ATCH 2 - PWS C-130 FuT 20220724.pdf

PDF 852 KB Posted

Attached to
C-130 Fuselage Trainer (FuT) Device Federal contract opportunity
Solicitation number
FA3002-22-R-0033
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to C-130 Fuselage Trainer (FuT) Device, newest first.
File Type Posted
MDG FuT QandA 20220801.pdf PDF
MDG FuT QandA 20220729.pdf PDF
MDG FuT QandA 20220727.pdf PDF
ATCH 4 - Relevant Experience.pdf PDF
ATCH 5 - Provisions.pdf PDF
ATCH 6 - Wage Determination 2015-5253 - Bexar Co.pdf PDF
Combo RFQ 20220724.pdf PDF
ATCH 3 - Price Proposal.xlsx XLSX spreadsheet
ATCH 1 - FuT RFP 20220724.pdf PDF
ATCH 7 - Wage Determination 2015-5263 - Wichita Co.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement C-130 Fuselage FuT

Version: 2022.07.24

P a g e | 1 of 9

C-130 Fuselage Trainer (FuT) Device

In support of:

59th Medical Wing

Office of Operational Medicine

JBSA-Lackland TX, 78235

Version: 2022.07.24

Version: 2022.07.24

P a g e | 2 of 9

Contents

1. EXECUTIVE SUMMARY

2. PURPOSE

3. SCOPE

4. DESCRIPTION OF SERVICES

5. PROGRAM MANAGEMENT/PROJECT MANAGEMENT

6. NON-PERSONAL SERVICES

7. MATERIALS, EQUIPMENT, AND FACILITIES

8. CONTRACTOR IDENTIFICATION. ....................................................... Error! Bookmark not defined.

9. PLACE OF PERFORMANCE

10. NORMAL HOURS OF OPERATION

11. RECORDS, FILES, AND DOCUMENTS. ............................................. Error! Bookmark not defined.

12. PERFORMANCE OF SERVICES DURING A CRISIS

13. PASS AND IDENTIFICATION ITEMS

14. SECURITY CLEARANCE REQUIREMENTS

Version: 2022.07.24

P a g e | 3 of 9

C-130 Fuselage Trainer (FuT) Device

1. EXECUTIVE SUMMARY

59 Medical Wing (MDW) Operational Medicine’s (SGO) Validated Assessment Program for Operational

Readiness (VAPOR) is aggressively working to modernize the medical readiness training platforms available to Airmen assigned to high deployment/operational tempo Unit Type Codes (UTC). With a changing global engagement strategy, peer and near-peer adversaries, and loss of subject matter experts due to reductions in forces, it’s imperative we maximize training platforms to ensure our medics are ready to meet the medical needs of Combatant Commanders. A critical component that is solely provided by the United States Air Force is fixed wing aeromedical evacuation of patients. In both deployed and Continental United States (CONUS) settings, the C-130 is a heavily used platform for these exact purposes. Acquiring a C-130 Fuselage Trainer (FuT) Device would allow medics to obtain a higher level of proficiency with respect to aeromedical evacuation (how to on/off load patients on an airframe quickly), making them more ready to accomplish the mission. Specifically, Joint Base San Antonio (JBSA) has the largest number of Critical Care Air Transport Team (CCATT) personnel, who accomplish approximately 20% of all CCATT global deployments, and JBSA medical personnel accomplish almost 40% of all Air Force Medical Service (AFMS) deployments. This means our personnel are regularly deployed and C-130s are frequently used to evacuate patients.

2. PURPOSE.

The VAPOR program has a need to conduct C-130 ground-based training IAW AFI 11-2AE Aeromedical

Evacuation (AE) Missions, En-Route Patient Staging, and IAW AFTTP 3-24.57 Critical Care Air Transport

Team operations. This training supports the FFEP3 Expeditionary Medical Support System (EMEDS) and

FFCCT Critical Care Air Transport Team Unit Type Codes (UTCs). Both UTCs utilize fixed wing aircraft to transport sick and injured patients from point of injury/sickness to higher levels of care globally. While medical readiness training and assets are available in Joint Base San Antonio (JBSA), no high-fidelity fixed wing simulation assets are available on JBSA-Lackland.

