ATT_1_140P8423Q0066_Project_Specifications_-_Construction_Drawings_-_PORE_Lighthouse_Paint_FY23.pdf

PDF 2 MB Posted

Attached to
REPAINT HISTORIC LIGHTHOUSE Point Reyes NS Federal contract opportunity
Solicitation number
140P8423Q0066
Issued by
Department of the Interior National Park Service

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope/Statement of Work (SOW)

Repaint the Historic Point Reyes Lighthouse

Package Number: PMIS-323979

140P8423Q0066

TABLE OF CONTENTS

POINT REYES NATIONAL SEASHORE

PORE 323979

REPAINT THE HISTORIC POINT REYES LIGHTHOUSE

CBS Contract Bid Schedule TOC Table of Contents

DIVISION 1 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 11 40 Work Restrictions 01 31 00 Project Management 01 33 23 Submittals Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities & Controls 01 73 40 Execution 01 77 00 Closeout Procedures

DIVISION 5 – METALS

05 90 00 Metal Repairs and Cleaning - Ventilators

DIVISION 7 – MOISTURE PROTECTION

07 92 00 Joint Sealants - Windows

DIVISION 9 – PAINTING - LIGHTHOUSE

09 90 00 Painting and Coating

DIVISION 9 – PAINTING – FOG SIGNAL BUILDING

09 90 10 Painting and Coating

ATTACHMENT A

Point Reyes Lighthouse – Photographs

ATTACHMENT B

Point Reyes Lighthouse – Drawings

ATTACHMENT C

Contractor’s Quality Control Form

ATTACHMENT D

Contractor’s Submittal Transmittal Form

ATTACHMENT E

Contractor’s Request For Information Form

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 1

DIVISION 1 GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK (SECTION 01 11 00)

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. General: All work outlined below will be performed under a single contract.

B. Project Location: Point Reyes National Seashore, California. The Point Reyes Lighthouse is approximately 20 miles west of park headquarters and the Bear Valley Visitor Center near the town of Olema, CA. The Lighthouse is accessed by 308 step-concrete stairways from the Lighthouse Visitor Center area above.

C. The Work consists of the following:

1. The Work includes repainting of the Lighthouse at the Point Reyes Light Station and related work, including:

i. Repair and repainting of the Lighthouse.

ii. Repairs to leaking window panels on the Lighthouse.

iii. Repairs to leaking ventilator shutters on the Lighthouse.

iv. Touch-up painting of the adjacent Fog Signal Equipment Building.

2. Note that all structures included in this project are considered historically significant and all work performed must meet The Secretary of the Interior’s Standards for the Treatment of Historic Properties.

3. All work to be completed under a single prime contract. See Definition of Contract Line items to clarify which scope items are bid options.

D. Due to weather conditions at the Lighthouse, all work to be completed during the most favorable weather conditions of September 1st to October 31st.

1.2 DEFINITION OF CONTRACT LINE ITEMS

A. Contract Line-Item No. 1 Repair and Repaint the Lighthouse. This item consists of repairs and rehabilitation of the Lighthouse per contract specifications including:

1. Prepare and repaint all painted exterior surfaces of the Lighthouse.

2. Prepare and touchup paint interior wrought iron studs and gutters at rust areas on the Second Gallery.

3. Payment will be made at the contract lump sum price.

B. Contract Line-Item No. 2 Repairs to leaking window panels on the Lighthouse Second Gallery. This item consists of repairs and rehabilitation of the Lighthouse per contract specifications including:

1. Install worker access and investigate source of water leaks at window panels.

2. Replace caulking at leaking window areas.

3. Payment will be made at the contract lump sum price.

C. Contract Line-Item No. 3 Repairs to leaking ventilator shutters on the Lighthouse Second Gallery. This item consists of rehabilitation of the ventilator shutters per contract specifications including:

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 2

1. Remove and recondition eight copper-alloy ventilators at bottom gutters of the Lighthouse Second Gallery.

2. Repair air gaps to cast iron at four ventilator gutters with metal epoxy filler.

3. Reinstall gutter ventilators with caulking on all edges.

4. Payment will be made at the contract lump sum price.

D. Contract Line-Item No. 4.: Bid Alternate A, Paint Fog Signal Building: This item consists of repairs and touch-up painting of the Fog Signal Building per contract specifications including:

1. Remove embedded rusting metal, treat metal, and patch wood surfaces.

2. Touchup paint of all repaired areas.

3. Payment will be made at the contract lump sum price.

1.3 REFERENCE DOCUMENTS / REPORTS

A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:

1. NPS Forms (RFI, CM-16, and QC Daily Report)

2. Site Location Map

3. Park Regulations

1.4 GOVERNMENT-FURNISHED ITEMS

A. Government-Furnished Items: No government furnished products or materials are anticipated for use on this contract.

1.5 PUBLIC / STAFF USE OF THE SITE

A. General: The upper Lighthouse area, including visitor center, overlook, and roads site will be open to the public and staff during construction. The contractor shall always conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer. The lower Lighthouse area project site will be closed to the public during the contractor’s on-site work period.

