This solicitation requests proposals to replace critical high voltage electrical switchgear at the Statue of Liberty National Monument. The National Park Service seeks a contractor to remove the existing 480-volt 800-amp switchgear and install new equipment that meets specifications outlined in the documentation. Proposals are due within the timeframe specified in any subsequent request for proposal letter issued by the contracting officer. The selected contractor will be responsible for procuring, delivering, and installing the new switchgear over the course of five days requiring the monument's closure. The contractor must comply with all applicable regulations and safety requirements and provide documentation including an accident prevention plan, waste management plan, and other submittals as specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4521R0010_Amd_0003.pdf | ||
| Amend_3_Attach_5_Electrical_Fort_wood_0003.pdf | ||
| Amend_3_Attach_2_PPQ_0003.docx | DOCX document | |
| Amend_3_Attach_3_LimitationsOnSubcontractingReport_Form_0003.xlsx | XLSX spreadsheet | |
| Amend_3_Attach_6_Liberty_single_line_0003.pdf | ||
| Amend_3_Attach_4_Electrical_Fort_wood_1P_0003.pdf | ||
| Amend_3_Attach_1_Q-n-A_0003.docx | DOCX document | |
| Sol_140P4521R0010_Amd_0002.pdf | ||
| Photos_and_Spec_Diagram_0001.zip | ZIP file | |
| Sol_140P4521R0010_Amd_0001.pdf | ||
| Statue_switchgear_access_map_0001.pdf | ||
| Sol_140P4521R0010.pdf | ||
| Att 2 DBA WD.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATUE of LIBERTY NM New York & New Jersey
REPLACE CRITICAL HIGH VOLTAGE SWITCHGEAR IN MONUMENT
ON LIBERTY ISLAND
PARK: STLI
PMIS NO.: 258838
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
February 11, 2021
PROJECT TABLE OF CONTENTS
DIVISION 01 -- GENERAL REQUIREMENTS
01 10 00 CONTRACT MODIFICATION PROCEDURES --------------------- 1 - 6
01 11 00 SUMMARY OF WORK --------------------------------------------------- 1 - 6
APPENDIX A – Guidelines for Park Access and Credentialing 12/3/2018
01 27 00 DEFINITION OF CONTRACT LINE ITEMS ------------------------- 1 - 1
01 31 00 PROJECT MANAGEMENT AND COORDINATION -------------- 1 - 10
01 32 33 PHOTO DOCUMENTATION FOR HISTORIC PRESERVATION 1 - 2
01 33 23 SUBMITTAL PROCEDURES ------------------------------------------- 1 - 8
01 35 23 SAFETY REQUIREMENTS --------------------------------------------- 1 - 3
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES --- 1 - 6
01 40 00 QUALITY REQUIREMENTS ------------------------------------------- 1 - 16
01 42 00 REFERENCES ------------------------------------------------------------- 1 - 25
01 50 00 TEMPORARY FACILITIES AND CONTROLS --------------------- 1 - 11
01 57 19.12 NOISE & ACOUSTICS MANAGEMENT ---------------------------- 1 - 3
01 67 00 PRODUCT REQUIREMENTS ------------------------------------------ 1 - 9
01 73 29 CUTTING AND PATCHING -------------------------------------------- 1 - 4
01 73 40 EXECUTION --------------------------------------------------------------- 1 - 6
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 1 - 8
APPENDIX A – WASTE MANAGEMENT PLAN WORKSHEET
APPENDIX B – STANDARD SOLID WASTE CONVERSIONS -
01 77 00 CLOSEOUT PROCEDURES -------------------------------------------- 1 - 5
DIVISION 26—ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL ----------------- 1 - 21
26 05 13 MEDIUM-VOLTAGE CABLES ----------------------------------------- 1 - 5
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES --------------------------------------------- 1 – 5
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 1 – 7
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS --- 1 – 5
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS ------ 1 – 11
26 05 44 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS 1 – 4
PROJECT TABLE OF CONTENTS PAGE 2
AND CABLING
26 05 48 SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS ------------ 1 – 7
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS ----------------- 1 – 8
26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 1 – 8
23 00 LOW-VOLTAGE SWITCHGEAR -------------------------------------- 1 – 13
26 24 13 SWITCHBOARDS --------------------------------------------- 1 – 8
APPENDIX A – SWITCHBOARD DIAGRAM
END OF PROJECT TABLE OF CONTENTS
STLI 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
STLI 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating
General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
STLI 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
STLI 01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region) http://www.nps.gov/dscw/publicforms.htm#ct
STLI 01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the
US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10%
Profit…………………….6%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par
1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
STLI 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
STLI 258838 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Soils Investigation Report.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Statue of Liberty National Monument and Ellis Island, Statue Pedestal New
York, New York 10004.