Through partnership with 19th Air Force (AF), VAPOR was able to locate a C-130H model aircraft at

Sheppard AFB, TX. This aircraft has reached the end of its flying life and was scheduled to be dismantled on-site. The aircraft is a prime candidate for conversion into a Fuselage Trainer (FuT) device IAW AFI 16-

402, for the purposes of utilization as a Ground Instructional Training Aircraft (GITA).

Currently, the only GITA systems available for medical personnel to train on for their war readiness tasks is located at Camp Bullis, TX. Access to those devices is only during enrollment into formal training courses offered by the on-site command.

Procuring the C-130 FuT will allow the VAPOR program to further support medical readiness sustainment training, without having to send personnel out of the city to a formal course. Placing the GITA on

Version: 2022.07.24

P a g e | 4 of 9

Lackland-East Torch Site will allow VAPOR to conduct (simulated) ground-based AE mission scenarios, provide en-route patient staging exercise training (without having to utilize a live aircraft), facilitate C-

130 familiarization and egress training, and allow for ground based medically driven scientific studies to be performed in a simulated aircraft environment. Note that these efforts have never been offered in one location, with this much versatility.

3. SCOPE.

The scope of this contract includes the delivery and setup of a functional C-130H fuselage (no wings, engines, or vertical/horizontal stabilizers) from Sheppard Air Force Base (SAFB) TX to JBSA-Lackland (San

Antonio TX).

During this process, the Contractor shall:

Use a C-130H tow-bar

Remove the aircraft’s wings, engines, vertical stabilizer, and horizontal stabilizer (on-site at

Sheppard AFB)

Use cranes or lifting devices

Transport fuselage, by ground, to JBSA-Lackland

Obtain all required permits germane to transporting the aircraft via ground

Set up the aircraft, on-site at JBSA-Lackland

4. DESCRIPTION OF SERVICES.

4.1. The Contractor shall perform IAW the capabilities identified in this performance work statement

(PWS). Additionally, the Contractor shall remain in communication with the Government Program

Manager (PM) to report status updates and any challenges should they occur. The Contractor shall communicate any Save List or DMil requirements to/with the gaining unit.

4.2. Disassembly and Disposition – Sheppard AFB, TX

4.2.1. The Contractor shall travel to SAFB with all equipment and personnel required to perform (trucks, cranes, tow devices, etc.). Upon arrival at SAFB, the Contractor shall contact the 82 TRW to coordinate access to the installation/facility. The Contractor(s) must qualify for an 82 TRW sponsored base visit pass

IAW the Security Forces background/records check. Information regarding the National Crime

Information Center Interstate Identification Index background/records check can be located at https://www.sheppard.af.mil/Contact/REAL-ID-Act-Base-Entry/. The 82 TRW point of contact (POC) will work with the Contractor to coordinate on base movement of asset once it is ready to ship to JBSA-

Lackland. Coordination of movement will include the base Fire Department, Security Forces, and Airfield

Management (among others). Any towing activities of the airframe must be accomplished during the early AM hours (generally 5:00 a.m.) to avoid interfering with flying operations scheduled at the base.

https://www.sheppard.af.mil/Contact/REAL-ID-Act-Base-Entry/

Version: 2022.07.24

P a g e | 5 of 9

4.2.2. The Contractor shall furnish all necessary personnel, tools, materials, equipment, supervision, and quality control necessary to perform all aspects of this requirement including specialty tooling for items such as propellers, engines, and other aircraft components, and stands for engines and propellers.

4.2.3. Prior to departure of SAFB, the Contractor shall assess the C-130H to ensure it contains the following:

Litter stanchion poles and straps for patient evacuation

Sidewall and center line red Evans seating in-place

Functionality of aft ramp

Left/right paratroop doors

Crew entry door

Overhead escape hatches

Pilot/copilot clear view windows

4.2.4. At both SAFB and JBSA-Lackland, the Contractor shall follow all state and local safety, OSHA, and

HAZMAT standards and regulations. The Contractor shall:

Dispose of excess materials IAW DMil requirements (provided by the 82 TRW POC) prior to leaving the worksite