1.6 CONTRACTOR USE OF SITE

A. General: Limit use of the site during the construction period to the project area limits including the area immediately adjacent to the Lighthouse, Fog Signal Building, and Transformer Building in the lower Lighthouse area. In addition, one garage bay in the upper Lighthouse area will be designated for contractor’s storage. Contractor’s vehicle parking shall be in designated areas along the Lighthouse entry road and two spaces adjacent to the Lighthouse garage.

B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 3

C. Site Access: The contractor shall access the project site via the Lighthouse Road and permitted to enter site through the gate at main public parking area. Do not drive vehicles off road or access non-project areas without permission from the contracting officer or their representative.

D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until 5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer.

E. Staging and Storage: Confine the storage of equipment and materials to the staging / lay-down / storage areas as established at the preconstruction meeting.

F. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at 415-464-5170.

G. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

PART 2 – WORK RESTRICTIONS (SECTION 01 11 40)

2.1 WORK RESTRICTIONS

A. Vehicles / Heavy Equipment:

1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.

2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting.

3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles always.

4. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.

B. Natural Resource Protection:

1. General: The Park is committed to protecting natural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions.

2. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.

3. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 4 in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to entry into the park.

C. Cultural Resource Protection: The Point Reyes Light Station contains a lighthouse tower with first order Fresnel lens and several adjacent historic buildings that convey the history of a late 19th/early

20th century light station. The NPS manages the totality of this property as a cultural resource asset. Work must be approached with care and discretion to ensure that no harm, damage, or loss will result from direct or indirect actions taken by the Contractor. All work, unless noted otherwise, will be undertaken in compliance with the Secretary of the Interior’s Standards for Treatment of

Historic Properties, and in accordance with Guidelines for the Treatment of Cultural Landscapes.

Contributing Properties include, and are not limited to the Point Reyes Lighthouse, Fog Signal

Equipment Building, and Transformer Building. Preservation treatment approaches are preferred.

Contractor shall not use short cuts, unproven means and methods, new materials or systems, or non-traditional practices unless properly reviewed and approved in advance by the Contracting

Officer.

PART 3 – PROJECT MANAGEMENT (SECTION 01 31 00)

3.1 SUBMITTALS

A. Division 01 Submittal Documents: The following documents shall be submitted a minimum of one week prior to the Preconstruction Meeting. If all these documents have not been received one week prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until a written Notice to Proceed has been issued.

1. Letter designating the Project Superintendent.

2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final inspection date, and other major milestones.

Provide updates to baseline schedule as needed / requested during construction.

3. Schedule of Values (SOV) – Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.

4. Accident Prevention Plan (APP) – Submit an accident prevention plan with the name of the supervisor responsible for executing the plan, a job hazard analysis for each major work activity, first aid procedures, and planning for potential emergency situations.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

B. Division 05-09 Submittal Documents: The following documents shall be submitted to the Contracting Officer prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 5

1. Product Data – Submit product cut sheets / material data on all products to be used for approval. Indicate the size, model, or type of each recommended product.

2. Samples – When requested, submit a physical sample of a product or an array of color choices for approval.

3.2 PRECONSTRUCTION MEETING

A. Preconstruction Meeting: Before the start of construction, the Contracting Officer will arrange for a preconstruction meeting either onsite or via teleconference. The meeting agenda will include the following topics:

