PROJECT NAME: A3 and Unit 26 WCS ENGR. PROJECT NO.: 21-051

LOCATION: Quivira NWR CONTRACT NO.:

CONTRACTOR:

Spec.

Section

Number

Spec.

Paragraph

No. Comments

012900 1.2.A.1

013100 1.3

013200 2.1

017700 1.3

017419 1.3 Waste Management Plan

313215 2.1 Culvert Sand Bedding

033000 1.3 Silica Dust Protection Plan

033000 2.6

033000 2.8

033000 3.6 Concrete Curing Materials and Plan

033000 3.2

033000 3.2

334100 2.1

Closeout Submittals

PROJECTED SUBMITTAL LIST

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Schedule of Values

Subcontract list and information

Construction schedule

Concrete Mix

Reinforcing Steel

Epoxy

PVC Culvert and Connection / Adhesive Per Manufacturer's Recommendations

Grout Mix

A - Approved as Submitted.

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

D - No Action Taken. See Comments. Resubmission Required.

E - disapproved. See Comments. Resubmission Required.

CONTRACTOR:

Spec.

Section

Number

Spec.

Paragraph

No. Comments

PROJECTED SUBMITTAL LIST

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Schedule of Values

A - Approved as Submitted.

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

CONTRACTOR:

Spec.

Section

Number

Spec.

Paragraph

No. Comments

PROJECTED SUBMITTAL LIST

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Schedule of Values

A - Approved as Submitted.

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.