B. The project will replace critical high voltage electrical switchgear located on Level 1P inside the
Monument on Liberty Island. The equipment to be replaced is 480 volt 800 amp capacity. The existing switchgear is outdated, and it is difficult to find replacement parts. The switchgear is critical because it powers essential functions including: the visitor elevator for accessibility, the secondary screening facility for Monument security, and 2 large chiller pumps for cooling.
C. The project will include, but not be limited to, the following:
1. Review site data and existing conditions.
2. Engage an Electrical Engineer licensed in the state of New York to select and specify replacement equipment that meets the requirements set forth in the Division 26
Specifications.
3. Provide schedule to include design/product selection, submittal review, procurement and delivery, and proposed date for monument closure.
4. Demolish and remove existing equipment.
5. Installation and energizing new equipment.
6. Create and provide operations and maintenance manual
D. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in two phases, Administrative and Construction.
STLI 258838 01 11 00 - 2
1. Administrative:
a. Upon issuance of Notice To Proceed Contractor is to engage the Electrical Engineer to select and size the new equipment and provide an action submittal for NPS review.
b. Upon approval of primary equipment submittal, procure and provide delivery timeline of the new switchgear.
c. Submit for review all other material submittals required by this project manual (Division 1 through 26)
d. Provide a schedule for install, which is anticipated to take three full days of monument shut down.
2. Construction:
a. Will occur no less than 190 calendar days from NTP to allow for the NPS and Ferry Concessioner to block ticket sales for the Crown and Pedestal for the three days anticipated.
b. Actual construction is anticipated to take 5 days;
1) Day 1 (Monday) mobilization, delivery, preparation and selective demolition,
2) Day 2 (Tuesday) for de-energized demolition,
3) Days 3&4 (Wednesday & Thursday) for de-energized installation, and
4) Day 5 (Friday) for clean-up and demobilization
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
1. Concurrent Work: Fort Wood Stone Masonry Rehabilitation and Terreplein Paver replacement.
1.5 GOVERNMENT FURNISHED MATERIALS
A. NONE.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to the areas in the immediate vicinity of the electric room.
2. Toilet Facilities – May use the facilities within the pedestal monument located at 2P.
3. No signs or advertising will be permitted. All directional, safety or informational signs must comply with OSHA or MUTCD requirements. All others must be approved by
NPS.
STLI 258838 01 11 00 - 3
4. The other buildings on Liberty Island will be off limits unless the contract work requires entry into the structures. These buildings are unoccupied and are stabilized only.
Contractor to enter existing buildings only to accomplish required work.
5. Working in the Park is different from many other construction locations in that special protection is given to cultural resources. Cultural Resources refers to any archeological, architectural, or landscape feature or artifact that contributes to the historic significance of the Park. Features are permanent or semi-permanent objects, such as architectural fragments, buried foundation walls, or pavements. Artifacts are any object made, used, or modified by people. An Archeological Site is an assemblage of artifacts or features that are in their original location. The National Park Service exists to preserve resources under its protection unimpaired for future generations. Carrying out Park construction projects requires more care for potential damage to historic resources than may be the case in commercial projects.
