Att2_MNF Road Maintenance QASP.pdf
PDF 320 KB Posted
- Solicitation number
- 12444324R0001
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for a road maintenance Indefinite Delivery/Indefinite Quantity (IDIQ) contract on the Monongahela National Forest in West Virginia. The QASP outlines performance standards and acceptable quality levels for tasks including road grading, culvert cleaning, ditch cleaning, and tree removal. It describes surveillance methods such as inspections and customer feedback to measure compliance. Key contractor responsibilities include implementing a Quality Control Plan and maintaining quality records. The Contracting Officer Representative will perform oversight including inspections, approving corrective actions, and analyzing performance results. Performance will be rated as excellent, satisfactory, or unsatisfactory based on metrics for timeliness, quality of work, and adherence to technical requirements. The plan includes example forms for discrepancy reports, customer feedback, inspection checklists, and monitoring activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att5_SZ_district_map.pdf | ||
| Att9_Project Methodology.pdf | ||
| Att4_NZ_district_map.pdf | ||
| Att8_Past Performance.pdf | ||
| Att6_Technical Drawings.pdf | ||
| Att10_Personnel and Equipment.pdf | ||
| Att3_Forest Map.pdf | ||
| 12444324R0001.pdf | ||
| Att1_MNF Road Maintenance PWS.pdf | ||
| Att7_Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Quality Assurance Surveillance Plan
Contents Project Name Solicitation / Contract Number Section 1: Introduction
1.1 Purpose
1.2 QASP Relation to the Contract
1.2.1 QASP Revisions
1.2.2 Surveillance of Performance Progression
1.3 QASP Relation to the Quality Control Plan (QCP)
Section 2: Performance Description
2.1 Performance Standards and Acceptable Quality Levels (AQLs)
2.1.1 Allowable Deviation
2.1.2 Substantially Complete
2.2 Non-Performance
2.2.1 Documentation
2.2.2 Remedial Actions
Section 3: Contractor and Government Responsibilities
3.1 Contractor Responsibility
3.2 Government Responsibility
3.2.1 Contracting Officer (CO)
3.2.2 Contracting Officer Representative (COR)
3.2.3 Customers
Section 4: Surveillance Methods to Perform Quality Assurance
4.1 Surveillance Methods
5.1 Analysis and Results
Appendix A: Example Discrepancy Report Appendix B: Customer Feedback Record Appendix C: Example Guide / Inspection List Appendix D: Example Quality Assurance Monitoring Appendix E: Example Customer Complaint Investigation Appendix F: Example Surveillance Activity Checklist
Project Name Monongahela National Forest Road Maintenance IDIQ
Solicitation / Contract Number Insert Solicitation / Contract Number
Section 1: Introduction This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled Monongahela National Forest Road Maintenance IDIQ.
This plan sets forth the procedures and guidelines that the USDA, Forest Service will use in ensuring the required performance standards or services levels are achieved by the contractor.
1.1 Purpose
The purpose of the QASP is to describe the systematic methods used to measure performance and to identify the reports required and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards identified in the PWS. This QASP is designed to define roles and responsibilities, identify the performance objectives, define the methodologies used to monitor and evaluate the contractor’s performance, describe quality assurance reporting, and describe the analysis of quality assurance monitoring results.
1.2 QASP Relation to the Contract
1.2.1 QASP Revisions
The Contracting Officer Representative (COR) may make revisions or changes to the QASP procedures and surveillance methods or increase or decrease the degree of surveillance methods at any time during the contract performance period. Changes to the Metric must be incorporated into the PWS, Performance Requirement Summary (PRS) and QASP by a bilateral modification to contract that is issued by the Contracting Officer (CO). A copy of the QASP is provided to the contractor to enable the contractor to enhance its Quality Control (QC) program to perform in accordance with its Quality Control Plan (QCP).
1.2.2 Surveillance of Performance Progression
As the performance period progresses, the levels of surveillance may be altered for service areas where performance is either consistently excellent or unsatisfactory. If consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.