1. NPS Roles & Responsibilities

2. Key Contractor Personnel

3. Coordination with Subcontractors

4. Correspondence & Submittal Procedures

5. Submittals

a. Status of Division 01 Submittals

b. Schedule & Schedule of Values

c. Safety & Accident Prevention Plan

d. Status of Division 05-09 Submittals

6. Park Rules & Regulations

7. Work Hours and Weekend, Holiday, and Night Work

8. Project Information

a. Park Access

b. Jobsite Access & Parking

c. Staging, Storage, and Lay-down Area(s)

d. Temporary Facilities & Controls

e. Jobsite Restrictions

f. Resource Protection

g. Weather, Climate, Environmental Conditions

h. Reference Documents

i. Other Contracts / Ongoing Work

9. Labor Standards Provisions

10. Labor Interviews

11. Payroll Reports

12. Payments to the Contractor

13. Change Orders / Modifications

14. Progress Meetings

15. QC Daily Reports

16. Inspections

17. Acceptance and Rejection of Work

18. Closeout Procedures & Submittals

19. Contract Period of Performance

20. Notice to Proceed

3.3 REQUESTS FOR INFORMATION (RFIs)

A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit a RFI utilizing the form attached.

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 6

1. Contracting Officer will only respond to RFIs submitted by the Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, if applicable.

PART 5 – SAFETY REQUIREMENTS (SECTION 01 35 23)

1.1 SAFETY REQUIREMENTS

A. General:

1. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing construction work at the site.

2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.

3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.

4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

Store hazardous materials in accordance with manufacturers and OSHA recommendations.

Maintain SDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the contracting officer.

5. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.

6. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.

7. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall Dial 911 as needed. The Contractor shall also contact Park Dispatch at 415-464-5170 for any medical emergency, traffic accident, or personal injury occurring within the park. Park Dispatch is called so that any available Emergency Medical Services personnel in the park might respond until such time as the ambulance arrives.

PART 6 – QUALITY REQUIREMENTS (SECTION 01 40 00)

6.1 QUALITY REQUIREMENTS

A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 7

B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached. The submission frequency of the QC Daily Report to the contracting officer will be determined at the preconstruction meeting.

PART 7 – TEMPORARY FACILITIES & CONTROLS (SECTION 01 50 00)

7.1 TEMPORARY FACILITIES & CONTROLS

A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.

B. Temporary Utilities: The following utilities / services are available for use at the project site:

1. Electrical Power Service: Electrical power service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations.

2. Water Service: Potable water service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services with proper backflow prevention devices in compliance with AWWA standards and local regulations.

3. Sanitary Facilities: Restrooms are available at the upper Lighthouse area for use on the contract without charge. Please keep toilet clean so as not to add extra work for maintenance staff.

4. Telephone Cellular Service: The project site has limited spotty cellular service depending upon phone company.

C. Temporary Office and Storage: The construction of temporary office buildings or installation of trailers will not be allowed in the park.

1. The construction of temporary office buildings or installation of trailers will not be allowed in the park.

2. The Park will provide one bay of garage storage space at the upper area.

3. Contractor shall be permitted to use the transformer building and interior of Fog Signal Equipment Building in the lower area for storage of equipment and materials.

4. Contractor shall provide adequate protection of all surfaces for buildings used for storage and repair any damage.

PART 8 – EXECUTION (SECTION 01 73 40)

8.1 EXECUTION

A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.

B. Preparation: Take field measurements or conduct surveys to verify dimensions before fabrication or installation.

C. Installation: Install all systems or components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations.

PORE – 323979 DIVISION 1 – GENERAL REQUIREMENTS Page 8

D. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.

E. Progress Cleaning: Clean the project site and work area daily. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.

F. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.

PART 9 – CLOSEOUT PROCEDURES (SECTION 01 77 00)

9.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. When the project, or a designated portion of the project, is substantially complete, the Contractor shall request a final inspection in writing. Upon receipt of the written request that the project is substantially complete, the Contracting Officer will proceed with a final inspection within ten (10) days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

B. If the work is determined to be substantially complete at the final inspection, the Contracting Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final acceptance. The Contractor shall complete the work described in the Punch List within thirty (30) calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.

C. If the work is determined to be not substantially complete, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.

D. After all deficiencies have been corrected and the project is complete, a Letter of Final Acceptance will be issued by the Contracting Officer.

9.2 CLOSEOUT SUBMITTALS

A. Operation & Maintenance (O&M) Manual: Submit two (2) hard copies (in D-ring binders) and three

(2) compact disks (CDs) with all operation and maintenance information including but not limited to a preventative maintenance schedule, product / material cut sheets, progress photos, product warranties, and a one (1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.

PORE – 323979 DIVISION 05 90 00 – METALS Page 1

SECTION 05 90 00

METAL REPAIRS AND CLEANING

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. In-situ repair and rehabilitation of existing ventilator shutters.