6. Archeological artifacts, architectural fragments, and natural objects are not to be taken from National Park units. It is illegal to remove materials from National Parks. Federal law provides penalties for doing so. If a contractor finds an artifact, it must be turned over to the Park.
7. It is also necessary to avoid damaging cultural resources. If, for example, an unanticipated obstruction, such as a buried foundation or wooden bulkhead, is found during excavation, one should not assume that demolishing it is acceptable. If a cultural resource has been damaged because it was not seen during excavation or other construction (for example, a buried wall is hit by a backhoe), or if an accident occurred
(for example, a vehicle scrapes a building or wall), this must be reported to the Park. In most cases, such damage will not impact the progress of construction activities, but it cannot be ignored or reported long after it occurred. Park staff can assist with issues that may arise.
8. A qualified archeological monitor will observe excavations in archeologically sensitive areas. Work can be conducted without the archeological monitor present, but it is helpful to all if the schedule for excavation be clearly communicated in advance. It is acceptable for contractors to layout excavation routes, mobilize equipment, and begin the excavation without having a monitor present. What is important is that excavated trenches remain open for inspection by the archeological monitor before backfilling.
9. Although it is very unlikely, from what is known about the locations for this project and the relatively shallow depths proposed for excavation, there is always the possibility that human remains will be found. By law, work must stop if human remains are found, and the remains may not be removed. The Park must be notified at once of a potential discovery. If bones are found, the NPS Archeologist will make a determination if they are human.
10. The existing trees and landscape are also the Park’s Cultural Resource and must also be protected and preserved. Avoid parking or stockpiling materials adjacent to a tree, under or within the drip line of the tree’s canopy.
B. Storage of Materials: Confine storage of materials to the areas designated as Contractor
Staging/Storage during the preconstruction site visit. (generally, the area in the immediate vicinity of the electrical room at 1P).
C. Parking on Ellis/Liberty State Park.
STLI 258838 01 11 00 - 4
1. Contractor and its subcontractors are responsible to shuttle workers to Ellis Island.
a. Limited parking will be made available for Contractor’s management staff, deliveries and loading.
b. A maximum of four (4) Ellis Island parking placards will be issued to the
Contractor for use during this project allowing the Contractor to park in Yellow spaces in the south lot. Any project vehicle not displaying an issued placard is subject to ticketing or tow. Additional placards may be authorized by the
Contracting Officer’s Representative provided an evaluation of available space and project need deem them appropriate.
D. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Driveways and Entrances: Keep driveways, parking areas, boat docks and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Construction Camp: Establishment of a camp within the park will not be permitted.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.7 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Building closures will be permitted, when required, upon specific approval of Contracting Officer.
B. Questions from Press, Interested Parties and Public Relations
1. Any questions raised by the general public or reporters to Contractor regarding the project, or the Park, should be deferred to the NPS. The Contractor should not answer
STLI 258838 01 11 00 - 5
any questions; rather they should provide the name and number of the Acting Chief of
Professional Services, Chris Parsons. (646)-356-2173 chris_parsons@nps.gov
1.8 OCCUPANCY REQUIREMENTS FOR BUILDINGS
A. Existing Buildings
1. Full Government Occupancy: Government and visitors will occupy and be present in the
Statue Pedestal except during the 2 days of de-energized construction.
a. The Monument will be closed to visitors on the 2 days of de-energized work
1.9 WORK RESTRICTIONS
A. On-Site Work Hours:
1. Five Days a week (Monday through Friday), subject to limitations on deliveries and hours for passing through USPP security and generally 7:00am to 5:00pm
2. Hours are subject to the park’s seasonal hours of operation which will affect Contractor’s use of the visitor ferry and/or NPS staff boat to arrive and depart from Liberty Island.