1.3 QASP Relation to the Quality Control Plan (QCP)
The QCP is a required element of contract and the Contractor shall adhere to its established quality control processes and procedures in managing and performing work as described in the contract. While the QCP represents the way in which the Contractor will ensure its quality and timeliness of services, as defined in the PWS, the QASP represents the way in which the Government personnel specified in Section 3: Contractor and Government Responsibilities, Paragraph 3.2, Government Responsibilities will evaluate the contractor’s performance. The contractor’s QC program and the residual organization’s QASP should be complementary programs that ensure successful contractor performance.
Section 2: Performance Description Performance of the contractor will be monitored through the surveillance methods described in Section 4: Surveillance Methods to Perform Quality Assurance to assess the Contractor’s performance against PWS requirements.
2.1 Performance Standards and Acceptable Quality Levels (AQLs) For selected activities in the PWS, the PRS provides a performance standard and an AQL. A performance standard is the expected level of contractor performance. An AQL defines the level of performance that is satisfactory. Depending on the service evaluated and the evaluation method selected, performance standards and AQLs may be stated as a number of occurrences or as a percentage. Performance standards and AQLs for random sampling and 100 percent inspection are generally stated as percentages. For periodic inspections, performance standards may be stated as either percentages or as absolute numbers.
The contract requires the Contractor to perform all work as specified. Any inaccuracies or omissions in services or products are referred to as “defects” on the part of the Contractor. The Contractor shall be responsible for all identified defects and may be required to perform the work at no cost to the government. The AQLs take into account that in some instances an allowable level of deficiencies (deviations) is possible while overall performance continues to meet the government’s desired level of service.
2.1.1 Allowable Deviation
The AQLs define the level or number of performance deficiencies the Contractor is permitted to reach under this contract. AQLs take into account the difference between an occasional defect and a gross number of defects. AQLs can be expressed as a percentage of or as an absolute number (e.g., three per month). There may be instances where 100 percent compliance is required, and no deviation is acceptable (e.g., where safety is involved).
2.1.2 Substantially Complete
In some cases, service outputs are evaluated using subjective values (e.g., excellent, satisfactory, unsatisfactory). The criteria for acceptable performance and for defects must be defined for these service outputs. The concept of “substantially complete” should be the basis for inspections based on subjective scales. Work is considered “substantially complete” where there has been no significant departure from the terms of the contract and no omission of essential work. In addition, the Contractor has performed the work required to the best of its ability and the only variance consists of minor omissions or deficiencies.
2.2 Non-Performance
Non-performance occurs when the contractor’s performance does not meet the AQL for a given requirement.
Requirements may contain multiple performance elements, and therefore, deficiencies may occur in one or more aspects of performance (e.g., timeliness, accuracy, completeness, etc.) or subject areas of effort.
When surveillance indicates that the contractor's service output is not in compliance with the contract requirements, the Contracting Officer’s Representative (COR) must determine whether the Contractor or the Government caused the deficiency. If the cause of the defect rests with the Government, corrective action must be taken through Government channels. If the cause of the defect is due to action or inaction by the contractor, the contractor is responsible for correction of the problem at no additional expense to the Government.
2.2.1 Documentation
Documentation of work non-performed or unacceptable work is essential for tracking Contractor performance. The COR will document deficient work by compiling facts describing the inspection methods and results and to substantiate nonconformance with the contract. A sample documentation reporting form is provided in Appendix B: Discrepancy Report. The documentation, with any recommendations, will be forwarded to the CO. In the case of the Contractor, the COR will decide whether to elevate the problem to the CO for corrective action.
2.2.2 Remedial Actions
The Federal Acquisition Regulation allows for penalties in the event that the Contractor fails to perform the required services. Penalties are defined as those actions taken under the direction of the CO against the contractor within the general provisions of the contract for nonconformance to the PWS and PRS.
Section 3: Contractor and Government Responsibilities
3.1 Contractor Responsibility
The Contractor is responsible for delivering products or services in accordance with the contract. Implementing its QCP, which describes the Contractor’s methods for ensuring all products and services under the contract meet established performance standards and AQLs. Maintaining, and providing for audit, quality control records and reports and all records associated with the investigation and complaint resolutions. Appointing a single quality control point-of-contact to act as a central recipient of communication from the COR or CO.