B. Scope of historic treatment as follows:

1. Remove and clean eight existing copper-alloy ventilator shutters.

2. Cleaning of metal.

3. Removing corrosion.

4. Reinstall ventilator shutters with caulking on all edges.

1.2 RELATED REQUIREMENTS

A. Section 01 35 91 - Historic Preservation Treatment Procedures.

B. Section 07 92 00 - Joint Sealants

C. Section 09 90 00 - Painting and Coating.

PART 2 - PRODUCTS

2.1 FASTENERS

A. General: Fasteners of same basic metal as fastened metal unless otherwise indicated. Use metals that are noncorrosive and compatible with each metal joined. Match shape, size, and appearance of original fasteners.

1. For exposed fasteners, use machine screws of head profile flush with metal surface unless otherwise indicated.

2. Finish exposed fasteners to match finish of metal fastened.

2.2 MISCELLANEOUS MATERIALS

A. Filler for Small Losses in Iron and Steel: Two-part, metal filled epoxy resin manufactured for filling holes in metal. Provide following or Contracting Officer approved equal:

1. Belzona 1111 Super Metal, as manufactured by Belzona Inc., Miami, FL.

http://www.belzona.com.

PORE – 323979 DIVISION 05 90 00 – METALS Page 2

B. Water-Resistant Product: At all locations, provide formulation that is resistant to erosion from water exposure without needing protection by sealer or waterproof coating, and that is recommended by manufacturer for exterior use.

C. Sealant Materials:

1. Provide sealant complying with applicable requirements in Section 07 92 00 - Joint

Sealant.

2. Colors: Provide colors of exposed sealants to match finish colors of painted metals in which sealant is placed unless otherwise indicated.

D. Miscellaneous Products: Base selection of materials and methods of use on following, subject to approval of field samples:

1. Previous effectiveness in performing Work involved.

2. Little possibility of damaging exposed surfaces.

3. Consistency of each application.

4. Uniformity of resulting overall appearance.

5. Do not use products or tools that could do following:

a. Remove, alter, or in any way harm present condition or future preservation of surfaces, including surrounding surfaces not in contract.

b. Leave unintended residue on surfaces.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Prior to removal of existing metal elements, conduct field survey of dimensions, anchorage conditions and details for repairs and reinstallation of replacement fabrications.

3.2 METAL RESTORATION AND CLEANING

A. Removal of Entire Components: Remove copper-alloy ventilator shutters by carefully removing fasteners and separating components. Do not break components or use methods that might damage, warp, bend, or deteriorate components.

3.3 PREPARATION OF SURFACES

A. Bronze and Copper: Clean in accordance with SSPC-SP 1 - Solvent Cleaning and/or using fine wire brush or wool. Clean to remove all visible rust, dirt, salt, and other contaminants from surface.

3.4 REPAIR OF CAST IRON VENTILATOR BASE

PORE – 323979 DIVISION 05 90 00 – METALS Page 3

A. Repairs to Cast Iron ventilator bases:

1. Clean surfaces to be filled free of contaminants that might adversely affect adhesion or performance of filler. Scarify prime coat according to manufacturer's recommendations and apply to dry, clean surfaces.

2. Prepare and apply epoxy filler following manufacturer’s directions.

3. Fill voids and other openings in the six cast iron ventilator bases which may allow moisture penetration from wind-blown rain, with epoxy filler and surfacer after priming.

4. Allow to dry a minimum of 24 hours before top coating. Fill holes and losses to match adjacent planes and profiles. Finish surface to match texture of adjacent surface.

3.5 REINSTALLATION OF VENTILATOR SHUTTERS

A. Examination:

1. Examine each element for condition to ensure that each element has been properly repaired and prepared for installation or reinstallation.

2. Confirm that all necessary repairs have been completed on ventilator bases and elements have been painted and properly prepared for reinstallation of ventilator shutters.

3. Do not proceed with installation until discrepancies have been corrected.

B. Installation, General:

1. Reinstall ventilator shutters with sealant on all four edges to ensure uniform, continuous ribbon, without gaps or air pockets.

2. Do not allow sealant to overflow or spill onto adjoining surfaces or to migrate into voids of adjoining surfaces, particularly rough or sculptural textures. Promptly remove excess and spillage of sealant as work progresses.

2. Set each unit using new fasteners to secure element to supports. Do not force elements into position to damage coatings and finishes.

3. Ensure that all edges are flush and properly secured to eliminate air gaps.

END OF SECTION

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 1

SECTION 07 92 00

JOINT SEALANTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Provide ladders and/or scaffolding for safe worker access to upper window area.