3. Liberty State Park opens at 0600.
B. Deliveries and Staff transport
1. See attached “Guidelines for Park Access & Credentialing”
C. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation if applicable.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than one hundred ninety (190) days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s or designee’s written permission.
E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
STLI 258838 01 11 00 - 6
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. Identification Cards and Background Checks
1. See attached “Guidelines for Park Access & Credentialing” dated 5/13/15
1.11 SOILS INVESTIGATION REPORT
A. NONE
1.12 ADDITIONAL REPORTS
A. NONE.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
IN REPLY REFER TO:
United States Department of the Interior
NATIONAL PARK SERVICE
UNITED STATES PARK POLICE
New York Field Office Statue of Liberty National Monument
Liberty Island New York, New York 10004
December 3, 2018
Memorandum
To: All Contractors, Subcontractors, Concessionaires & Partners of the National Park Service
From: Captain Peter Culver
Liberty District Commander, United States Park Police
Subject: Guidelines for Park Access and Credentialing
The Statue of Liberty National Monument and Ellis Island Immigration Museum are American Icons of freedom, recognizable around the world. The United States Park Police provide law enforcement and security services at this National Park Service site. Access to this site is restricted and regulated by our “Guidelines for Park Access & Credentialing” plan. This comprehensive plan is designed to enhance security operations at the park. Your cooperation and adherence to these guidelines is required and appreciated.
Attachments (1) Guidelines for Park Access & Credentialing (revised 12/3/2018)
Revised 12/3/2018
Statue of Liberty N.M. & Ellis Island Guidelines for Park Access & Credentialing
The following rules and procedures shall guide all Contractors, Subcontractors, Concessionaires and Partners of the National Park Service through the process of obtaining a Park ID for authorized access to the Park.
Park Identification Cards
• A completed U.S. Park Police Identification Card Application & Background Check Request Form (attached) must be submitted to the U.S. Park Police (USPP) at least (2) weeks in advance of the employment or work start date. All ID applications shall be submitted to Mr. Douglas Osoba, U.S.
Park Police Administrative Assistant. The USPP Administrative Assistant’s desk is located inside the Ellis Island Police Office (EPO); see attached map. Direct contact: douglas_osoba@nps.gov Phone: 646-356-2121.
• All criminal history must be included on the form. Although the main concern of the USPP is serious criminal activity, and/or appearance on terrorist watch lists, omission of minor criminal incidents is a credibility issue which will delay approval and may be cause for denial. Intentionally providing false information in any way will result in denial of the application.
• Once the application is approved you will be required to arrange an appointment with the USPP
Administrative Assistant to have your photograph taken and ID card issued. You must come in person to EPO for this appointment. Digital photographs will not be accepted via email.
• ID cards will be valid for the anticipated term of the project or for a (1) year period for concessioners and long term contractors.
• A replacement ID card will not be issued unless the expired or damaged card is returned. If the ID card is lost or stolen a report must be immediately filed with the USPP. The USPP case number must be provided to the USPP Administrative Assistant prior to issuance of the replacement card.
• Short-term contractors & sub-contractors (requiring access for up to 7 calendar days) do not require a
Park ID, but will need to be placed on a list to obtain a day-pass at the service entrance. This can be accomplished by requesting access for non-NPS credentialed contractors or visitors through your NPS Project Manager or designated NPS point of contact. These requests will be routed to Ms.
Jennifer Getter, Confidential Assistant to the Superintendent, who will have the requests approved and added to the access list. Direct contact: Jennifer_Getter@nps.gov Phone: 646-356-2102.
• The day-pass program is designed to allow access to visitors and/or contractors who will be on site for a very brief period. If we identify that you are attempting to utilize the day-pass program for a period beyond (7) calendar days you will be removed from the list and prohibited from entering the park.
mailto:Jennifer_Getter@nps.gov
Be prepared to present your Park ID/day-pass to a USPP Officer or National Park Service (NPS) employee if you are in an area closed to the general public. Generally, the ID/day pass should be worn on an outer garment and kept readily visible at all times. You will also be required to present a Federal or State issued photo ID at the service entrance during the check-in & screening process.
