ATT B Crane Rehab SOW.pdf

PDF 186 KB Posted

Attached to
REHAB MACHINE SHOP CRANE
Solicitation number
140R4020Q0080
Issued by

View the file

Other files

File Type Posted
Sol_140R4020Q0080_Amd_0001.pdf PDF
ATT C 140R4020Q0080.docx DOCX document
ATT A Terms and conditions 140R4020Q0080 (AutoRecovered).docx DOCX document
ATT D Machine Shop Crane Pictures.docx DOCX document
Sol_140R4020Q0080.pdf PDF
ATT E 15-5466 wage Determination 7 1 2020.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rehabilitation of Machine Shop Crane

Glen Canyon Dam, Page, Arizona

1.0 Purpose

The Bureau of Reclamation, Glen Canyon Field Division Power Plant, located in Page, Arizona requires rehabilitation of one Savigliano 75 Ton Bridge Crane located in the Power Plant Machine Shop.

2.0 SCOPE Restore functionality of the crane maintaining the original rate capacity of the crane

• Convert to radio control

• Replace all four sets of brakes with new thruster brakes (disks brakes preferred)

• Perform a mechanical inspection of all components of the crane

• Perform load tests of both hooks and make any adjustments necessary to accomplish smooth, safe operation.

• Provide four hours training to plant mechanics and electricians

• Perform work in accordance with Crane Manufacturer’s Association of America

(CMAA), OSHA 1910.179, ASME B30.2, and Reclamation Safety and Health Standards (RSHS).

• Provide parts of OEM quality or better. Parts are considered equal if they meet the same performance quality and reliability standards as OEM parts that would be used in a new crane installation.

3.0 Background

3.01 The Savigliano 75 Ton Bridge Crane was installed during initial construction of the machine shop in the early 1960s. In this configuration it was equipped with DC motors and drives. In the mid-1990s the crane was modernized. Motors and drives were switched to AC.

It has the following configuration:

Location HP RPM Speeds Brake Diameter Brake Width

Number of Brakes

Trolley Drive 3 1140 0 – 30 ft/min 4 ½” 2 ¾” 1 Bridge Drive 10 1160 0 – 85 ft/min 5 ½” 3 ¼” 1 15 Ton Hook 60 1160 0 – 33 ft/min 500mm 165mm 2 75 Ton Hook 60 1160 0 – 6.6 ft/min 500mm 165mm 2

Electrical power is 480VAC 3phase 60hz.

Motor drives are Baldor 18H AC Vector Drives.

This upgraded configuration has developed numerous small problems with the result that the crane is not used at present. In addition, access to the operator’s cab is difficult and the cage around the cab limits visibility of objects on the floor.

4.0 Site Visit

4.01 A site visit is planned for prospective Vendors on August 19-20, 2020 staring at 10:00am Mountain Standard Time by appointment only. See Provision 52.237-7 in the terms and conditions for full details. Attendance is highly recommended as information for the crane is scarce. We will assume that all vendors have sufficient knowledge of the crane to present accurate quotes, whether or not they were present at the site visit.

4.02 Attendees must contact Lisa Laughbon (llaughbon@usbr.gov) 801-524-3732 at least four calendar days in advance to schedule the site visit.

4.03 Present a valid photo ID at check in. Meet in the Glen Canyon Visitor Center for check in.

Visitors will be escorted at all times. ATTENDEES ARE TO PROVIDE AND WEAR SAFETY BOOTS, HARD HATS, SAFETY VESTS and Industrial Face Mask due to COVID 19

5.0 Job Supervisor

A Supervisor shall be on site any time work is being performed. The Supervisor must be employed by the main Contractor and be the point of contact with the Government.

Certifications? Qualifications

6.0 Submittals

Section Submittal required Due date/

Delivery time

Sets to be sent

CO COR

2.0 SCOPE Crane testing

procedures

At least 7 days before work begins.

1 paper + 1 electronic

2.0 scope Project Records Document

Remedies for deficiencies found in inspection

Within 7 days of inspection 1 paper + 1 electronic

5.0 STANDARDS Catalog Cuts sheets with

commercial product data

Before purchase of equipment 0 1 paper + 1 electronic

5.0 STANDARDS Contractors Safety Plan At least 14 days before works begin

1 paper + 1 electronic

6.0 JOB

SUPERVISOR

Qualifications for Job Supervisor

At least 14 days before work begins

1 paper + 1 electronic mailto:llaughbon@usbr.gov

Project Records Documents

AutoCAD drawings for all wiring, schematics and equipment installed

Within 14 days of final inspection

Project Records Documents

Final Report With in 14 days of job completion 1 paper + 1

Project Records Documents

Spare Parts list At final inspection 1 paper + 1

LIST OF ATTACHMENTS

ATTACHMENT Description Number of Pages A Terms and Conditions 43 B Statement of Work 3 C Price schedule 1 D Photographs 8 E Wage Rate Determination 14

1.0 Purpose
3.0 Background
4.0 Site Visit
4.0
4.0
5.0 Job Supervisor
6.0 Submittals

File details come from the government source that posted it. Updated .