B. Investigation and identification of water intrusion locations at window and cornice interface.

C. Application of exterior sealants at window cleats and joints in all failed leak areas.

1.2 RELATED DOCUMENTS

A. Attachment A: Lighthouse drawings.

B. Attachment B: Lighthouse photos.

1.3 REFERENCED STANDARDS

A. ASTM C920 - Standard Specification for Elastomeric Joint Sealants; 2014.

B. ASTM C1193 - Standard Guide for Use of Joint Sealants; 2016.

1.4 SUBMITTALS

A. See Section 01 33 23 - Submittal Procedures for submittal procedures.

B. Product Data: Provide data indicating sealant chemical characteristics, performance criteria, substrate preparation, limitations, and color availability.

C. Manufacturer's Installation Instructions: Indicate special procedures, surface preparation, and perimeter conditions requiring special attention.

D. Scaffolding Installation: Submit scaffolding installation method and design for approval.

Ensure methodology protects all historic lighthouse elements.

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing the Products specified in this section with minimum twenty years documented experience.

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 2

B. Elastomeric joint sealants shall be produced and installed to establish and to maintain watertight continuous seals without causing staining or deterioration of joint substrates.

C. Sealant manufacturer shall confirm in writing that all materials contacting the sealants, including joint backings, gaskets, spacers, and joint substrates, are compatible with the sealant to be installed. Schedule sufficient time to test these materials for compatibility with the sealant, as necessary. Compatibility tests shall be performed to the sealant manufacturer’s standards.

D. Sealant manufacturer shall confirm in writing the appropriate joint preparation and priming techniques required to obtain rapid, acceptable adhesion of the joint sealants to the joint substrates.

1.6 FIELD CONDITIONS

A. General: Contractor is responsible for complying with the manufacturer's requirements and requirements of this section, so as not to delay the project. In case of conflict, the most stringent requirements shall govern.

B. Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint sealant manufacturer or are below 40 deg F (5 deg C).

2. When joint substrates are wet.

3. Where joint widths are less than those allowed by joint-sealant manufacturer for applications indicated.

4. Where contaminants capable of interfering with adhesion have not yet been removed from joint substrates.

1.7 WARRANTY

A. Correct defective work within a one-year period after Date of Substantial Completion.

B. Warranty: Include coverage for installed sealants and accessories which fail to achieve watertight seal, exhibit loss of adhesion or cohesion, or do not cure.

PART 2 PRODUCTS

2.1 MATERIALS, GENERAL

A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer, based on testing and field experience.

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 3

B. VOC Content of Interior Sealants: Sealants and sealant primers used inside the weatherproofing system shall comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

1. Architectural Sealants: 250 g/L.

2. Sealant Primers for Nonporous Substrates: 250 g/L.

3. Sealant Primers for Porous Substrates: 775 g/L.

C. Colors: Provide color of exposed joint sealants to remain uncoated to match colors indicated by reference to manufacturer's standard designations.

2.2 JOINT SEALANTS

A. Provide products complying with ASTM C920, also with ASTM C1193 and tested under ASTM

C719.

B. Glazing, Weatherproofing and Perimeter Sealant: ASTM C920, Type S, Grade NS, Class 50;

single component elastomeric that accommodates joint movement of not more than 50 percent in both extension and compression for a total of 100 percent, use for weatherproofing, unless otherwise indicated.

1. Basis of Design product: Sika Corporation; Sikaflex-1a.

C. Metal Roofing and Flashings Sealant: ASTM C920, Type S, Grade NS, Class 100/50; single component elastomeric accommodating joint movement of not more than 100 percent in extension and 50 percent in compression for a total of 150 percent.

1. Basis of Design product: Sika Corporation; Sikaflex-1a.

2.3 JOINT SEALANT BACKING

A. General: Provide sealant backings and accessory materials, including primers, of material and type that are non-staining; are compatible with joint substrates, sealants, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

2.4 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint sealant manufacturer where required for adhesion of sealant to joint substrates indicated.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 4 harming in any way joint substrates and adjacent nonporous surfaces, and formulated to promote optimum adhesion of sealants with joint substrates.

C. Masking Tape: Non-staining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints, to mask off adjacent joint surfaces where sealant is not permanently intended to be applied.

PART 3 EXECUTION

3.1 INVESTIGATION FOR WATER LEAKS

A. Install ladders and/or scaffolding to provide safe worker access to the upper window area adjacent to the cast iron roof cornice. All work areas to be OSHA compliant for worker fall protection. Estimated vertical height is 28.5 feet from ground level.