3.2 Government Responsibility
3.2.1 Contracting Officer (CO)
The CO is responsible for administering and monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by COR and the contractor’s performance. The CO may delegate various day-to-day contract administration duties to a Administering ACO (ACO) and/or the COR for performance management and administrative actions such as invoice approval and issuance of Contract Discrepancy Reports may be, and normally are, delegated by the CO to the COR. The CO shall approve any revisions to the QASP processes or standards.
3.2.2 Contracting Officer Representative (COR)
The COR, is designated in writing, by the CO. The COR will ensure that the QA function is properly executed, plays a key role in contract administration and performs the contract surveillance and monitoring. Some key contract administration duties include, but are not limited to, performs surveillance as required by this QASP; make recommendations to the CO for issuance of Contract Discrepancy Reports or letters of commendation and acceptance or rejection of completed work and for administrative actions based on unsatisfactory or non-performed work, and revisions or changes to the QASP;
and assists the CO in identifying necessary contract modifications and preparing reports of Contractor performance and cost.
The COR may use the form(s) included in the Appendices to perform the inspection or other forms as approved by the CO. The Contractor overall guidance is also provided by Federal Acquisition Regulation (FAR).
3.2.3 Customers
Customers or organizations/offices that the Contractor provided support may be requested to assist the COR in conducting QA to provide information relating to the Contractor’s performance through Customer Feedback.
Information gained from the Customer Feedback may be used in conjunction with other methods of observation to rate the performance of the Contractor.
Section 4: Surveillance Methods to Perform Quality Assurance
4.1 Surveillance Methods
The surveillance methods used in the QA process are the Government’s tools to monitor the Contractor’s products and services. The best means of determining whether the Contractor has met all contract requirements is to inspect the Contractor’s service products and analyze the results. Further, documented inspection results are an effective tool in contract administration that can confirm the successful achievement of all performance requirements or highlight areas where defects exist and improvements are necessary.
5 Performance Objective
Required Task or Deliverable
Performance Standard Method of Surveillance
Positive/Negative Incentive % for NOT meeting the Task
1. Roadbed
1.1 Grading Produce a safe, smooth, drained, and lasting road surface free of potholes, ruts, berms, washboard, and organic soil and debris while recovering any useable existing aggregate. This work also includes the reconditioning of drainage dips, turn-outs, and turnarounds.
Road Safe to drive within speed limit over 95% of traveled way; Surface shaped with proper crown or slope as well as can be accomplished utilizing native surface material over 100% of length.
Leave Seven or fewer loose rocks 3” or larger in two dimensions on traveled way within a mile 100% of the time.
Drive the road.
Inspection for adherence to Quality Control Plan; Visual Inspection;
Physical measurements.
Potential additional option years.
Rework at no additional cost to the government for noncompliance.
All work to be done in an environmentally sound manner.
Surface prepared according to Quality Control Plan 100% of time; 100% of potholes with a depth greater than 1.5” removed; Leave Seven or fewer visible potholes within a mile 100% of the time;
Leave Less than 300’ containing berms, and/or washboard, and/or organic soil within a mile 100% of the time.
Recover 95% of usable existing aggregate that has been worked onto the road shoulder and take extra care to prevent wasting usable aggregate over shoulder.
No undercutting of traveled way edges over 95% of road length.
No roadway material or waste deposited in or near streams and deposited away from ditches and culverts 100% of time.
100% of Wood debris larger than 1.5” diameter or over 18” long will be removed from traveled way.
Exercise caution and care, erect signs and schedule work per contract specifications 100% of time
Complete work in accordance with contract times 100% of time.
2. Drainage
2.1 Culvert Cleaning Inspect and clean
culverts to maintain free flow.
95% Free flowing to maximum attainable flow to, through, and away from culvert on culverts 3’ or smaller in diameter; flag and report 100% of larger pipes needing cleaning to COR.
100% of Culvert barrel clean a minimum of 3’ into each end.
Visual inspection;
Physical measurement.
Rework at no additional cost to the government for noncompliance.
Potential additional option years.
