Attachment 0002 - DUALNOCPRICE - W91CRB-20-R-5018.xlsx
XLSX spreadsheet 31 KB Posted
- Attached to
- Iraq Network Operations Center (NOC) Federal contract opportunity
- Solicitation number
- W91CRB-20-R-5018
About this file
This document contains a statement of work and pricing details for a federal contract opportunity to establish and operate Network Operations Centers in Iraq. The solicitation seeks products, services, training, and support to deliver two NOCs under Foreign Military Sales cases IQ-B-ADU and IQ-B-ZCA for the country of Iraq. Requirements include Cisco networking equipment, EMC storage servers, software licenses, installation materials, technical manuals, spare parts, generators, extended warranty coverage, site surveys, installation and integration services, factory acceptance testing, field service representatives, contractor travel, program support, student travel, logistical support, and regional and on-the-job training. Pricing is provided for base and option order periods, with inspection and acceptance to occur between months 4-12 after the start of each period following factory acceptance testing in the US. The total proposed contract amount will include sums for the base and option periods. The solicitation was issued by the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Request for Proposal - Iraq NOC - W91CRB-20-R-5018.pdf | ||
| Attachment 0001 PWS - W91CRB-20-R-5018.pdf | ||
| Exhibit A - CDRLS W91CRB-20-R-5018.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IQ-B-ZCA
| LINE | DESCRIPTION | UNIT OF ISSUE | COST | DOCUMENT # | MANP | SALES ORDER | WBS | PRON | PR | ||
| 001 | Student Travel and Logistical Support | 1 | $450,000 | BIQ04Z8313Y001 | F.0005977.1.1.1.1 | J59SAC629C | 59917641 | IQ-B-ZCA 001, Student Travel and Logistical Support, J59SAC629C | |||
| 002 | Contractor Technical Assistance | 1 | $325,000 | BIQ04Z8313Y002 | F.0005977.2.1.1.1 | J59SAC639C | |||||
| 003 | Contractor Travel and Program Support | 1 | 487000 | $121,750 | BIQ04Z8313Y003 | F.0005977.3.1.1.1 | J59SAC649C | 59919743 | IQ-B-ZCA 003, Contractor Travel and Program Support, J59SAC649C | ||
| 003 | Contractor Travel and Program Support | 1 | $365,250 | BIQ04Z8313Y003 | F.0005977.3.1.1.1 | J59SAD789C | 59919744 | IQ-B-ZCA 003, Contractor Travel and Program Support, J59SAD789C | |||
| 004 | In-Country Training Lab Equipment | 1 | $300,000 | BIQD7Z8313D004 | GFMS311047:80063 | 1115258815 | F.0005977.4.1.1.1 | J59SAC659C | 59919847 | IQ-B-ZCA 004, In-Country Training Lab Equipment, J59SAC659C | |
| 005 | In-Country Network, System, and Frequency Management Training | 1 | $450,000 | BIQ04Z8313Y005 | F.0005977.5.1.1.1 | J59SAC669C | 59919745 | IQ-B-ZCA 005, In-Country Network, System, and Frequency Management Training, J59SAC669C | |||
| 006 | Regional VSAT and Network Training | 1 | $1,800,000 | BIQ04Z8313Y006 | F.0005977.6.1.1.1 | J59SAC679C | 59919746 | IQ-B-ZCA 006, Regional VSAT and Network Training, J59SAC679C | |||
| $3,812,000 | |||||||||||
| $871,750 | Phase 1 | ||||||||||
| $2,615,250 | Phase 2 | ||||||||||
| $3,487,000 |
THIS CASE IS FOR IQ-B-ZCA, LINE ITEM 004, IN-COUNTRY TRAINING LAB EQUIPMENT
The SAMD POC IS DIMITRA BAIRAKTARIS, 609-552-5943 The ACQ Center is P5H.
CONTRACT Number: VSAT IDIQ
NOC AND TRAINING CLINS
| CLIN | Description | PWS Paragraph Reference (all whole paragraph references, ie 4.2, includes all sub-paragraphs) | U/I | Cost | Required Delivery After the Start of the Base Period or the Start of the Option Period: |
| 0001 | PHASE 1 SERVICES AND TRAINING -- BASE PERIOD | ||||
| 0001AA | Contractor Travel and Program Support (Training) | 4.1, 4.2, 4.3, 4.7, 4.12-4.16,4.18 | 1 LO | 12 month PoP starting from the beginning of the base period | |
| 0001AB | In-Country Training Equipment Installation and Training | 3.2.2.2.1.2, 3.3.1, 3.3.2, 4.2.2 | 1 LO | 5 month PoP starting on 8th month after start of base period | |
| 0001AC | In-country Site Surveys | 3.2.1 | 1 LO | 10 day PoP starting on 30th day after start of base period | |
| 0001AD | In-country Installation and Integration Services | 3.2.2.2.1.1, 3.2.3 | 1 LO | 1 month PoP starting on 12th month after start of base period | |
| 0001AE | CONUS Engineering, Build and Test, Factory Acceptance Test | 3.2.2.1, 4.4, 4.5 | 1 LO | 2 month PoP starting on 6th month after start of base period | |
| 0001AF | Extended Warranty | 3.2.5 | 1 LO | 36 month PoP starting after standard warranty coverage ends | |
| 0001AG | In-Country Field Service Representatives | 3.2.4, 4.2.1.3, 4.2.1.4 | 1 LO | 6 month PoP starting on 13th month after start of base period | |
| 0001AH | Contractor Program Support, Travel and Life Support (NOC) | 4.1, 4.2, 4.3, 4.7, 4.12-4.16, 4.18 | 1 LO | 18 month PoP starting from the beginning of the base period | |
| 0001AJ | In-Country On-the-Job Training | 3.3.4 | 1 LO | 1 month PoP starting on 12th month after start of base period | |
| Total CLIN Amount Phase 1 Services and Training - Base Period | |||||
| 0002 | PHASE 1 HARDWARE -- BASE PERIOD | ||||