Violations of this policy will be documented and relayed to your NPS point of contact.
Truck Deliveries & Access
Deliveries via Post IV can be arranged (7) days a week, between the hours of 0700 to 1400.
(48) hours advance notice is required.
Vehicles attempting to enter the Park through Post IV in Liberty State Park must be placed on the access log by your NPS point of contact. All concessionaires/project managers will have a designated person who will act as a single point of contact with the NPS. This individual will be responsible for properly completing the Post IV & Battery Park access request forms (attached) and providing these forms to the Confidential Assistant to the Superintendent prior to 1400 hours each day. The list for Monday will be submitted Friday afternoon along with any requests for weekend access.
All trucks must be equipped with a lift gate for canine access. The center isle of the truck must be left open to allow for a walkthrough. Delivery trucks cannot be overloaded, or the driver will be required to empty out the truck’s contents at Post IV for canine inspection. Some deliveries may not be easily screened (soil or cement for example) and an officer may need to be present when off-loaded.
The driver’s name, company name and receiving company or NPS point of contact must be provided.
Driver and all delivery personnel must carry a valid photo ID. The driver must have a bill of lading.
The time of delivery must be provided.
Armored vehicles must be on the Post IV access list. When an armored vehicle arrives at Post IV the driver must stop the vehicle and make contact with the USPP Officer. The driver must provide valid photo identification and open the back of the vehicle for a visual only inspection. At no time will the driver be asked to leave the vehicle unattended. Barring any exigent circumstance, a USPP Officer or canine team will not enter the armored vehicle. A canine team will conduct an exterior sweep of the vehicle.
There may be random inspections of departing motor vehicles & vessels.
All persons and bags are subject to search and canine inspection when entering or departing the park and at all times while on-site.
Unscheduled or late deliveries (whether by boat or Post IV bridge) will be denied access and turned away by USPP.
Barge Deliveries & Access
All barges & vessels will be screened by a USPP Canine Team prior to entering the maritime security zones or arriving at Liberty or Ellis Island. Be advised that unauthorized entry into the USCG security zones around the islands is a violation of law and punishable by appropriate law enforcement action including summons issuance and/or arrest. At no time should a vessel enter the security zone without permission. (See attached security zone map)
Emergency requests may be made by calling the 24 Hour USPP Dispatch Center at (718) 338-3988.
Deliveries by water, with a qualified need to go directly to Liberty or Ellis Island, must be arranged at least (48) hours in advance and are by strict appointment only.
Canine Sweep requests for off-site locations such as Miller’s Launch require dedicated personnel and will be considered on a case by case basis. Additional canine teams may be required to accommodate these requests. The NPS/USPP will provide a cost estimate to the contractor for services outside 0600-1400 or at locations other than Post IV (NJ), Liberty State Park (NJ), or Battery Park (NY) where canine teams are typically assigned. The contractor will be responsible for reimbursement of all expenses related to these special request sweeps. A minimum of (48) hours advance notice is required and a weekly summary of scheduled deliveries is preferred.
Canine sweeps for waterside deliveries may be conducted at a pre-arranged local boat ramp, marina or Miller’s Launch in Staten Island (NY). After the sweep is completed the vessel will either be escorted by The USPP Marine Patrol Unit (MPU) or be monitored on CCTV while entering the security zone. In some cases a USPP Officer may remain present on the barge while it is in transit to Liberty Island.