95% Free flowing to maximum attainable flow to, through, and away from culvert on culverts 3’ or smaller in diameter; flag and report 100% of larger pipes needing cleaning to COR.
100% of Culvert barrel clean a minimum of 3’ into each end (flushing not required)
100% of Culvert outlet ditches cleaned and reshaped a minimum of 10’ beyond the outlet.
100% of Inlet (pipe pockets)/outlet basins maintained per typical or original shape.
100% of Wood debris larger than 1.5” diameter or over 18” long will be removed from inlet/outlet basins.
2.2 Ditches Clean ditches to
maintain free flow in an environmentally sound manner.
95% Free flowing
95% of Suitable material reclaimed and used within traveled way.
100% of Unsuitable material wasted beyond and below outside edge of road shoulder away from drainage courses.
100% of Leadoff ditches opened minimum of one grader length from edge of road and to the end unless obstructions prevent operation of motor grader.
100% of Wood debris larger than 1.5” diameter or over 18” long will be removed from ditches.
Leave 7 or fewer Loose rocks larger than 6” in two dimensions in ditch line within a mile 100% of time.
Visual inspection;
Physical measurement.
Rework at no additional cost to the government for noncompliance.
Potential additional option years.
95% of erosion-controlling vegetation growing in ditches not unnecessarily disturbed.
No undercutting of road shoulders.
2.3 Tree Removal Remove felled trees
that interfere with drainage or vehicle travel and require use of a chainsaw.
Remove 100% of felled trees that interfere with drainage or vehicle travel and require the use of a chainsaw.
Visual by FS inspector while work is being done.
3. Equipment Provide and operate equipment as approved by FS for road maintenance work not specifically covered under previous tasks.
100% compliance with OSHA Industry practice.
100% compliance with FS fire suppression practice.
Visual inspection by FS inspector at inspector discretion.
5.1 Analysis and Results
When the inspections and customer feedback validations have been completed, the COR will perform an analysis of the Contractor’s performance. The purpose of the analysis is to ensure Government is receiving high-quality products and services from the Contractor. The COR will review the results, rate the Contractor’s compliance with the performance standards and AQLs, and characterize the Contractor’s overall performance.
Appendix A: Example Discrepancy Report The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
DISCREPANCY REPORT 1. DISCREPENCY REPORT NO.
2. TO: (Contractor / Project Manager Name) 3. FROM: (Name of COR)
CONTRACT NUMBER: DATE:
PREPARED ORAL NOTIFICATION RETURNED BY CONTRACTOR ACTION COMPLETE
4. DISCREPENCY OR PROBLEM (Describe in Detail. Include PWS references. Attach Continuation Sheet if Necessary)
5. SIGNATURE OF COR
6. TO: (Name of COR) 7. FROM: (Contractor / Project Manager)
8. CONTRACTOR RESPONSE AS TO CAUSE, EFFECT, CORRECTIVE ACTION AND ACTIONS TO PREVENT RECURRENCE (Attach Continuation Sheet if necessary. Cite applicable Contractor QC program procedures or new QC procedures)
9. SIGNATURE OF CONTRACTOR REPRESENTIVE 10. DATE
11. GOVERNMENT EVALUATION (Acceptance, partial acceptance, or rejection. Attach Coordination Sheet if necessary)
12. GOVERNMENT ACTIONS (Cure notice, show cause, other)
CLOSE OUT
KTR NOTIFIED
NAME AND TITLE SIGNATURE DATE
COR
Appendix B: Customer Feedback Record The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
CUSTOMER FEEDBACK RECORD
DATE AND TIME OF COMPLAINT CONTRACT NUMBER/ OR PROJECT:
SOURCE OF COMPLAINT
ORGANIZATION
INDIVIDUAL
NATURE OF COMPLAINT
PWS REFERENCE
VALIDATION
DATE AND TIME CONTRACTOR INFORMED OF COMPLAINT NAME OF CONTRACTOR REPRESENTATIVE INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR (Responsible officer):
RECEIVED AND VALIDATED BY
Determination: Complaint Valid Complaint Invalid
Appendix C: Example Guide / Inspection List The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
CONTRACT NUMBER: ___________________________________
SERVICE FUNCTION:
PWS SECTION:
1 Method of Surveillance:
2 Lot Size:
3 Sample Size:
4 Performance Requirement: Performance is Excellent (E) when ___________or fewer defects are discovered per month. Performance is Satisfactory (S) when ________ or fewer defects are discovered per month. Performance is Unsatisfactory (U) when _______ or more defects are discovered per month.
