About this file
Summary
This is a Request for Proposals (RFP) issued by the City of Raleigh, North Carolina, for the annual Thermal Hydrolysis Process (THP) maintenance shutdown at the Neuse River Resource Recovery Facility. The City seeks an OEM-qualified contractor to plan and execute the annual five-working-day shutdown of the Cambi B64 THP system, including safe removal from service, cleaning, inspection, preventive maintenance, authorized repairs, and return to operation. The contractor may also provide emergency and on-call assistance services during the contract term. The RFP was issued on August 7, 2026, with a mandatory pre-proposal conference and site visit scheduled for August 18, 2026, at 12:00 PM at the facility located at 8500 Battle Bridge Road, Raleigh, North Carolina. Written questions must be submitted by August 25, 2026, at 1:00 PM, with anticipated City responses by August 28, 2026. Proposals are due by September 8, 2026, at 1:00 PM EST and must be submitted in one signed original, one electronic PDF version on a USB Flash Drive, and three copies. The contract term is estimated at five years, with annual shutdowns typically scheduled in October and planned two months in advance.
Pricing shall be submitted on the provided cost form with a not-to-exceed amount for the annual five-day shutdown, additional day rates if authorized, markup percentages for replacement parts and materials, hourly rates for weekend/holiday service, emergency or on-call hourly rates, and estimated annual parts and materials allowances. Contractors must demonstrate minimum five years of experience with OEM-level THP maintenance for Cambi B64-equivalent systems and possess appropriate licensing and insurance, including Commercial General Liability of at least $1,000,000 each occurrence and $2,000,000 aggregate. Evaluation criteria are weighted as follows: Corporate Background and Experience (15 percent), Firm Financial Stability (10 percent), Project Understanding (25 percent), Project Approach (25 percent), and Proposed Cost (25 percent). A short-list of qualified firms may be invited to Stage 2 for interviews and demonstrations. All contractors must comply with the City's Environmental Management System protocols and acknowledge such compliance by submitting the required EMS Acknowledgement Form.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposals # 274-5230-604-2026-THP
Title: Annual Thermal Hydrolysis Process (THP) Maintenance Shutdown – Neuse River Resource Recovery Facility
Issue Date: August 7, 2026
Due Date: September 8, 2026 no later than 1:00PM EST
*LATE PROPOSALS WILL NOT BE ACCEPTED*
Issuing Department: Raleigh Water
Direct all inquiries concerning this RFP to:
Jeffrey Bognar Plant Maintenance Superintendent Email: Jeffrey.bognar@raleighnc.gov
Table of Contents
1. Introduction
1.1 Purpose
1.2 Background
1.3 RFP Timeline
1.4 Pre-Proposal Conference
1.5 Proposal Question
1.6 Proposal Submission Requirements & Contact Information
1.7 Business Engagement & Opportunities
1.8 Rights to Submitted Material
1.9 Communications
1.10 Lobbying
1.11 Conflicts of Interest
1.12 Proposer Expenses
1.13 Proposer Acceptance
2. Proposals
2.1 Request for Proposals Required Document Format
2.2 RFP Documents
3. Proposal Evaluation
3.1 Proposal Evaluation Criteria (Stage 1)
3.2 Interview/Demonstration (Stage 2)
3.3 Final Selection
3.4 Notice to Proposers Regarding RFP Terms & Conditions
3.5 Contract Term…………………………………………………………….12
4. Scope of Services
Appendix I – Proposal Cost Form
Appendix II – Proposer Questionnaire
Appendix III – Reference Questionnaire (Instructions)
Appendix III – Reference Questionnaire Form
Appendix IV – Sample Contract
Appendix V – Company Profile Form
Appendix VI – Environmental Management System Acknowledgement
1 INTRODUCTION
1.1 Purpose
The City of Raleigh (COR) is solicitating proposals from one or more firm(s) with which to contract for the following services:
To plan and execute the annual THP maintenance shutdown for the Cambi B6‑4 Thermal Hydrolysis Process (THP) at the Neuse River Resource Recovery Facility (NRRRF). The selected firm will provide OEM‑qualified personnel and services to safely remove the THP from service, perform cleaning, inspection, preventive maintenance, authorized repairs, and return the system to operation. During the contract term the firm could provide emergency and on-call assistance support services if requested. No representation or guarantee is made regarding the quantity of work to be awarded under any as‐needed service contract.
