Atch_2_SOW_Div_2_thru_49.pdf
PDF 2 MB Posted
- Attached to
- SCBL Upgrade Maintenance Fire and Security Alarm S Federal contract opportunity
- Solicitation number
- 140P6324Q0014
About this file
This document appears to be a government solicitation for upgrading and maintaining the fire and security alarm system at Scotts Bluff National Monument. The key details are:
The solicitation is a Request for Quotes (RFQ) issued by the Department of the Interior, National Park Service Midwest Region. The overall objective is to upgrade and maintain the fire and security alarm system at the Scotts Bluff National Monument site. Specific products and services required include conduit, wiring, connectors, grounding and bonding, supports, and installation. The solicitation references technical specifications for the electrical work, as well as requirements for submittals, warranties, training, and project coordination. No set-asides or pricing terms are provided. The solicitation number is 140P6324Q0014, and responses are due by the date specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6324Q0014_Amd_0002.pdf | ||
| Atch_7_Site_Visit_Sign-in_Sheet_0002.pdf | ||
| Atch_6_Questions_and_Answers_0002.docx | DOCX document | |
| Sol_140P6324Q0014_Amd_0001.pdf | ||
| Atch_3_SOW_Drawings-8_pages_0001.pdf | ||
| Atch_4_Experience_Questionnaire.xls | XLS spreadsheet | |
| Atch_1_SOW_Div_1.pdf | ||
| Atch_3_SOW_Drawings.pdf | ||
| Sol_140P6324Q0014.pdf | ||
| Atch_5_DOL_Wage_Determination_NE20240079.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCBL 227334 145-091 06 10 00-1
DIVISION 6 – WOOD, PLASTIC AND COMPOSITES
SECTION 06 10 00
ROUGH CARPENTRY
PART 1 - GENERAL
1.1 RELATED WORK SPECIFIED ELSEWHERE
1.2 REFERENCES
1.3 QUALITY ASSURANCE
A. Comply with PS 20 and with applicable rules of the respective grading and inspecting agencies for species and products indicated. Comply with PS 1-74 (ANSI 199.1) or, for products not manufactured under PS 1-74 provisions, with applicable APA Performance Standard for type of panel indicated. Identify each plywood panel with the appropriate APA Trademark. All stress grades and stress criteria shall be based on the National Design Specifications for Wood Construction, latest edition.
1.4 SUSTAINABILITY REQUIREMENTS
A. Adhesives and sealants that comply with the following requirements:
1. Adhesives, sealants and sealant primers must comply with the South Coast Air Quality
Management District (SCAQMD) Rule #1168, which limits their VOC content by product type.
2. Aerosol adhesives must comply with Green Seal Standard for Commercial Adhesives GS-36 requirements in effect October 19, 2000.
1.5 STORAGE
A. Store rough carpentry materials on bunks or skids at least 6 inches above the ground, and protect materials from weather with waterproof covers.
1.6 JOB CONDITIONS
A. Fit carpentry work to other work; scribe and cope as required for accurate fit. Correlate location of furring, nailers, blocking, grounds, and similar supports to allow proper attachment to other work.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Lumber shall be S4S, kiln dried, with 19 percent maximum moisture content at time of dressing. Lumber shall be grade stamped in accordance with the latest edition of the standard grading rules of NELMA, SPIB, WCLIB, WWPA or NLGA (or equivalent Canadian governing authority).
2.2 MISCELLANEOUS PLYWOOD
A. Electrical/Telephone Backing Panels: C-D Plugged, Exposure 1 plywood, fire-retardant treated, ¾-inch thick.
B. Miscellaneous panels: C-D Plugged, Exposure 1 plywood, fire-retardant treated, 5/8-inch thick
2.3 MISCELLANEOUS MATERIALS
A. Fasteners and anchorages shall be of the size, type, material and finish as indicated below or on the Drawings and as recommended by applicable standards complying with applicable Federal Specifications for nails, (staples), screws, bolts, nuts, washers and anchoring devices. Metal anchors shall be of the size and type recommended by the manufacturer for each use. Where rough carpentry work is exposed
SCBL 227334 145-091 06 10 00-2
to the weather, in ground contact, or in areas of high humidity, provide fasteners and anchorages with a hot-dip zinc coating (ASTM A 153).
B. Adhesives shall conform to Specification AFG-01 of the American Plywood Association.
PART 3 - EXECUTION
3.1 MISCELLANEOUS WOOD BLOCKING
A. Erect miscellaneous blocking as shown on the Drawings or as required to secure materials to rough construction.
3.2 CONCEALED BLOCKING
A. Wood blocking shall be nominal 2" thick and secured to structural members for the anchorage of all surface-mounted items. Blocking shall be provided and installed as recommended by the manufacturer of the product to be mounted on the wall. Blocking shall be installed for, but not limited to, the following items:
1. Panels, equipment and other wall mounted items to be mounted in new and existing construction.
3.3 INSTALLATION OF TREATED WOOD
A. Provide pressure-treated wood where framing lumber is in contact with concrete. Field cuts shall be coated with a concentrated solution of preservative treatment.
B. Treated lumber shall be anchored in place using concrete nails at 24” O.C.
3.4 ALLOWABLE TOLERANCES
A. The following tolerances establish the range of acceptable variances. Assure that work outside this range is removed; act to prevent reoccurrence.
1. Lumber
a. Straightness, no bows exceeding 0.1%, i.e., 1/8-inch in 10 feet, 1/16-inch in 5 feet.
b. No twisted or split lumber allowed.
c. Moisture content not to exceed 14% when installed.
