-loading option”, must be received before 1200 hours.

These hours are subject to change, however, the Government will notify the contractor of such changes. The vendor will contact the designated COR to obtain an electronic key for their representative (i.e. delivery driver) in order to have access to the facility. Deliveries and service calls outside the normal hours stated above will be coordinated with the COR to address any emergency situations."

4.3 Completion

4.3.1 Final acceptance of the equipment shall occur after the following:

4.3.1.1 Set-up completion by the contractor.

4.3.1.2 Successful completion of performance testing at Rock Island Arsenal.

4.3.1.3 Final inspection approval by the government representative or inspector. This is to verify full compliance with this description to include amendments and modifications to the final contract. The government representative shall perform any and all tests he deems necessary to insure compliance with this description and industry standards to include, but not limited to ease of control, convenience of operation, safe operation, and adequacy of lubrication devices.

4.3.1.4 Complete documentation packages are delivered.

5. SERVICE

5.1 Service/Support Requirements

The contractor shall have as a minimum, a verifiable service/repair capability for warranty work which meets or exceeds the following requirements:

5.1.1 STAFF: Staffed by qualified, English speaking personnel fully knowledgeable in the service/repair of the equipment offered.

5.1.2 TELEPHONE ACCESS: Telephone access to service/repair personnel shall be available for consultation during Rock Island Arsenal normal working hours. Rock Island

Arsenal normal working hours are 8:00 am CST to 3:00 pm CST, Monday through Friday, except legal federal holidays.

5.1.3 ON-SITE RESPONSE: Physical, on-site response shall be possible within 48-hrs of notification that warranty service/repair of the equipment is necessary.

5.1.4 MAINTENANCE PARTS: Parts necessary for periodic replacement such as belts, hoses, filters, and other parts normally considered as spare parts, by the manufacturer, shall be stocked and available for shipment during the warranty period

5.1.5 PRIOR HISTORY: Said service/repair capability shall have been available to the general public prior to the issue date of this purchase description. Adequate proof of prior availability shall be provided upon request.

5.1.6 WARRANTY: The equipment/ system proposed shall have a warranty period of not less than 1 year after final acceptance. After the warranty period, the system shall be included in

RIA-JMTC’s maintenance and service contract with its current bulk gas supplier/ service company.

File details come from the government source that posted it. Updated .