A detailed scope of services is provided in Section 4 of this document.
All information related to this solicitation, including any addenda, will be posted to the North Carolina electronic Vendor Portal (eVP) at https://evp.nc.gov/.
All questions related to this solicitation must be submitted in writing (via email) to the following individual – questions submitted via telephone will not be answered:
Contact Name Email Address Jeffrey Bognar Jeffrey.Bognar@raleighnc.gov
1.2 Background
The City of Raleigh, the Capital City of North Carolina, remains one of the fastest growing areas in the country. A great economy, top educational institutions, and exceptional health care facilities are some of the characteristics that attract people to the triangle area. The mild climate, diverse work force and proximity to Research Triangle Park combine to make Raleigh a great place to live.
Raleigh is a 21st Century City of Innovation focusing on environmental, cultural, and economic sustainability. The City conserves and protects our environmental resources through best practice and cutting-edge conservation and stewardship, land use, infrastructure and building technologies. The City welcomes growth and diversity through policies and programs that will protect and enhance Raleigh’s existing neighborhoods, natural amenities, history, and cultural and human resources for future generations. The City leads to improve quality of life for neighborhoods and standard of living for all citizens.
The City works with universities, colleges, citizens, and local partners to promote new technology, create new job opportunities, and encourage local businesses and entrepreneurs. The City enlists and prepares 21st Century staff with the skill sets to carry out the duties of the City through transparent civic engagement and by providing the very best customer service to our citizens.
Raleigh Water’s THP pretreats sludge prior to anaerobic digestion. The B6‑4 THP system includes the pulper and recirculation system, reactor feed pumps, hydrolysis https://evp.nc.gov/ mailto:Jeffrey.Bognar@raleighnc.gov reactors, flash tank, and digester feed pumps integral to solids processing reliability and performance. An annual planned five (5) working day shutdown is used to address wear, leaks, safety/instrumentation issues and developing deficiencies before they cause unplanned outages.
1.3 Request for Proposal (RFP) Timeline
Provided below is a list of the anticipated schedule of events related to this solicitation.
The City of Raleigh reserves the right to modify and/or adjust the following schedule to meet the needs of the service. All times shown are Eastern Time (EST):
1.4 Pre-Proposal Conference
All bidders are required to attend the Pre-Proposal Conference. The Pre-Proposal Conference will be held at the Neuse River Resource Recovery Facility, 8500 Battle Bridge Rd. Raleigh, NC 27610, in the administration building training room starting promptly at 12:00 pm. Prospective Proposers are encouraged to submit written questions in advance. Date, time, and location of pre-proposal conference is shown above in the RFP Timeline (Section 1.3).
1.5 Proposal Questions
Requests for clarification and questions to this RFP must be received by the City not later than the date shown above in the RFP Timeline (Section 1.3) for the submittal of written inquires. The firm’s failure to request clarification and submit questions by the date in the RFP Timeline above shall be considered to constitute the firm’s acceptance of all City’s terms and conditions and requirements.
The City shall issue addenda reflecting questions and answers to this RFP, if any, and shall be posted to North Carolina electronic Vendor Portal (eVP). No information, instruction or advice provided orally or informally by any City personnel, whether made in response to a question or otherwise in connection with this RFP, shall be considered
RFP Process Date and Time
RFP Date
August 7, 2026
Pre-Proposal Meeting/Site-Visit (Mandatory)
August 18, 2026 at 12:00 PM.
Neuse River Resource Recovery Facility, 8500 Battle Bridge Rd. Raleigh, NC 27610
Deadline for Written Questions
August 25, 2026 by 1:00 PM
City Response to Questions (anticipated)
August 28, 2026
Proposal Due Date and Time
September 8, 2026 by 1:00 PM authoritative or binding. Proposers can only rely on written material contained in an Addendum to this RFP.
It is important that all Proposers submitting to this RFP periodically check eVP for any Addenda. It is the Proposers responsibility to ensure that all addenda have been reviewed and, if required signed and returned.