END OF SECTION
SCBL 227334 145-091 07 92 00-1
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07 92 00
JOINT SEALERS
1.1 RELATED WORK SPECIFIED ELSEWHERE
Joint Sealers in Electrical and Communications Work Divisions 26, 27 & 28
1.2 SUSTAINABILITY REQUIREMENTS
A. For field applications that are inside the weatherproofing system, use adhesives and sealants that comply with the following requirements:
1. Adhesives, sealants and sealant primers must comply with the South Coast Air Quality
Management District (SCAQMD) Rule #1168, UL2818 (Greenguard) Gold or Scientific Certification Systems Global Services Indoor Advantage Gold.
1.3 GENERAL PERFORMANCE
A. Joint sealers, except as otherwise indicated, are required to establish and maintain airtight and waterproof continuous seals to the substrates they will be applied to in this project on a permanent basis, within recognized limitations of wear and aging as indicated for each application. Failures of installed sealers to comply with this requirement will be recognized as failures of materials and workmanship.
B. Sealants shall be compatible for use with each joint substrate used on this project in accordance with sealant manufacturer’s documented recommendations for each application.
1.4 SUBMITTALS
A. Color samples shall be submitted in accordance with Section 01 33 23. Samples shall be strips of actual caulking. Paper samples will not be acceptable.
B. Submit test reports indicating compatibility of joint sealers with exact materials being used on this project in accordance with Section 01 33 23.
1.5 JOB CONDITIONS
A. Sealants shall be installed on dry days preferably with temperatures between 40 deg. F and 75 def. F, but in no case shall sealants be installed when temperatures are below 40 deg. F or above 90 deg. F.
B. Special care shall be exercised to prevent damage to adjacent work during installation of sealants.
C. Sequencing:
1. Install sealant adjacent to painted surfaces before adjacent surfaces receive their final coat of paint.
2.1 SEALANTS
A. Multi-Purpose Silicone Sealant (Type S-1):
1. Pecora Corp.: PCS
2. BASF/Sonneborn:
SCBL 227334 145-091 07 92 00-2
3. Sika Corp: Sika WS-305 CN
4. Dow Corning: CWS Contractors Weatherproofing Sealant
B. Acrylic-Emulsion Sealant (Type S-2):
1. Pecora Corp: AC-20
2. Sika Corp: Acrylic
3. Tremco, Inc.: Tremflex 834
C. Mildew-Resistant Silicone Sealant (Type S-4):
1. Pecora Corp.: 860
2. General Electric: SCS 1700
3. Sika Corp: Sika Sil N Plus
4. Tremco: Tremsil 200
5. Dow Corning: 786 Mildew Resistant
D. Mildew Resistant Neutral Curing Silicone Sealant (Type S-4A):
1. Pecora: 898 NST
E. Urethane Sealant for Joints Subjected to Traffic (Type S-5):
1. Pecora Corp.: NR-21
2. Sika Corp: Sika Flex 1C SL
3. Tremco: Vulkem 45SSL
4. BASF/Sonneborn: MasterSeal SL 1
F. Silicone Sealant for Joints Subjected to Traffic (Type S-5A)
1. Pecora Corp.: 300 SL, 301 NS
2. Tremco: 900, 800
3. Dow Corning: 890 SL, 888 NS
G. Firestopping sealant (Type S-7) for use at all penetrations through fire-rated walls, at tops of such walls, and at smoke-resistance-rated floors and walls shall be CP25WB Sealant, MPS-2 and MMP-4S putty and other accessories as manufactured by 3M Corp., or equivalent products manufactured by RectorSeal Corporation, Bio Fireshield, Tremco, Specified Technologies, Johns Manville, or United States Gypsum Co. Provide proper product at each appropriate location.
H. Acoustical sealant (Type S-8) for use at certain GWB partitions (as shown on Drawings) shall be one-component, Butyl Rubber Base sealant, aluminum gray color, and shall be Acoustical Sealant BA-98 manufactured by Pecora Corporation, or approved equal.
2.2 SEALANT LOCATION TYPE
S-1 Exterior, except joints subject to traffic S-2 Interior, except expansion joints in exterior walls and as noted below S-4 Interior joints around plumbing fixtures and countertops S-4A Interior joints around plumbing fixtures and countertops S-5 Joints subject to traffic S-5A Joints subject to traffic S-7 For firestopping at fire-rated construction S-8 At penetrations thru sound-resistant construction
2.3 MISCELLANEOUS MATERIALS
A. Provide the sealant manufacturer's recommended type of joint primer for joint surfaces to be primed.
Verify with the sealant manufacturers which materials require priming for each of the sealants used.
B. Bond breaker, where required to break the bond between sealant and the back-up material or joint filler, shall be a tape material recommended by the sealant manufacturer, or shall be polyethylene film.
SCBL 227334 145-091 07 92 00-3
C. Provide glass fiber roving, neoprene, butyl, polyurethane, or polyethylene foams free from oil or other staining elements as recommended by sealant manufacturer. Provide 25 to 33 percent oversized backing for closed cell material and 40 to 50 percent oversized backing for open cell material, unless otherwise indicated. Provide backstop material that is compatible with sealant. Do not use oakum or other types of absorptive materials as backstops.
D. Cleaning solvents shall be type(s) recommended by the sealant manufacturer and in accordance with applicable environmental requirements. Protect adjacent glass, aluminum and bronze surfaces from solvents.
3.1 INSPECTION
A. Installer must examine substrates (joint surfaces) and conditions under which joint sealer work is to be performed, including joint width tolerances, and must notify Contractor in writing of unsatisfactory conditions. Do not proceed with joint sealer work until unsatisfactory conditions have been corrected in a manner acceptable to installer.