5 Sampling Procedure: Instructions on how to select the sample must be clear and complete
6 Inspection Procedure: The procedure must be detailed enough to allow a yes/no objective decision as to the acceptability of performance by anyone making the inspection. Explain when evaluation is to occur and what is acceptable/unacceptable
Performance: Excellent (E), Satisfactory (S), Unsatisfactory (U), Not Applicable (N/A)
PRS Requirements Timeliness Quality of Work Notes
Overall Rating Of Inspection (E, S, U or N/A)
COR/Inspector Comments:
Contractor Signature: ___ Date: __
COR Signature: ____________________Date: _________________
Appendix D: Example Quality Assurance Monitoring The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
CONTRACT NUMBER: ______________________________________
SERVICE or STANDARD:
SURVEY PERIOD:
SURVEILLANCE METHOD (Check the applicable item):
Random Sampling 100% Inspection Periodic Inspection Customer Complaint
LEVEL OF SURVEILLANCE (Check the applicable item):
Monthly Quarterly As needed
PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %
ANALYSIS OF RESULTS:
Observed Service Provider Performance Measurement Rate: ______%
Service Provider’s Performance (Check the applicable item):
Meets Standards
Does Not Meet Standards
Narrative of Performance During Survey Period:
Prepared By: _______________________________ Date: ______________
Appendix E: Example Customer Complaint Investigation The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
CONTRACT NUMBER: _________________________
SERVICE or STANDARD:
SURVEY PERIOD: ___________________
DATE COMPLAINT RECEIVED: ____________
SOURCE OF COMPLAINT: _________________________________________ (Name) _______________________________________________________________ (Organization) ___________________ (Phone No.) _________________________________ (Email Address)
NATURE OF COMPLAINT:
RESULTS OF COMPLAINT INVESTIGATION:
DATE SERVICE PROVIDER INFORMED OF COMPLAINT: _____________
CORRECTIVE ACTION TAKEN BY SERVICE PROVIDER:
Received and Validated By: __________________________________________ Prepared By: _____________________________ Date: _________________
Appendix F: Example Surveillance Activity Checklist The following document is only an example, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
Performance Requirement
Performance Standard
Method of Measurement
Performance Metrics
Method of Surveillance
Date Accomplished
Compliance (Exceed, Met, Partial Met)
| Project Name |
| Solicitation / Contract Number |
| Section 1: Introduction |
| 1.1 Purpose |
| 1.2 QASP Relation to the Contract |
| 1.2.1 QASP Revisions |
| 1.2.2 Surveillance of Performance Progression |
| 1.3 QASP Relation to the Quality Control Plan (QCP) |
| Section 2: Performance Description |
| 2 |
| 2.1 Performance Standards and Acceptable Quality Levels (AQLs) |
| 2.1.1 Allowable Deviation |
| 2.1.2 Substantially Complete |
| 2.2 Non-Performance |
| 2.2.1 Documentation |
| 2.2.2 Remedial Actions |
| Section 3: Contractor and Government Responsibilities |
| 3 |
| 3.1 Contractor Responsibility |
| 3.2 Government Responsibility |
| 3.2.1 Contracting Officer (CO) |
| 3.2.2 Contracting Officer Representative (COR) |
| 3.2.3 Customers |
| Section 4: Surveillance Methods to Perform Quality Assurance |
| 4 |
| 4.1 Surveillance Methods |
| 5.1 Analysis and Results |
| Appendix A: Example Discrepancy Report |
| Appendix B: Customer Feedback Record |
| Appendix C: Example Guide / Inspection List |
| Appendix D: Example Quality Assurance Monitoring |
| Appendix E: Example Customer Complaint Investigation |
| Appendix F: Example Surveillance Activity Checklist |