Remove and dispose of residual fuel found in the wings

Have the contractor lead and Government POC conduct a site walk through/review prior to leaving SAFB o Site clean up o Foreign Objects (FO), debris will be cleaned up removed from site

4.2.5. In coordination with the 82 TRW POC, the Contractor shall:

Remove the wings, engines, and vertical & horizontal stabilizers

Cap and weatherproof exposed areas such as tail and wing roots

Remove items on USAF Aircraft Save List and coordinate proper return of items

Load the fuselage and components onto a trailer and coordinate transportation

Provide all necessary matting and securing devices for aircraft

Obtain required transportation permits from SAFB to final destination

Be responsible for the physical security of their own equipment as well as this asset (must be secured and locked when not manned/monitored)

Maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS

4.2.6. The Contractor shall disconnect, terminate, and cap all electrical harness between the fuselage and removed wings and vertical tail section. The Contractor shall abide to published Air Force “pull lists”

Version: 2022.07.24

P a g e | 6 of 9

(provided by 82 TRW POC) and dispose all removed items correctly including scrap. The Contractor shall preserve the structural integrity of aircraft fuselage while preparing for transportation. The Contractor shall reseal and weatherproof all the reassembled joint seams and exposed cutting joints, pressure wash the exterior skin of the fuselage, and retouch the painted surfaces with a similar paint shade. The

Contractor shall cap and seal all disconnected hydraulic lines between the fuselage and removed wings and tail section.

4.2.7. The Contractor shall have the ability to utilize a C-130 tow bar and lifting crane if needed, to load

C-130 onto contractor provided transport vehicle.

4.3. Transportation from Sheppard AFB to JBSA-Lackland

4.3.1. The Contractor shall safely transport (via ground) the C-130H fuselage to JBSA-Lackland without incurring any damages not present at SAFB.

4.3.2. The Contractor shall obtain all required permissions, passes, and permits needed to perform

IAW this PWS. This includes for both SAFB and JBSA-Lackland military installations.

4.3.3. The Contractor shall observe all current Department of Transportation rules and regulations.

4.4. Fuselage Installation at JBSA-Lackland, TX

4.4.1. Upon arrival at JBSA-Lackland, the Contractor shall contact the 59 MDOS POC to coordinate access to the installation/facility. The 59 MDOS POC will work with the Contractor to coordinate on base movement of asset once it is ready to ship to JBSA-Lackland. Coordination of movement will include the base Fire Department, Security Forces, and Airfield Management (among others). The Contractor shall deliver the C-130 fuselage to Torch Site on JBSA-Lackland East. Upon delivery the Contractor shall connect all 110V and 220V required items (ex. exterior air conditioning unit, functional aft ramp, functional internal aircraft lighting, etc.), and ensure the aircraft is secured on brackets/braces to prevent tip-over with personnel on-board.

4.4.2. The Contractor shall design and fabricate mounting jacks/stands to anchor, saddle, and stabilize the aircraft in place.

4.4.3. The Contractor shall provide stands and ensure that material/workmanship is capable of supporting weight of fully loaded C130 (i.e. loaded with personnel/cargo). Stands shall be made so the belly of the aircraft is simulating the height that the wheels have if they were extended on a functional aircraft. The stands must secure the airframe to the concrete pad in order to prevent the airframe from shifting or becoming dislodged from its training area.

Version: 2022.07.24

P a g e | 7 of 9

4.4.4. The Contractor shall replace the hydraulic pump with an appropriate and equivalent commercial system that will not erode performance capability. The electrical system shall be updated to allow aircraft fuselage to be operated from the commercial grid. Electrical work that requires aircraft operation from generators will not be accepted.

4.5. Access and General Protection/Security Policy and Procedures

4.5.1. Contractor employees shall obey the regulations of the federal installations, including fire, traffic, safety, and security regulations. Contractor employees should only enter restricted areas when required to do so and only when accompanied by a government employee (military or civilian). The Contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.

4.5.2. When applicable, all contractor/subcontractor personnel shall wear identification badges so as to distinguish themselves from government employees. When conversing with government personnel during business meetings, over the telephone, or via electronic mail, contractor/subcontractor personnel shall identify themselves as such to avoid situations arising where sensitive topics might be better discussed solely between government employees. Contractors/subcontractors shall identify themselves on any coordination documents they may review.