3.2 PREPARATION
A. Clean down joint surfaces using oil-free solvent for metal, glass, and other non-porous surfaces.
Surfaces to receive sealant shall be sound, clean and dry, and free of frost, laitance, curing compounds, waterproofing compounds, mastic compounds, corrosion, mill scale, rust, oil, tar, wax, paint, mastic, and similar contaminates.
B. Sandblast concrete in contact with form release agents.
C. Prime concrete, masonry, wood and similar porous surfaces. Brush out excess material to ensure a uniform film over the joint face. Allow primer to dry out before applying sealant.
D. Mask adjacent areas as necessary to obtain a neat sealant line.
3.3 INSTALLATION
A. Comply with the manufacturer's documented instructions except where more stringent requirements are shown or specified, and except where manufacturer's technical representative directs otherwise.
B. Mix two-part sealants by mixing the activator with the resin uniformly and thoroughly, in the proportions supplied to meet the recommendations of the sealant manufacturer. Sealant shall be mixed in a mechanical mixer, except very small amounts may be hand mixed with a trowel.
C. Clean out loose particles from joints immediately prior to application of primer. Apply primer to joints in concrete masonry units, wood, and other porous surfaces in accordance with sealant manufacturer’s documented instructions. Do not apply primer to exposed finished surfaces.
D. Install backer rod with a blunt rod or plain faced roller. Recess into joint to meet the sealant manufacturer's recommendations for joint width and depth ratio. Do not puncture, fold, twist, or crease backer rod.
E. Install bond breaker where sealant would otherwise bond to backer rod or joint filler.
F. Do not allow sealants or compounds to overflow from confines of joints, to spill onto adjoining work, or to migrate into voids of exposed finishes. Clean adjoining surfaces by whatever means may be necessary to eliminate evidence of spillage.
SCBL 227334 145-091 07 92 00-4
G. Install sealants in uniform, continuous ribbons without gaps or air pockets, with complete "wetting" of joint bond surfaces equally on opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly concave surface slightly below adjoining surfaces.
H. Where horizontal joints are between the horizontal surface and vertical surface, fill joint to form a slight cove, so that joint will not trap moisture and dirt.
I. Apply non-self-leveling sealants by holding the gun nozzle at an angle of about 45 degrees and move steadily along the joint so that a uniform bead is applied without dragging, tearing, or leaving unfilled spaces. Push the bead rather than draw it with the gun leading. Fill joints in vertical surfaces level with adjacent surfaces and tool within ten minutes of application with one continuous stroke to insure intimate contact with the joint surfaces, to remove any trapped air or voids, to consolidate material, and to provide a neat, uniform, appearance. Fill joints in horizontal surfaces holding the top surface of the sealant slightly below the adjacent surfaces.
J. Install self-leveling sealants to a depth equal to 75 percent of joint width but neither more than 5/8-inch deep or less than 3/8-inch deep as recommended by sealant manufacturer. Pour sealant into joints and fill to within 1/16-inch of adjacent surfaces, exercising care not to spill sealant on such surfaces. Refill any areas where sealant seeps out of joint through the expansion joint filler before sealant sets up.
3.4 CLEANING AND PROTECTION
A. Remove masking immediately after application and tooling operations are complete. Clean excess or spilled sealant from non-porous surfaces with solvent before curing. Clean excess or spilled sealant from porous surfaces with abrasive or mechanical means after curing.
B. Protect sealant where bituminous material is to be applied over thermosetting joint sealant with vinyl or polyethylene sheet material.
C. Cure sealants in compliance with manufacturer's instructions and recommendations to obtain high early bond strength, internal cohesive strength and surface durability. Advise Contractor of procedures required for cure and protection of joint sealers during construction period, so that they will be without deterioration or damage (other than normal wear and weathering) at time of Substantial Completion.
Replace or restore sealants which are damaged or deteriorated during construction period.
3.5 SCHEDULE OF SPECIAL SEALANT COLORS
A. Special sealant colors shall be as follows:
At perimeter of exterior wall openings Match adjacent colors At joints between wall & other surfaces Match wall color At miscellaneous locations shown on the Drawings Standard color to most closely match adjacent colors
SCBL 227334 09 29 00-1
SECTION 09 29 00
GYPSUM DRYWALL
1.1 WORK SPECIFIED
A. Use gypsum drywall where required to patch/repair existing abandoned, new &/or modified openings in interior gypsum walls & ceilings.
1.2 QUALITY ASSURANCE
A. On faces of work exposed in occupied spaces, limit offsets between planes of board faces to 1/8-inch, and limit variations from plumb and location (including warp and bow) not to exceed 1/4-inch in 8'-0".
1.3 SUSTAINABILITY REQUIREMENTS
B. Use adhesives and sealants that comply with South Coast Air Quality Management District (SCAQMD) Rule #1168, which limits their VOC content by product type.
1.4 DELIVERY, STORAGE AND HANDLING
A. Gypsum drywall shall not be delivered to the project site until immediately before application begins. All gypsum drywall materials shall be delivered in original packages, containers or bundles bearing brand name and identification nomenclature.
B. Gypsum drywall shall be stored inside under cover and stacked flat in a manner to keep material flat, dry, protected from weather, direct sunlight, surface contamination, traffic or other construction damage.
Other materials and accessories shall remain in their original wrappings or containers, stored flat and protected from weather damage and bending until ready for actual use.
C. Handle materials in a manner to prevent damage to edges, ends or surfaces. Damaged materials or accessories shall not be incorporated within the work and shall be immediately removed from the site.