Prohibited Items
All firearms (even if licensed in a State) Air Guns, BB/Pellet guns & all ammunition Knives, machetes, and all bladed instruments All weapons including items that can be considered or used as weapons Self-defense items including stun guns and pepper spray/mace Bats, clubs and all striking instruments, including brass knuckles Flammable liquids, dangerous chemicals and aerosols are prohibited Alcohol and all narcotics/drugs are prohibited ALL Explosives including fireworks
*****You may be permitted to possess tools and other equipment specifically required for the project with the explicit consent of your NPS point of contact, who will be responsible for providing this information to the USPP*****
Restricted Areas
Contractors and subcontractors are only authorized to be on-site in a designated work zone. Individuals may not enter closed or restricted areas, or take park property as souvenirs. The vast majority of buildings and other park resources are historic in nature and therefore protected by ARPA
(Archeological Resource Protection Act). This Federal Law protects the resources against theft, destruction and vandalism. ARPA imposes severe penalties for these types of violations.
Parking
Parking on Ellis Island is limited and restricted. Contractors will be allotted parking permit hang tags per the contract documents. All vehicles must display the hang tag when on island and only park in designated areas if outside of the Contractor’s staging and laydown area. In general, Contractor parking will be restricted to the area north of the Baggage and Dormitory building. If additional parking is authorized, then the Contractor/Subcontractor vehicles are restricted to YELLOW parking spaces as designated by yellow wheel stops. At no time may any contractor vehicle park in a space with green, grey or black & white wheel stops, nor in any area designated by signage or striping as no parking. Violators of this policy will be issued summonses and may be towed at the owner’s expense. Parking in unauthorized areas is prohibited.
(See attached parking map).
The contractor is free to manage parking for itself and subcontractors within the designated staging and laydown area. The Contractor will need to coordinate swing space for parking or alternate off-site parking needed to accommodate parking. Any contractor vehicles that park in Liberty State Park must use the metered day lot off of Audrey Zapp Drive, located west of the Railroad Terminal building. Liberty State Park may allow parking in other locations if the Contractor coordinates with Liberty State Park management and pays the required permit fees. The National Park Service will not be liable for any fines if vehicle owners are ticketed or towed for illegal parking in Liberty State Park.
The Confidential Assistant to the Superintendent may authorize Post IV to issue a limited number of yellow “Visitor” parking placards for single day use for deliveries or other contract activities.
If an assigned parking placard is lost or stolen, a report must be immediately filed with the USPP.
Important Contact Numbers
Liberty Island/Ellis Island Dispatch & Command Center Phone: 646-356-2205
U.S. Park Police 24-hour Dispatch & Command Center
Phone: 718-338-3988
Mr. Douglas Osoba - U.S. Park Police Administrative Assistant douglas_osoba@nps.gov / Phone: 646-356-2121
Ms. Jennifer Getter - Confidential Assistant to the Superintendent jennifer_getter@nps.gov / Phone: 646-356-2102 mailto:douglas_osoba@nps.gov mailto:jennifer_getter@nps.gov
1) (a) Depending on your starting location, drive north or south on the New Jersey Turnpike to the Turnpike Newark Bay Extension (Exits 14 A-B-C) and head east on the Extension toward the Holland Tunnel.
(b) If you are coming west, through the Holland Tunnel to New Jersey, keep to the right for several blocks after you exit the tunnel in Jersey City. You will eventually come to signs directing you to the New Jersey Turnpike. Take this Turnpike road and pass through the first tollbooths then follow the instructions beginning with # 2 below.
2) Leave the Extension at Exit 14 B, bearing to the left immediately after passing through the tolls.
DO NOT drive over the bridge to your right!
3) Follow the signs to the Statue of Liberty/Ellis Island Ferry. You will quickly come upon a traffic circle where you will bear to the RIGHT, going past the circle and heading down Morris Pesin Drive, which is lined with flags. You will reach a barrier somewhat further along that road at which point you should turn left onto Freedom Way.
Directions to the Ellis Island Bridge & Post IV Security Checkpoint
4) Follow Freedom Way about 9/10th of a mile at which point you will see an asphalt drive turning off on your right with a sign saying “Ellis Island Deliveries / Authorized Vehicles Only,” with concrete barriers & a Police checkpoint further down in the direction of the island.