B. Conduct water pressure test to identify source of windblown rainwater leakage at the upper edge of glass the windows at the joint with the roof cornice. There is approximately 40 lineal feet of perimeter joint at the window panel and cornice interface.

1. Leaks and stains from wind-blown rain appears to be predominantly located at the 16 vertical wrought iron studs which function as window mullions.

2. NPS staff using hose nozzle tests suggest the water leakage to be at the cornice and window intersection and following the wrought iron studs down to the lower levels.

3. Rust staining and water leakage into the Second Gallery gutters and the Ground Floor ceiling similarly suggest the leakage at the area of the upper window, cornice, and stud connection.

4. See attached drawing 10/A.3 for details on cast iron cornice, wrought iron stud, window glazing, and window cleat connections.

3.2 REPAIRS TO LEAKING AREAS

A. Based upon the Contractor’s water test, propose corrective actions for approval by the

Contracting Officer. Assume for contract bidding purposes that the areas to be repaired include the entire 48 LF of perimeter cornice and window interface. Assumed repairs to include:

1. Remove upper-window level copper alloy transom cleat.

2. Clean all surfaces and install new caulking in all identified failed areas.

3. Clean cleat and reinstall in bed of sealant.

4. Repaint all surfaces to match existing colors per Painting Section 09 90 00

3.2 PREPARATION

A. Verify that joint sizes and surfaces are free of defects and acceptable for installation of joint sealants.

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 5

B. Verify joint dimensions and shapes to ensure they are within the sealant manufacturer’s guidelines. Resolve any variances prior to installation. Do not proceed with sealant installation until the unsatisfactory conditions have been corrected.

C. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with recommendations of joint sealant manufacturer.

D. Completely remove existing sealant from joints taking care not to damage surfaces of adjacent materials.

E. Thoroughly clean the areas that the new sealant will contact using a de-greasing solvent such as toluene or xylene and the two-rag wipe technique. IPA (isopropyl alcohol) is not a de-greasing solvent. The new sealant should have a minimum contact area of 1/4”.

F. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

G. Clean metal, glass, and other nonporous surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

H. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.3 JOINT PRIMING

A. Prime joint substrates where indicated or where recommended by joint sealant manufacturer. Apply primer to comply with joint sealant manufacturer's recommendations.

B. Confine primers to areas of joint sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Allow primer to dry. Do not prime areas that cannot be sealed the same day.

3.4 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint sealant manufacturer's printed installation instructions applicable to products and applications indicated, except where more stringent requirements apply.

PORE – 323979 DIVISION 07 92 00 – JOINT SEALANTS Page 6

B. Sealant Installation Standard: Comply with recommendations of ASTM C1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

C. Installation of Sealants: Install sealants by proven techniques that result in sealants directly contacting and fully wetting joint substrates, completely filling recesses provided for each joint configuration, and providing uniform, cross-sectional shapes, and depths relative to joint widths that allow optimum sealant movement capability.

D. Tooling of Non-sag Sealants: Immediately after sealant application and prior to time skinning or curing begins, tool sealants to form smooth, uniform beads of configuration indicated, to eliminate air pockets, and to ensure contact and adhesion of sealant with sides of joint. Remove excess sealants from surfaces adjacent to joint. Do not use tooling agents that discolor sealants or adjacent surfaces or are not approved by sealant manufacturer.

E. Provide concave joint configuration per Figure 5A in ASTM C1193, unless otherwise indicated.

3.6 CLEANING

A. Clean off excess sealants or sealant smears adjacent to joints as work progresses by methods and with cleaning materials approved by manufacturers of joint sealants and of products in which joints occur.

B. Leave finished work in a neat, clean condition with no evidence of spillovers onto adjacent surfaces.

3.7 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating substances or from damage resulting from construction operations or other causes so that they are without deterioration or damage at time of Substantial Completion.

B. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so that and installations with repaired areas are indistinguishable from original work.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 1

SECTION 09 90 00

PAINTING AND COATING - LIGHTHOUSE

PART 1 – GENERAL

1.1 SECTION INCLUDES

A. Surface preparation.

B. Field application of paints and high-performance coating systems.

C. Scope: Finish all exterior surfaces exposed to view and Second Gallery interior mullions and gutters, unless fully factory-finished and unless otherwise indicated, including the following:

1. All exterior ferrous metal elements:

a. Cast and wrought iron.

b. Steel.