1.5 JOB CONDITIONS
A. Comply with requirements of referenced gypsum board application standards and recommendations of gypsum board manufacturer for environmental conditions before, during and after application of gypsum board.
B. When outside temperatures are below 55 deg. F, maintain continuous interior temperature in the range of
55 deg. F to 70 deg. F for minimum period of 48 hours prior to, during, and following application of gypsum board and joint and finishing treatment materials or bonding of adhesives.
C. Ventilate building spaces as required to remove water in excess of that required for drying of joint treatment material immediately after its application. Avoid drafts during dry, hot weather to prevent too rapid drying.
D. Protect all adjacent surfaces and work by suitable means from splatter or overspray from texture surface application (if any).
SCBL 227334 09 29 00-2
2.1 GYPSUM BOARD
A. Moisture resistant gypsum board (All applications) shall conform to ASTM E136, shall be 1/2-inch thick (unless noted otherwise on the Drawings) regular board with tapered edges, and shall be one of the following (or approved equal):
1. G-P toughrock Mold-guardboard* Georgia-Pacific
2. Gold Bond XP Gypsum Board National Gypsum
3. Sheetrock Ultralight Panels Mold Tough* United States Gypsum
2.2 JOINT TREATMENT
A. Joint treatment shall be paper reinforcing tape and ready-mixed vinyl-type compound by the same manufacturer as the wallboard, except use fiberglass tape at moisture-resistant GWB, and shall meet ASTM C475 and C840 standards.
2.3 COMPRESSIBLE FILLER
B. Provide ompressible fille to fill gaps between partitions and/or structure and to close gaps around pipes, ducts, flues, and other penetrations and to fill gaps between gypsum board and other materials,
2.4 FASTENERS
A. Screws shall be Type S, drywall screws for securing gypsum board to studs.
B. Adhesive shall be Mastic No. 11 manufactured by Dow Corning Corporation unless other adhesive is recommended by the gypsum board manufacturer.
3.1 INSTALLATION OF GYPSUM BOARD
A. Install and finish gypsum board to comply with ASTM C 840.
3.2 FINISHING
A. After compound is thoroughly dry, the tape shall be covered with a coat of joint compound or topping compound spread over the tape approximately 3 inches on each side of the tape and feathered out at the edge. After thoroughly dry, another coat of joint compound or topping compound shall be applied with a slight, uniform crown over the joint. This coat shall be smooth and the edges feathered approximately 3 inches beyond the preceding coat.
B. Allow each application of compound to joint and fastener heads to dry, then sand if necessary. Caution shall be used to avoid roughing of wallboard paper. Where more than one compound coat is specified herein, allow 24 hours drying time between coats.
C. Provide the following levels of gypsum board finish per GA-214:
1. Level 4 for exposed gypsum board surfaces. No textured coatings will be allowed.
2. Level of finish shall match adjacent surfaces.
SCBL 227334 145-091 09 90 00 - 1
SECTION 09 90 00
PAINTING
1.1 SCOPE
A. The scope and extent of painting and finishing:
a. Paint immediate area of any patch &/or repair. The immediate area shall mean edge to edge/corner to corner of a logical break where the detection of dissimilar appearance will not be readily identified.
b. Paint immediate area and new construction such as building-wide chases and soffits, and new infill patches in the basement, where gypsum drywall is exposed. The immediate area shall mean edge to edge of a logical break where the detection of dissimilar appearance will not be readily identified.
B. Paint finish, texture and color shall match adjacent painted surfaces that are in sound condition.
C. Paint coatings shall be applied by brush only in all historic structures.
1.2 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)
ACGIH 0100Doc (2005) Documentation of the Threshold Limit Values and Biological Exposure Indices
THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC PA Guide 3 (1982; E 1995) Guide to Safety in Paint Application
1.3 REGULATORY REQUIREMENTS
A. Environmental Protection: In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution Control District and regional jurisdiction. Notify the Government of any coating specified herein which fails to conform.
B. Lead Content: Do not use coatings having a lead content over 0.06 percent by weight of nonvolatile content.
C. Chromate Content: Do not use coatings containing zinc-chromate or strontium-chromate.
D. Asbestos Content: Materials shall not contain asbestos.
E. Mercury Content: Materials shall not contain mercury or mercury compounds.
F. Human Carcinogens: Materials shall not contain ACGIH 0100Doc confirmed human carcinogens (A1) or suspected human carcinogens (A2).
1.4 SUSTAINABILITY REQUIREMENTS
A. Flats VOC content shall be no greater than 50 g/L.
B. Non-flats and primers VOC content shall be no greater than 150 g/L.
SCBL 227334 145-091 09 90 00 - 2
C. Varnish VOC content shall be no greater than 350 g/L.
D. Lacquer VOC content shall be no greater than 550 g/L.
E. Stains VOC content shall be no greater than 250 g/L.
F. Sanding sealer VOC content shall be no greater than 275 g/L.
1.5 QUALITY ASSURANCE
A. ACCEPTABLE MANUFACTURERS are as follows (or approved equal):
Benjamin Moore and Company Diamond Vogel Pittsburgh Paints, PPG Industries, Inc.
Sherwin-Williams Company
B. Applicator shall have a minimum of five (5) years proven satisfactory experience, and shall show proof to the Contractor before commencement of work that he will maintain a qualified crew of painters throughout the duration of the work.
1.6 REVIEW OF COATING SCOPE BEFORE BIDDING
A. The Painting Contractor shall be responsible for performing all work and providing all materials required to achieve the design intent shown on the Drawings. The Government will not be responsible for any additional expense to the Contractor if the conditions causing those expenses could have been discovered in an on-site inspection prior to bid submittal. Paint coatings shall be applied by brush only in all historic structures.