5. PROJECT MANAGEMENT.

The Contractor shall identify a project manager who shall be the primary contractor representative responsible for all work awarded under this requirement. The PM’s contact information (i.e. name, phone number, email, etc.) shall be sent to the CO and government PM no later than three (3) business days after contract award date.

6. KICK-OFF MEETING.

The Government shall schedule, coordinate, and host a Kick-Off Meeting no later than 5 days after contract award. The meeting will provide an introduction between contractor and government stakeholders and allow for discussion of technical, management, and security requirements (among other items). At a minimum, the attendees shall include key contractor personnel, the Contracting

Officer (CO), the government’s Program Manager (PM) and the government’s Subject Matter Expert

(SME).

7. NON-PERSONAL SERVICES.

The Government will neither supervise contractor employees nor control the method by which the

Contractor performs required services. Under no circumstances shall the Government assign work to, or prepare work schedules for individual contractor employees. It shall be the responsibility of the

Contractor to manage its employees, and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor feels that any actions constitute, Version: 2022.07.24

P a g e | 8 of 9 or are perceived to constitute personal services, it shall be the contractor’s responsibility to notify the

CO immediately. These services shall not be used to perform work of a policy/decision making or management nature (i.e. inherently Governmental functions). All decisions relative to programs supported by the Contractor shall be the sole responsibility of the Government.

8. MATERIALS, EQUIPMENT, AND FACILITIES.

8.1. The Contractor shall furnish all material and equipment needed in performance of this requirement. The Contractor shall establish and maintain an inventory of on-site contractor assets.

8.2. The Government, at its discretion, may suspend or terminate the access and/or use of any or all

Government access and systems for conducting business with any/or all contractors when a security or other electronic access, use or misuse issue gives cause for such action. The suspension or termination may last until such time as the Government determines that the situation has been corrected or no longer exists.

8.3. The Government, at its discretion, may direct the removal of an employee from a federal facility for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor of responsibility for performance and completion of the requirements within this PWS.

8.4. There are no latrine facilities on site at SAFB. The Contractor shall provide Porta Potty (or like facilities) for contractor employees, and be responsible for maintenance and removal prior to leaving

SAFB.

9. PLACE OF PERFORMANCE.

Contractor performance shall take place at SAFB and JBSA-Lackland.

10. PERIOD OF PERFORMANCE.

The period of performance shall be 31 days after contract award. The Contractor shall ensure all state or local permits and/or licenses required for transportation shall be available and the Contractor will be ready to begin contract performance immediately upon contract award.

11. NORMAL HOURS OF OPERATION.

The Contractor shall receive and deliver the C-130 fuselage during the hours of operation of 0730-1630, Monday through Friday. If the Contractor is unable to do so, they must contact the PM NLT COB to arrange a time for delivery. The Contractor shall not deliver the C-130 unless a VAPOR representative is available to receive.

Version: 2022.07.24

P a g e | 9 of 9

Delivery attempts shall not be made on September 5, 2022 as it is a federal holiday and access to facilities shall be limited.

12. PERFORMANCE OF SERVICES DURING A CRISIS.

IAW DoDI 1100.22, and DFARS 237.76, “Continuation of Essential Contractor Services”, unless otherwise directed by an authorized government representative, it is determined that services as identified in this

PWS are NOT essential for performance during a crisis. In the event of an unforeseen natural or military crisis (i.e. hurricane, insurrection, etc.), the Contractor’s primary responsibility is to safeguard the contractor’s employees.

13. PASS AND IDENTIFICATION ITEMS.

13.1. The Host Unit shall ensure the following pass and identification items required for contract performance are obtained for employees and non-government owned vehicles:

Installation Access Pass (IAP) (DBIDS), Visitor/Vehicle Pass (DoDM 5200.08, Volume 3, DoD

Physical Security Program: Access to DoD Installations), used for contracts for less than one year to include one-day visits (i.e. warranty work).

13.2. Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and

Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

14. SECURITY CLEARANCE REQUIREMENTS.

The Contractor does not require access to classified information, will not require a facility security clearance, and does not need access to government computers or the NIPRNET.

File details come from the government source that posted it. Updated .