All questions related to this solicitation must be submitted in writing (via email) to the following individual – questions submitted via telephone will not be answered:
Contact Name Email Address Jeffrey Bognar Jeffrey.Bognar@raleighnc.gov
1.6 Proposal Submission Requirements and Contact Information
Proposals must follow the format as defined in Section 2 (PROPOSALS), and be addressed and submitted as follows:
DELIVERED BY US POSTAL SERVICE
MAIL:
DELIVERED BY OTHER DEIVERY
SERVICES:
City of Raleigh City of Raleigh
ATTN: Jeffrey Bognar ATTN: Jeffrey Bognar
8500 Battle Bridge Rd. 8500 Battle Bridge Rd.
Raleigh, NC 27610 Raleigh, NC 27610
RFQ No. 274-5230-604-2026-THP RFQ No. 274-5230-604-2026-THP
Proposals must be enclosed in an envelope or package and clearly marked with the name of the submitting company, the RFP number and the RFP Title.
Proposers must submit:
A. one (1) signed original;
B. one (1) electronic version of the signed proposal and;
C. and three (3) copies of the signed proposal.
The electronic version of the Proposal must be submitted as a viewable and printable Adobe Portable Document File (PDF) on a USB Flash Drive. Both hard copy and electronic versions must be received by the City on or before the RFP due date and time provided in RFP Timeline (Section 1.3). Proposals received after the RFP due date and time will not be considered and will be returned unopened to the return address on the submission envelope or package.
Proposers must respond to the entire Request for Proposals (RFP). Any incomplete proposal may be eliminated from competition at the discretion of the City of Raleigh. The City reserves the right to reject any or all proposals for any reason and to waive any informality it deems in its best interest.
Proposals that arrive after the due date and time will not be accepted or considered for any reason whatsoever. If the firm elects to mail in its response, the firm must allow sufficient time to ensure the City’s proper receipt of the package by the time specified in the RFP Timeline (Section 1.3). Regardless of the delivery method, it is the responsibility of the firm to ensure that their proposal arrives at the designated location specified in this Section by the due date and time specified in the RFP Timeline (Section 1.3).
1.7 Business Engagement & Opportunities
The City of Raleigh maintains processes to conduct business with all business enterprises, including small, emerging, growing, under-capitalized, and under-resourced firms or organizations.
1.8 Rights to Submitted Material
All proposals and supporting materials, as well as correspondence relating to this RFP, shall become the property of the City. The content of all submittals will be held confidential until the selection of the firm is made. Proposals will be reviewed by the Evaluation Team, as well as other City staff and members of the general public who submit public record requests. Any proprietary data must be clearly marked. In submitting a Proposal, each Prospective Proposer agrees that the City may reveal any trade secret materials contained in such response to all City staff and City officials involved in the selection process and to any outside consultant or other third party who serves on the Evaluation Team or who is hired by the City to assist in the selection process.
Proposals marked entirely as “confidential”, “proprietary”, or “trade secret” will be considered non-responsive and will be removed from the evaluation process.
1.9 Communications
All communications of any nature regarding this RFP with any City staff, elected City officials, evaluation committee members, are strictly forbidden from the time the solicitation is publicly posted until award. Questions must be submitted in writing to the individual designated in Section 1.1 (Purpose), prior to the deadline provided in the RFP Timeline (Section 1.3). Violation of this provision may result in the firm’s proposal being removed from consideration.
1.10 Lobbying
By responding to this RFP, the firm certifies that is has not and will not pay any person or firm to influence or attempt to influence an officer or employee of the City or the State of North Carolina, or any elected official in connection with obtaining a contract as a result of this RFP.
1.11 Conflicts of Interest
City of Raleigh contracts are controlled by three conflict of interest provisions.
First, federal procurement standards provide in 2 CFR 200.318 (c)(1), No employee, officer, or agent may participate in the selection, award, or administration of a contract supported by a Federal award if he or she has a real or apparent conflict of interest. Such a conflict of interest would arise when the employee, officer, or agent, any member of his or her immediate family, his or her partner, or a firm which employs or is about to employ any of the parties indicated herein, has a financial or other interest in or a tangible personal benefit from a firm considered for a contract. The officers, employees, and agents of the non-Federal entity may neither solicit nor accept gratuities, favors, or anything of monetary value from contractors or parties to subcontracts.