1.7 SUBMITTALS
A. Submit manufacturer’s product data for all primers, paints, and related products in accordance with General Requirements and Submittals List. Include a detailed schedule that indicates the product that is proposed for each substrate.
B. Submit samples of each type of finish and color in accordance with General Requirements and Submittals
List. Paint samples shall be submitted on 8 1/2-inch x 11-inch Mead Mark I cover paper, coated on one side, with paint sprayed or applied with a foam rubber roller. Back of samples shall show the manufacturer and the trade name of the proposed product.
C. Submit documentation indicating VOC content of coatings applied in accordance with Div. 1 General Requirements and Submittals List.
1.8 DELIVERY, STORAGE AND PROTECTION
A. All materials shall be delivered in the original containers with seals unbroken and labels intact. Labels shall include manufacturer’s name and label and the following information:
1. Product name of title of material
2. Product description (generic classification of binder type)
3. Manufacturer’s stock number and date of manufacture
4. Contents by volume for pigment and vehicle constituents
5. Thinning instructions
6. Application instructions
7. Color name and number
8. VOC content
B. All materials shall be delivered in the original containers with seals unbroken and labels intact.
SCBL 227334 145-091 09 90 00 - 3
C. All materials used on the project shall be stored in a single well-ventilated place designated by the CO/COR at a minimum ambient temperature of 46 degrees F. Such storage place shall be kept neat and clean, and all damage thereto or to its surroundings shall be made good. Any oil, rags, waste, etc. shall be removed from the building every night, and every precaution taken to avoid the danger of fire.
1.9 JOB CONDITIONS
A. Surface temperature shall be maintained at the minimum temperature required by the coating manufacturer during application and drying of coatings. Exterior surfaces shall not be painted or finished during weather period that are forbidden by the manufacturer’s documented instructions. See manufacturer’s written instructions for more specific information.
B. Adjacent work, building finishes and surfaces shall be totally protected with masking tape, drop cloths or other suitable coverings. Paint coatings shall be applied by brush only in all historic structures.
1.10 SAFETY AND HEALTH
A. Safety Methods used During Coating Application: Comply with the requirements of SSPC PA Guide 3.
B. Toxic Materials: To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:
1. The applicable manufacturer’s Material Safety Data Sheets (MSDS) or local regulation.
2. 29 CFR 1910.1000.
1.11 ENVIRONMENTAL CONDITIONS
A. Comply, at minimum, with manufacturer recommendations for space ventilation during and after installation.
2.1 MATERIALS
A. The Contractor shall have the option of using materials and finishes manufactured by any one of the manufacturers previously listed (or approved equal). Materials used throughout shall be the products of one manufacturer only, and shall be first line and top grade materials produced by the manufacturer selected. The mentioning of a specific brand name is done to establish a minimum acceptable standard or quality desired.
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Applicator present, for compliance with requirements for coating application. Proceed with coating application only after unsatisfactory conditions have been corrected and surfaces receiving coatings are thoroughly dry.
B. Start of coating will be construed as Applicator’s acceptance of surfaces and conditions within a particular area.
C. Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers.
D. Notify Contractor and Government about anticipated problems when using materials specified over substrates primed by Others.
3.2 PREPARATION
SCBL 227334 145-091 09 90 00 - 4
A. Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be coated. If removal is impractical or impossible because of size or weight of the item, provide surface-applied protection before surface preparation and coating. After completing finishing operations in each space or area, reinstall items removed using workers skilled in the trades involved.
B. All surfaces to be scraped and wiped cleaned free of loose dirt and dust before finishing. After the first coat, putty holes, cracks, etc. with putty of a color to match that of finish. Bring putty flush to the adjoining surface.
C. Metal surfaces which are not galvanized or shop-coated shall be washed with mineral spirits to remove dirt and grease. Remove rust or scale by wire brushing or sandpapering clean.
D. Clean and treat galvanized metal chemically with a compound designed for this purpose, such as
"Lithoform", "Stibley", or "Solfo Metallic Coat", in accordance with the paint manufacturer's instructions.
E. Sand hard, glossy and previously-painted finishes to insure adhesion. Spot prime with primer specified for new surfaces where existing paint or primer has been partially removed by blistering, peeling, rupture, or cracking. Completely remove existing finish if 25 percent or more of the existing finish has failed or can be easily scraped off the surface.
3.3 APPLICATION
A. Paint coatings shall be applied by brush only in all historic structures.
B. Apply all materials under adequate illumination.
C. Extent of painting and finishing shall be to paint immediate area of any patch &/or repair. The immediate area shall mean edge to edge of a logical break where the detection of dissimilar appearance will not be readily identified. Areas without a discernable break shall be painted edge to edge.
D. Do not coat over dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions detrimental to formation of a durable coating film.
E. Provide finish coats that are compatible with primers used.
F. Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for coating as soon as practicable after preparation and before subsequent surface deterioration.
G. The number of coats and film thickness required are the same regardless of application method. Do not apply succeeding coats until previous coat has cured as recommended by manufacturer.
H. Allow sufficient time between successive coats to permit proper drying. Do not recoat surfaces until previous coat has dried to where it feels firm, and does not deform or feel sticky under moderate thumb pressure, and until application of another finish coat does not cause undercoat to lift or lose adhesion.
I. Apply finish coatings by brush according to manufacturer’s instructions, and as follows:
1. Brushes: Use brushes best suited for type of material applied. Use brush of appropriate size for surface or item being coated.
