APPENDIX D Monthly Maintenance Schedule for Barriers.docx

DOCX document 22 KB Posted

Attached to
J036--FY21 Vehicle Barriers PM
Solicitation number
36C24821Q0900
Issued by

View the file

Other files

File Type Posted
36C24821Q0900 0002.docx DOCX document
QUESTIONS to SOLICITATION Barriers final.pdf PDF
PLAW 116publ183.pdf PDF
LOS CERTIFICATION SOLICITATION VERSION 1 Dec 17 2020.doc DOC document
APPENDIX B WORKLOAD ESTIMATES.doc DOC document
WAGE DETERMINATION.docx DOCX document
APPENDIX A BARRIER SYSTEM CHART.doc DOC document
36C24821Q0900.docx DOCX document
APPENDIX C BARRIERS INSPECTION LOG.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX D

Monthly Maintenance Schedule for Barriers

Date: _____________________Barrier: _______________________________________
Lead Tech: ________________________Second Tech: __________________________________
Start of PM: _______________________Finish of PM: _________________________
Barrier System OperationCheck CompletedNotes
Check Vehicle barrier raises fully up

Check vehicle barrier Up Position sensors

Check vehicle barrier lowers fully down

Check vehicle barrier Down position sensors

Check raise / lower for free, non-binding operation

Check barrier for any non-flush beam surface

Check safety traffic light accessory

De Energize and CleanCheck completedNotes
Check all Error / Indicator lamps on control panel exterior

Check for visual damage

Make sure hydraulic pressure is at 2000 psi

De-Energize the system as per shut down sequence

Verify UPS is on when power is shut down then switch to OFF

Clean all debris from barrier trough

Pressure wash all outside equipment

Wipe Clean any debris inside Hydraulic Cabinet

Wipe Clean any debris inside the control panel cabinet.

Barrier System InspectionCheck CompletedNotes
Check for hydraulic leaks near vehicle barrier

Check for hydraulic leaks at hydraulic line connection points Check drainage system and to ensure no standing water

Clean all hydraulic fluid leaks

Check for loose mechanical fasteners

Check wear plates, linkage and pivot joints for wear

Touch up paint any vehicle barrier exposed surfaces

Check barrier cylinder flange mount bolts are secure

Check barrier cylinder for leakage

HPU Cabinet InspectionCheck CompletedNotes
Check for hydraulic leaks around and under HPU

Check for hydraulic leaks at line connection points

Check hydraulic fluid level in Reservoir

Clean motor fan guard of debris, if motor is a TEFC type

Check for loose fasteners

Check for loose hydraulic fittings

Check Accumulator pre charge pressure is correct

Check for loose or disconnected connectors

Check for kinked, degraded, cut or other damage to hoses

Check for abraded cut or other damage to electrical wiring

Check all indicator light lamps

Clean operator Control Panel enclosures, including interior

Technician Notes: ______________________________________________________________________

_____________________________________________________________ ______________
Technician NameTechnicians SignatureDate

Pre-Start UP Inspection

ItemTask DescriptionCompleted
1
Complete the Pre-Op Checklist
2
Remove all Lock Out Tag Out Items
3
Ensure the area is clear of all pedestrians and vehicular traffic
4
Make sure there are no safety chains bars connected prior to lowering barrier
5
Make sure that all electrical cabinets enclosures are closed and locked by client
6
Make sure that enclosure doors, component covers, and equipment guards are in place.

Technician Notes:

Technician Name Technician Signature Date

Start Up Sequence

The following preoperational procedures assist in verifying that the barrier system is ready for normal operation.

Pre-Op Checklist for Vehicle Barrier Barrier: ______________________________________

Item
Task Description
Completed
1
Ensure visually that there are no pedestrians, personnel, or vehicles in close proximity to the Barrier System during start up.
2
Ensure that there are no objects over, under or around the Barrier System, and that the Barrier System will be free to operate unobstructed.
3
Perform a walk around inspection of the Barrier System Installation, making certain that all electrical and hydraulic connections are safe, correct and secure. Also check for any signs of binding or damage, and or other general conditions that would make the barrier system unsafe or inoperable.
4
Ensure that the barrier base trough is not flooded or has standing water underneath.
5
Ensure that there are no hydraulic fluid leaks, especially under the barrier cylinder, and at the interconnecting hydraulic lines.
6
Ensure all EFO buttons are not activated, if this option is provided.

Pre-Op Check for the HPU and Electrical Enclosure

Item
Task Description
Completed
1
Ensure that all hydraulic interconnection liens are connected
2
Ensure that any unused port is capped or plugged
3
Ensure that there is sufficient ventilation for the HPU air cooled motor
4
Ensure that there are no rags, dirt, debris, or other foreign objects around the HPU, and that the HPU is clean.
5
Ensure that there are no hydraulic fluid leaks
6
The hydraulic Reservoir is filled with the proper hydraulic fluid
7
Ensure that there is a sufficient hydraulic fluid level in the reservoir, which can be observed using the fluid level sight gauge.
8
Ensure that the Accumulator is precharged with nitrogen gas, to the proper pressure.
9
Ensure that the Accumulator Vent Valve is fully closed and tightly seated
10
Ensure that the Hand Pump “T” bleed valve is closed and tightly seated (if supplied), and the handle is removed and stowed.
11
Ensure that the hydraulic fluid is at an acceptable temperature to start the pump

Cont’d 12- 20 next page Task Description

Completed

12
Temporarily start with the electrical disconnect on the electrical enclosure OFF but ensure the facility power electric is on.
13
Ensure incoming fused breakers are reset and properly seated
14
Ensure that the electrical disconnect located o the electrical enclosure is ON
15
Ensure that the UPS is switch “On” functional
16
“JOG” Start (quickly turn on and then off) the motor to ensure that the pump motor direction of rotation is correct.
17
Ensure that the pump and motor start and run
18
Ensure that the Accumulator is charged to an acceptable operating pressure, which can be observed on the hydraulic supply pressure gauge.
19
Ensure that the pump and motor stop, after the accumulator is charged
20
Ensure that the Electrical Enclosure door is closed, and properly sealed

Pre-Op Check for the Remote Operator Control Panel

Item
Task Description
Completed
1
The Panel ON indicator is illuminated
2
All armed indicators are illuminated
3
The EFO indicator is off and all EFO buttons are NOT activated, if this option is provided.

All Barriers located at the following location have been properly serviced, maintenance inspection as per manufacturer guidelines and placed back into EFO mode or according to site requirements.

Note any Barrier Specific Anomalies or items of concern.

_______________________________________________________________________ ____________
Technician NameTechnician SignatureDate

Site Supervisor / COR Name Site Signature Date