2. Interior mullion and gutters in Second Gallery.

a. Spot touch-up of interior mullions and gutters where rust stained.

2. Exterior non-ferrous metal elements:

a. Copper and copper-alloy elements, primarily window cleats.

b. NOTE: copper roof and ventilator ball not included in repainting.

3. Do Not Paint or Finish the Following Items:

a. Items fully factory-finished unless specifically so indicated, materials and products having factory-applied primers are not considered factory finished.

b. Items indicated to remain unfinished.

c. Glass

d. Copper roof and ventilator ball.

1.2 RELATED REQUIREMENTS

A. Section 05 90 00 - Ventilator Repairs.

B. Section 07 92 00 – Joint Sealants.

1.3 DEFINITIONS

A. Conform to ASTM D16 for interpretation of terms used in this Section.

B. Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D523.

C. Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D523.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 2

1.4 REFERENCE STANDARDS

A. 40 CFR 59, Subpart D - National Volatile Organic Compound Emission Standards for

Architectural Coatings; U.S. Environmental Protection Agency; current edition.

B. ASTM D16 - Standard Terminology for Paint, Related Coatings, Materials, and Applications;

2012.

C. SSPC-PA1 - Shop, Field, and Maintenance Painting of Steel.

D. SSPC-PM1 - Good Painting Practice: SSPC Painting Manual, Vol. 1; Society for Protective

Coatings; Fourth Edition.

1.5 SUBMITTALS

A. See Section 01 33 23 - Submittal Procedures, for submittal procedures.

B. Product Data: Provide complete list of all products to be used, with following information for each:

1. Manufacturer's name, product name and/or catalog number, and general product category.

2. MPI product number (e.g. MPI #47).

3. Cross-reference to specified paint system(s) product is to be used in; include description of each system.

4. VOC content.

5. Manufacturer's installation instructions.

C. Samples for Initial Selection: Submit three paper "draw down" samples, 8-1/2 by 11 inches in size, illustrating range of colors available for each finishing product specified.

1. Where color is specified to match existing, submit samples in color custom matched to existing.

2. Where sheen is specified, submit samples in only that sheen.

3. Where sheen is not specified, discuss sheen options with Contracting Officer before preparing samples, to eliminate sheens not required.

D. Certification: By manufacturer that all paints and coatings comply with VOC limits specified.

E. Manufacturer's Instructions: Indicate special surface preparation procedures.

F. Maintenance Data: Submit data including product technical data sheets, material safety data sheets (MSDS), care and cleaning instructions, touch-up procedures, repair of painted and coated surfaces, and color samples of each color and finish used.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 3

G. Maintenance Materials: Furnish the following for Contracting Officer's use in maintenance of project.

1. Extra Paint and Coatings: 1 gallon of each finish coat; store where directed.

2. Label each container with color in addition to manufacturer's label.

H. Qualifications Data for applicator and testing and inspection agency.

I. Substitution Requests: Not permitted as paint is to match existing paint manufacturer’s system.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing the products specified, with minimum 10 years documented experience.

B. Applicator Qualifications: Company specializing in performing the type of work specified with minimum 10 years documented experience.

C. Testing and Inspection Agency Qualifications: NACE Coating Inspector Certified.

D. Finish Coat Performance Criteria:

1. Hardness Requirement: ASTM D3363. No gouging or scratching with an HB or less pencil.

2. QUV Exposure Requirement: ASTM D4587. No blistering, cracking, chalking or delamination of film. No less than 80% gloss retention, no more than 5.8 units gloss loss and 2.66 DE00 color change (white) after 5,000 hours exposure.

3. Corrosion Resistance Requirement: ASTM B117. No blistering, rusting or delamination of film. No more than1/64-inch rust creepage at the scribe after 2,500 hours exposure. (TR6297)

1.7 MOCK-UP

A. General: Apply mockups of each coating system indicated to verify preliminary selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

B. Contracting Officer will select one surface to represent surfaces and conditions for application of each coating system specified.

C. Final approval of color selections will be based on mock-ups.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 4

D. If preliminary color selections are not approved, apply additional mock-ups of additional colors selected by Contracting Officer at no added cost to NPS.

E. Approval of mock-ups does not constitute approval of deviations from Contract Documents contained in mock-ups unless Contracting Officer specifically approves such deviations in writing.

F. Subject to compliance with requirements, approved mockups may become part of completed

Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver products to site in sealed and labeled containers; inspect to verify acceptability.