J. Apply coating materials no thinner than manufacturer’s recommended spreading rate to achieve dry film thickness indicated. Provide total dry film thickness of the entire system as recommended by manufacturer.
K. Before applying finish coats, apply a prime coat, as recommended by manufacturer, to material that is required to be coated or finished and that has not been prime coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears to ensure a finish coat with no burn-through or other defects due to insufficient sealing.
SCBL 227334 145-091 09 90 00 - 5
L. Pigmented (opaque) finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable.
Match approved samples for color, texture, and coverage. Remove, finish, or recoat work not complying with requirements.
3.4 CLEANING
A. At the end of each workday, remove empty trash cans, rags, rubbish, and other discarded paint materials from Project site.
B. After completing painting, clean glass and coating-spattered surfaces. Remove spattered paint by washing and scraping without scratching or damaging adjacent finished surfaces.
3.5 PROTECTION
A. Protect work of other trades, whether being painted or not, against damage from coating work. Correct damage by cleaning, repairing or replacing, and recoating, as approved by the Government.
B. Provide “Wet Paint” signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work.
C. After work of other trades is complete, touch up and restore damaged or defaced painted surfaces.
3.6 COATING SCHEDULE
A. See list of approved manufacturers of paint products earlier in this section. The paint materials listed below are given as a means of establishing the standard for the required coat materials.
B. Where manufacturer’s names are mentioned herein, an equivalent product by another manufacturer may be submitted for approval. Manufacturers and products specified are not intended to limit the selection of equal products from other manufacturers.
EXTERIOR WORK
WOOD TRIM, EAVE AND SOFFIT
2 coats S-W Duration Exterior Latex Acrylic Satin Coating, K33 Series (Self-priming- 7 mils wet, 2.8 mils dry per coat)
INTERIOR WORK
NEW GWB WALLS
1 coat S-W ProMar 200 Zero VOC Latex Interior Primer B28-2600 (4 mils wet, 1.5 mils dry) 2 coats S-W ProMar 200 Zero VOC Eg-Shel Interior Latex B20-2600 Series (4 mils wet, 1.7 mils dry per coat)
EXISTING GWB AND PLASTER WALLS AND CEILINGS
2 coats S-W ProMar 200 Zero VOC Flat Interior Latex B20-2600 Series (4 mils wet, 1.5 mils dry per coat)
WOOD AND MDO PLYWOOD FOR PAINTED FINISH
1 coat S-W Wall and Wood Primer B49W2 (4 mils wet, 1 mil dry) 2 coats S-W ProMar 200 Latex Eg-Shel Enamel, B20W200 (4 mils wet, 1.7 mils dry per coat)
SCBL 227334 145-091 09 90 00 - 6
EXTERIOR COLOR PLACEMENT
Soffits and eaves Match adjacent color
INTERIOR COLOR PLACEMENT
GWB / Plaster walls/ceilings and soffits Match adjacent color
DIVISION 26 - ELECTRICAL
SCBL 227334 145-091 26 04 00-1
SECTION 26 04 00
COMMON REQUIREMENTS FOR ELECTRICAL
PART 1 GENERAL
1.1 SUMMARY
A. This section describes the general requirements of these specifications and shall apply to all phases of the work specified, shown on the drawings, or required to provide for complete installation of all systems for this project.
B. This Section includes basic materials and methods to complement other Division 26 Sections.
C. This Section includes basic materials and methods to complement Section 28 46 00 - Fire Detection and Alarm.
1.2 WARRANTIES
A. Warrant materials, workmanship and equipment against defects for a period of one year after the date of substantial completion.
B. Certain equipment shall be warranted beginning at the time of final acceptance or for longer periods of time as specified in those divisions of the Project Manual.
C. Repair or replace, at no additional cost to the Owner, any item which may become defective within the warranty period.
D. Any manufacturers' warranties concerning any item installed will run to the benefit of the Owner.
E. The Contractor agrees not to void or impair, or to allow Sub-Contractors to void or impair, any warranties regarding products or items installed as part of this project.
F. The repair of faulty workmanship shall be considered to be included in the contract.
1.3 ALTERNATES
A. Alternates, if required, shall be as described in the “Alternates” section of this Project Manual, as described on the proposal form, or as indicated on the drawings.
1.4 QUESTIONS OF INTERPRETATION DURING BIDDING PHASE
A. If questions arise during the bidding process regarding the meaning of any portion of the contract documents, the prospective bidder shall submit the questions to the Contracting Officer or Contracting Officer Representative for clarification.
B. Any definitive interpretation or clarification of the contract documents will be published by addenda, properly issued to each person holding documents, prior to the bid date.
C. Verbal interpretation or explanation not issued in the form of an addendum shall not be considered part of the bidding documents.
02/23/2024CA-2169
SCBL 227334 145-091 26 04 00-2
D. When submitting questions for clarification, adequate time for issuance and delivery of addenda must be allowed.
E. The Contracting Officer or Contracting Officer Representative shall be the sole judge regarding interpretations of conflicts within contract documents.
1.5 CONTRACT DOCUMENT DISCREPANCIES
A. If any ambiguities should appear in the contract documents, request clarification from the Contracting Officer or Contracting Officer Representative before proceeding with the work.
B. If the Contractor fails to make such request, no excuse will thereafter be entertained for failure to carry out the work in a manner satisfactory to the Contracting Officer or Contracting Officer Representative.
C. Should a conflict occur within the contract documents, the Contractor is deemed to have estimated the more expensive way of doing the work unless a written clarification from the Contracting Officer or Contracting Officer Representative was requested and obtained before submission of proposed methods or materials.