5) You should turn right and drive carefully & slowly along this road, because there are sometimes bicyclists, joggers, and pedestrians crossing the road. You must yield to pedestrians.
6) When you reach the guardhouse you must stop for inspection by the United States Park Police. The officer will ask you to present a photo ID and to raise the hood of your vehicle and also to look in your vehicle trunk. The private security guard at the guardhouse will check a list for your name, which has been placed there in anticipation of your arrival. He or she will ask you to fill out a temporary ID tag form to place on your clothes and may provide you with a temporary parking tag for your car.
DIRECTIONS TO THE USPP OFFICE (EPO) ON ELLIS ISLAND
The U.S. Park Police (USPP) Office is located on the second floor of the Power House Building
(Marked by yellow „X‟)
Maritime Security Zone – Liberty Island & Ellis Island (150 Yards)
Buoy “35”
Please contact Jennifer Getter, Confidential Assistant to the Superintendent if you have any questions regarding this form - (212) 363-3206 x101
NATIONAL PARK SERVICE
STATUE OF LIBERTY NATIONAL MONUMENT AND ELLIS ISLAND
POST IV VISITOR ACCESS FORM
REQUEST DATE (s): **
Please PRINT Clearly! √ Check all that apply
ARRIVAL
TIME LAST NAME FIRST NAME ORGANIZATION
VEHICLE MAKE/MODEL/
STATE/LICENSE # PA
RK
IN
G Pa rk in g pa ss re qu ire d!
DR
IV
ER
SH
U
TT
LE
(p as se ng er
DE
LI
VE
RY
W
AL
KI
N
G
Use a new form for additional names
NOTES:
Point of Contact Name/Department: Phone #/ Radio #: Date:
All requests must be submitted no later than 3:00 PM daily.
Form must be completely filled out. Any missing information may delay your visitor's entrance into Post IV.
* If parking, ALL vehicles must have a parking pass.
** If visitor(s) need access for more than one week, an application for an ID must be submitted to the USPP.
Please contact Jennifer Getter, Confidential Assistant to the Superintendent if you have any questions regarding this form - (646)356-2102
NATIONAL PARK SERVICE STATUE OF LIBERTY NATIONAL MONUMENT AND ELLIS ISLAND
Battery Park VISITOR ACCESS FORM
REQUEST DATE (s): **
Please PRINT Clearly!
BOAT
LAST NAME
FIRST NAME
ORGANIZATION
Use a new form for additional names
NOTES:
Point of Contact Name/Department: Phone #/ Radio #: Date:
Form must be completely filled out. Any missing information may delay your visitor's entrance.
** If visitor(s) need access for more than one week, an application for an ID must be submitted to the USPP.
STLI - 258838 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 Payment for the contract line items described below will be based on a mutually agreed upon percentage of work in place, whether by resource loaded schedule , observation of work, materials delivered and stored on site, or other verifiable means (such as dump tickets or supplier invoices etc).
A. Payment will be made at the contract lump sum price or the contract unit price as listed on the
Contract Price Schedule.
3.2 LIST OF CONTRACT LINE ITEMS
A. CONTRACT LINE ITEM NO. 1 – Replace Liberty Island Electrical Switchgear
1. Replacement of the Liberty Island electrical switchgear, including but not limited to:
a. Removal and offsite disposal of existing switchgear.
b. Fabrication and installation of 480v 800 amp switchgear. New switchgear must be custom built for this application and delivered in three cabinet sections. It is required that the sections be no deeper than 30 inches to accommodate doorways.
Must be signed and sealed by an electrical engineer licensed in the state of New York.
END OF SECTION 01 27 00
STLI - 258838 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Authority Having Jurisdiction (AHJ): An AHJ is an agency that has been granted legal authority over a location, action or resource. This authority includes the ability to issue a permit or other legal permission document.
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
STLI - 258838 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
STLI - 258838 01 31 00 - 3
3. Number of Copies: Submit one electronic copy of each submittal in PDF format.