| 0002AA | NOC A Software Licenses | 3.1.1.3; 4.17, 4.19 | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AB | Cisco Nexus 7000 Series For Data Aggregation (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AC | Cisco Router For DMVPN (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AD | Cisco Call Manager (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AE | Cisco Firewall (Internal Network) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AF | Cisco Firewall (External Network) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AG | Cisco Firewall Management Console (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AH | Cisco Email Security Appliance (ESA) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AJ | Cisco Web Security Appliance (WSA) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AK | Cisco Identity Services Engine (ISE) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AL | Cisco – UCS (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AM | EMC - Storage Server (200 TB) (NOC A) | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AN | Installation materials (NOC A) | 3.1.1.4; 4.5-4.11, 4.17 | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AP | DC Integrated Information Technology Module | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AQ | Technical Manuals | 3.1.1.5; 4.5-4.11, 4.17 | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AR | Spare Parts | 3.1.1.6; 4.5-4.11, 4.17 | 1 PG | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AS | Generator | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 EA | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AT | Automatic Transfer Switch | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 EA | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AU | Power Cable Feeder | 3.1.1.1; 4.5-4.11, 4.17; Appendix A | 1 EA | Inspect/accept on 8th month after start of base period; after CONUS FAT | |
| 0002AV | Training Lab Equipment | 3.1.1.2; 4.5-4.10, 4.17 | 1 PG | Inspect/accept on 4th month after start of base period; origin | |
| Total CLIN Amount Phase 1 Hardware - Base Period | |||||
| Total Price Phase 1 - Base Period | |||||
| 0003 | PHASE 2 SERVICES AND TRAINING -- OPTION PERIOD | ||||
| 0003AA | Student Travel and Logistical Support (Training) | 3.3.3.2; 3.3.3.3 | 1 EA | 10 month PoP starting from the beginning of the option period | |
| 0003AB | Contractor Travel and Program Support (Training) | 4.1, 4.2, 4.3, 4.7, 4.12-4.16, 4.18 | 1 EA | 10 month PoP starting from the beginning of the option period | |
| 0003AC | Regional VSAT and Network Training | 3.3.3.1 | 1 EA | 8 month PoP starting on 3d month after option period start | |
| 0003AD | In-country Site Surveys | 3.2.1 | 1 EA | 10 day PoP starting on 30th day after option period start | |
| 0003AE | In-country Installation and Integration Services | 3.2.2.2.2, 3.2.3 | 1 EA | 2 month PoP starting on 11th month after option period start | |
| 0003AF | CONUS Engineering, Build and Test, Factory Acceptance Test | 4.4, 4.5 | 1 EA | 1 month PoP starting on 6th month after option period start | |
| 0003AG | Extended Warranty | 3.2.5 | 1 EA | 36 month PoP starting after standard warranty coverage ends | |
| 0003AH | In-Country Field Service Representatives | 3.2.4, 4.2.1.3, 4.2.1.4 | 1 EA | 6 month PoP starting 13th month after option period start | |
| 0003AJ | Contractor Program Support, Travel and Life Support (NOC) | 4.1, 4.2, 4.3, 4.7, 4.12-4.16, 4.18 | 1 EA | 18 month PoP starting from the beginning of the option period | |
| 0003AK | In-Country On-the-Job Training | 3.3.4 | 1 EA | 2 month PoP starting on 11th month after option period start | |
| Total CLIN Amount Phase 2 Services and Training - Option Period | |||||
| 0004 | PHASE 2 HARDWARE -- OPTION PERIOD | ||||
| 0004AA | NOC B Software Licenses | 3.1.2.2.1, 4.17, 4.19 | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AB | Additional licenses | 3.1.2.2.2, 4.17, 4.19 | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AC | Cisco Nexus 7000 Series For Data Aggregation (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AD | Cisco Router For DMVPN (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AE | Cisco Firewall (Internal Network) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AF | Cisco Firewall (External Network) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AG | Cisco Firewall Management Console (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AH | Cisco Email Security Appliance (ESA) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AJ | Cisco Web Security Appliance (WSA) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AK | Cisco Identity Services Engine (ISE) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AL | Cisco – UCS (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AM | EMC - Storage Server (200 TB) (NOC B) | 3.1.2.1; 4.5-4.11, 4.17; Appendix A | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AN | Installation materials (NOC B) | 3.1.2.3; 4.5-4.11, 4.17 | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AP | IP microwave gigabyte radio hardware | 3.1.2.4; 4.5-4.11, 4.17 | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| 0004AQ | Additional equipment required to make NOCs operational | 3.1.2.5; 4.5-4.11, 4.17, 4.19 | 1 PG | Inspect/accept on 7th month after start of option period; after CONUS FAT | |
| Total CLIN Amount Phase 2 Hardware - Option Period | |||||
| Total Price Phase 2 - Option Period |
TOTAL PROPOSED CONTRACT AMOUNT (BASE & OPTION PERIODS)