D. The Contracting Officer or Contracting Officer Representative shall be the sole judge regarding interpretations of conflicts within contract documents.
1.6 DEFINITIONS
A. The following definitions shall apply throughout the contract documents:
1. Contracting Officer or Contracting Officer Representative: Architect or Engineer
2. Code: Applicable national, state and local codes
3. Mechanical: Plumbing, HVAC, and Fire Protection work required by the Contract
Documents
4. Electrical: Electrical and Fire Alarm work required by the Contract Documents
5. Contractor: Any Contractor performing work required by the Contract Documents
6. Indicated: Noted, scheduled or specified
7. Selected: Selected by the Contracting Officer or Contracting Officer Representative.
8. Provide: Furnish, install, connect and tested complete and ready for use
9. Furnish: Supply and deliver to the site ready for installation
10. Install: Install complete, per Contract Documents and manufacturer's requirements.
11. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawl spaces, and tunnels.
12. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.
13. Exposed, Exterior Installations: Exposed to view outdoors, or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.
14. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in duct shafts.
15. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants, but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.
16. Dry Locations: A location not normally subject to dampness or wetness. A location classified as dry may be temporarily subject to dampness or wetness, as in the case of a building under construction.
17. Damp Locations: Locations protected from weather and not subject to saturation with water or other liquids but subject to moderate degrees of moisture.
SCBL 227334 145-091 26 04 00-3
a. Examples of such locations include partially protected locations under canopies, marquees, roofed open porches, and like locations, and interior locations subject to moderate degrees of moisture, such as some basements, some barns, and some cold storage warehouses.
18. Wet Locations: Installations underground or in concrete slabs or masonry in direct contact with the earth; in locations subject to saturation with water or other liquids, such as vehicle washing areas; and in unprotected locations exposed to weather.
1.7 SYMBOLS
A. Items of equipment and materials are indicated on the drawings in accordance with the symbols on the plans.
1.8 ABBREVIATIONS
A. Refer to abbreviations list on the Drawings.
B. The following abbreviations apply throughout the Contract Documents:
1. ADA: Americans with Disabilities Act
2. ANSI: American National Standards Institute
3. ASHRAE: American Society of Heating, Refrigerating and Air Conditioning Engineers
4. ASME: American Society of Mechanical Engineers
5. ASTM Specification: Standard specifications of the American Society for Testing
Materials
6. FM: Factory Mutual Engineering Corporation
7. IRI: Industrial Risk Insurers
8. NEC: National Electrical Code, latest edition
9. NEMA: National Electrical Manufacturers Association
10. NFPA: National Fire Protection Association
11. UL or Underwriters: Underwriters Laboratories, Inc.
1.9 CODES
A. The work shall be performed by persons skilled in the trade involved and shall be done in a manner consistent with normal industry standards.
B. The work shall conform to all applicable sections of currently adopted editions of the following codes, standards, and specifications:
1. International Building Code (IBC)
2. International Fire Code (IFC)
3. International Energy Conservation Code (IECC)
4. Safety and Health Regulations for Construction
5. Occupational Safety and Health Standards (OSHA), National Consensus Standards and
Established Federal Standards
6. National Electrical Code (NEC)
7. National Electrical Safety Code (NESC)
8. National Fire Protection Association (NFPA)
9. Life Safety Code (NFPA 101)
10. Factory Mutual Global Engineering (FMG)
11. Underwriters' Laboratories, Inc. (UL)
12. National Electrical Manufacturers Association (NEMA)
13. Institute of Electrical and Electronics Engineers (IEEE)
14. Insulated Power Cable Engineers Association (IPCEA)
15. Telecommunications Industry Association (TIA)
16. Building Industry Consulting Service International (BICSI)
SCBL 227334 145-091 26 04 00-4
17. Applicable national, state and local codes
C. Where there is a conflict between the code and the Contract Documents, the code shall have precedence only when it is more stringent than the Contract Documents.
1. Items that are allowed by the code but are less stringent than those specified shall not be substituted.
1.10 PERMITS
A. The Contractors shall familiarize themselves with requirements regarding permits, fees, etc., and shall comply with them.
B. Permits, licenses, inspections and arrangements required for the work shall be obtained by the Contractor at his expense.
1.11 MATERIALS AND EQUIPMENT MANUFACTURERS
A. Options in selecting materials and equipment are limited by requirements of the contract documents and governing regulations. They are not controlled by industry traditions or procedures experienced on previous construction projects.
B. Materials and equipment shall be provided in accordance with the following:
1. Primary Design Products: Primary design products are those products around which the project was designed in terms of capacity, performance, physical size and quality.
2. Primary design products are indicated by use of a single manufacturer's name, model number or similar data on drawings or schedules or within the specifications.
3. Provide primary design products unless substitutions are made in accordance with the following paragraphs.
4. Acceptable Equivalent Substitutions: Acceptable equivalent substitutions are products of manufacturers other than those listed for the primary design products. Equivalent acceptable substitutions shall meet each of the following requirements:
a. The product shall be manufactured by one of the acceptable manufacturers listed in the Project Manual, drawings, or addenda.
b. The product shall meet or exceed the requirements of the contract documents in terms of quality, performance, suitability, appearance, and physical characteristics.
c. The Contractor providing the substitution shall bear the total cost of changes due to substitutions. These costs may include additional compensation to the Contracting Officer or Contracting Officer Representative for redesign and evaluation services, increased cost of work by the Owner or other Contractors, and similar considerations.
5. Performance Requirements: Where the contract documents list performance requirements or describe a product or assembly generically, provide products that comply with the specific requirements indicated and that are recommended by the manufacturer for the respective application.