B. Container Label: Include manufacturer's name, type of paint, brand name, lot number, brand code, coverage, surface preparation, drying time, cleanup requirements, color designation, and instructions for mixing and reducing.

C. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained between 45-to-90-degree F.

1. Maintain containers in clean condition, free of foreign materials and residue.

2. Remove rags and waste from storage areas daily.

1.9 FIELD CONDITIONS

A. General: Contractor is responsible for complying with manufacturer's written requirements and requirements of this Section, so as not to delay Project. In case of conflict, most stringent requirements shall govern.

B. Do not apply materials when surface and ambient temperatures are outside temperature ranges required by paint product manufacturer.

C. Do not apply coatings when relative humidity exceeds 85 percent; at temperatures less than

5-degree F above the dew point; or to damp or wet surfaces.

D. Do not apply exterior coatings in snow, rain, fog, or mist.

E. Do not apply exterior coatings if wind velocity exceeds 15 mph.

F. Follow manufacturer's recommended procedures for producing best results, including testing of substrates, moisture in substrates, and humidity and temperature limitations.

1.10 WARRANTIES

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 5

A. Provide coating manufacturer’s 15-year warranty for color, gloss, chalking, blistering, checking and delamination from substrate.

B. Provide one-year workmanship warranty for paint application.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. General:

1. Provide all paint and coating products used in any individual system from same manufacturer.

2. Provide all paint and coating products from same manufacturer to greatest extent possible.

3. Primer Sealers: Same manufacturer as topcoats.

B. Basis-of-Design for Paints for Ferrous and Non-Ferrous Metal Surfaces:

1. Tnemec Company, Inc., Kansas City, MO., www.tnemec.com.

Local representative: Amos and Associates, Inc. – Carl J. Bowers – 866-317-3206.

2.2 PAINTS AND COATINGS, GENERAL

A. Paints and Coatings shall be ready-mixed, unless intended to be field-catalyzed coating.

B. Where MPI paint numbers are specified, provide products listed in Master Painters Institute

Approved Product List, current edition available at www.paintinfo.com, for specified MPI categories, except as otherwise indicated.

C. Provide paints and coatings of a soft paste consistency, capable of being readily and uniformly dispersed to a homogeneous coating, with good flow and brushing properties, and capable of drying or curing free of streaks or sags.

D. Provide materials for use within each coating system that are compatible with one another, and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

E. For each coat in a coating system, provide products recommended in writing by manufacturers of topcoat for use in coating system and on substrate indicated.

F. For opaque finishes, tint each coat including primer coat and intermediate coats, one-half shade lighter than succeeding coat, with final finish coat as base color.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 6

G. Supply each coating material in quantity required to complete entire project's work from a single production run.

H. Do not reduce, thin, or dilute coatings or add materials to coatings unless such procedure is specifically described in manufacturer's product instructions.

I. Volatile Organic Compound (VOC) Content:

1. Architectural paints and coatings shall comply with VOC limits in Table 1 of ARB

Architectural Coatings Suggested Control Measure unless more stringent local limits apply.

2. Determination of VOC Content: Testing and calculation in accordance with 40 CFR

59, Subpart D (EPA Method 24), exclusive of colorants added to a tint base and water added at project site; or other method acceptable to authorities having jurisdiction.

J. Flammability: Comply with applicable code for surface burning characteristics.

K. Colors: As selected by Contracting Officer from manufacturer's standard range.

2.3 PRIMERS:

A. All Ferrous Metals:

1. Tnemec Tneme-Zinc Series 394 (Zinc-Rich Primer).

B. All Non-Ferrous Metals with Opaque Finish:

1. Tnemec Series 69F Hi-Build Epoxoline.

2.4 BASE (INTERMEDIATE) COAT:

A. All Ferrous and Non-Ferrous Metals:

1. Tnemec Series 1095 Endura-Shield.

2.5 FINISH COAT:

A. All Ferrous and Non-Ferrous Metals:

1. Tnemec Series 1095 Endura-Shield.

2.7 FINISHES, GENERAL

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

PORE – 323979 DIVISION 09 90 00 – PAINTING LIGHTHOUSE Page 7

B. Appearance of Finished Work: Noticeable variations in adjacent areas are not acceptable.

2.10 SOURCE QUALITY CONTROL

A. Contractor to provide supply Third-party NACE-certified Industrial Coating Inspection Service to perform tests for compliance with product requirements, B. Contracting Officer may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying coating materials from Project site, pay for testing, and recoat surfaces coated with rejected materials.