6. Compliance with Standards, Codes and Regulations: Where the specifications require only compliance with an imposed standard, code or regulation, the Contractor has the option of selecting a product that complies with specification requirements, including the standards, codes and regulations.
C. Proposed substitutions will be judged on the basis of quality, performance, appearance and on the governing space limitations. The reputation of the manufacturer, delivery time requirements, and the availability of repair or replacement parts may also be considered.
D. The Contracting Officer or Contracting Officer Representative shall be the sole and final judge as to the suitability of substitution items.
SCBL 227334 145-091 26 04 00-5
1.12 SUBMITTALS
A. Shop Drawings, Product Data and Samples:
1. Other sections in the Project Manual shall be adhered to if more stringent than the following paragraphs.
2. When required by other sections of this Project Manual, submit shop drawings, product data or samples to the Contracting Officer or Contracting Officer Representative for review.
3. Submittals deemed unnecessary by the Contracting Officer or Contracting Officer Representative shall be returned indicating “No Action Taken”.
4. A completed copy of the transmittal form included with the Project Manual shall accompany each submittal.
5. Submittals shall be numbered consecutively.
6. Unless otherwise noted, submit one copy electronically of shop drawings and product data for review. Review comments will be returned electronically. A hard copy of the electronic submittal will be returned if requested.
7. Where samples are required, submit one (1) sample of each required item.
8. Shop drawings are drawings, diagrams, schedules and other data specifically prepared for this project by the Contractor, Manufacturer, Supplier, or Distributor to illustrate some portion of the work. Shop Drawings shall also detail fabrication and installation for metal and wood supports and anchorage for mechanical materials and equipment.
a. Shop drawings shall be drawn to accurate scale and of adequate size to illustrate required details.
9. Product data are illustrations, standard schedules, performance charts, instruction brochures, diagrams and other information furnished by the Contractor, Manufacturer, Supplier, or Distributor to illustrate a material, product or system for some portion of the work.
10. Samples are physical examples furnished by the Contractor, Manufacturer, Supplier, or Distributor to illustrate materials, equipment or workmanship and to establish the standards by which the work will be performed.
11. Each submittal shall clearly indicate proposed items, capacities, characteristics and details in conformance with contract documents. Equipment items shall be marked with the same item number as used on drawings or schedules. Capacities, dimensions and special features required shall be certified by the manufacturer.
12. Submittals shall indicate manufacturer's delivery time for the item after review by the Contracting Officer or Contracting Officer Representative.
13. The Contracting Officer or Contracting Officer Representative shall review or take other appropriate action upon the Contractor's submittals such as shop drawings, product data and samples, but only to determine conformance with the design concept of the work and the information given in the contract documents.
14. Contractor shall not be relieved of responsibility for any deviation from the requirements of the contract documents by the Contracting Officer or Contracting Officer Representative's review of shop drawings, product data or samples.
15. Contractor shall not be relieved from responsibility for errors or omissions in the shop drawings, product data or samples by the Contracting Officer or Contracting Officer Representative's review of those drawings.
16. No portion of the work requiring submission of a shop drawing, product data or sample shall be commenced until the submittal has been reviewed by the Contracting Officer or Contracting Officer Representative. Such portions of the work shall be in accordance with reviewed submittals.
B. Operation and Maintenance Manuals:
1. Prepare three (3) hard copy operation and maintenance manuals for the equipment furnished. Also provide Operation and Maintenance manuals in electronic format. Send the electronic pdf. format by e-mail. Coordinate electronic format with CO/COR. Manuals
SCBL 227334 145-091 26 04 00-6
shall be submitted to the Contracting Officer or Contracting Officer Representative for review and distribution to the Owner not less than 30 days prior to substantial completion of the project. Manuals not meeting the following requirements may be rejected by the Contracting Officer or Contracting Officer Representative.
2. Each manual shall be assembled in a three-ring binder with hard cover and plastic finish.
Binders shall not exceed a 3-inch thickness. Where more than one binder is required, the manuals shall be separated into a logical grouping, i.e., “Mechanical”, “Electrical”, “Maintenance”, “Operation”, “Parts”, Shop Drawings”, etc. Each binder shall have the following information clearly printed on its front cover:
a. Project name and address.
b. Portion of the work covered by each volume (if more than one volume in the set).
Where more than one volume is required, label each volume as “Volume _____ of _____”.
c. Name, address and telephone number of Contractor and Sub-Contractors including night or emergency number.
3. Manual shall include, but shall not be limited to, the following:
a. A Complete Index. Contractor may submit the index to the Contracting Officer or
Contracting Officer Representative for review prior to submittal of complete manuals if desired.
b. Names, Addresses and Telephone Numbers. This list shall include the manufacturer and local representative who stocks or furnishes repair parts for all items of equipment and shall be typed on a single page in front of the binder.
c. Startup, Operation and Shutdown Procedures. Provide a written description of procedures for startup, operation and shutdown of each electrical item or system.
This description shall include switches to operate, buttons to push, etc., in proper sequence, and the location of switches, starters, and pushbuttons. Description shall include item references or labels used in the contract documents unless otherwise instructed in advance by the Owner.
d. Equipment Accessory Schedule. Upon completion of the work, furnish the Owner with a complete equipment accessory schedule listing each piece of equipment and the related size, type, number required and the manufacturer of renewable items.
e. Manufacturer's Operation and Maintenance Manuals and Parts Lists.
f. Emergency Procedures. Provide a written description of emergency operating procedures or a list of service organizations (including addresses and telephone numbers) capable of rendering emergency services to the various parts of the system.
g. One copy of shop drawings and product data, clearly marked for each item furnished…