Similarly, the North Carolina General Statutes provides a criminal statute for conflicts of interest in public contracting. N.C.G.S. § 14-234(a):
(1) No public officer or employee who is involved in making or administering a contract on behalf of a public agency may derive a direct benefit from the contract except as provided in this section, or as otherwise allowed by law. (2) A public officer or employee who will derive a direct benefit from a contract with the public agency he or she serves, but who is not involved in making or administering the contract, shall not attempt to influence any other person who is involved in making or administering the contract. (3) No public officer or employee may solicit or receive any gift, favor, reward, service, or promise of reward, including a promise of future employment, in exchange for recommending, influencing, or attempting to influence the award of a contract by the public agency he or she serves.
City of Raleigh Charter Section 3.9 regulates private transactions between the City and its officials and employees. The Charter states:
No member of the City Council, official, or employee of the City of Raleigh shall be financially interested, or have any personal beneficial interest, either directly or indirectly, as agent, representative, or otherwise, in the purchase of, or contract for, or in furnishing any materials, equipment or supplies to the City of Raleigh, nor shall any official or employee of the City of Raleigh accept or receive, or agree to accept or receive, directly or indirectly, from any person, firm or corporation to whom any contract may be awarded or from whom any materials, equipment or supplies may be purchased by the City of Raleigh, by rebate, gift, or otherwise, any money or anything of value whatsoever, or any promise, obligation or contract for future reward or compensation, for recommending or procuring the uses of any such materials, equipment or supplies by the City of Raleigh; no member of the City Council, official or employee of the City of Raleigh shall for his own personal benefit operate, directly or indirectly, any concession in any building or on any lands of the City of Raleigh, nor shall any official or employee of the City of Raleigh bid for or be awarded any contract granting concessionary rights of any nature or kind from the City of Raleigh; it shall be unlawful for any member of the City Council, official or employee of the City of Raleigh to bid for or to purchase or to contract to purchase from the City of Raleigh any real estate, equipment, materials, or supplies of any nature or kind whatsoever, either directly or indirectly, at either public or private sale, either singly, or through or jointly with any other person.
1.12 Proposer Expenses
The City of Raleigh will not be responsible for any expenses incurred by any Proposer in the development of a response to this Request for Proposal or any other activities associated with this procurement including but not limited to any onsite (or otherwise) interviews and/or presentations, and/or supplemental information provided, submitted, or given to City of Raleigh and/or its representatives. Further, the City of Raleigh shall reserve the right to cancel the work described herein prior to issuance and acceptance of any contractual agreement/purchase order by the recommended Proposer even if the awarding authority for each entity has formally accepted a recommendation.
1.13 Proposer Acceptance
Submission of any proposal indicates a Proposer’s acceptance of the conditions contained in this RFP. Furthermore, the City of Raleigh is not bound to accept a proposal on the basis of lowest price, and further, the City has the sole discretion and reserves the right to cancel this RFP, and to reject any and all proposals, to waive any and all informalities and/or irregularities and reserves the right to re-advertise this RFP with either the identical or revised scope and specifications if it is deemed to be in the best interests of the City to do so.
The City of Raleigh reserves the right to accept or reject any or all of the items in the proposal, and to award the contract in whole or in part and/or negotiate any or all items with individual Proposers if it is deemed in the best interest of the City to do so. Moreover, the City reserves the right to make no selection if proposals are deemed to be outside the fiscal constraint or not in the best interest of the City.
2 PROPOSALS
Submitted proposals must follow the format outlined below. The City may reject as non-responsive at its sole discretion any proposal that does not provide complete and/or adequate responses or departs in any substantial way from the required format.
2.1 Request for Proposals Required Document Format
Proposals should be on 8-1/2” x 11” (A4-sized) paper, printed on both sides, bound with only removable clips or staples (no 3-ring binders), and divided into sections using tabs to easily identify and separate each section as follows:
2.1.1. Section/Tab 1: Cover Letter
Provide an introduction letter summarizing the unique proposal of your firm to meet the needs of this service requirement. This letter should be presented on the firm’s official letterhead and signed by an authorized representative who has the authority to enter into a contract with the City on behalf of the firm. Additionally, include the name, address, telephone and email address of the individual who serves as the point of contact for this solicitation.
2.1.2. Section/Tab 2: Corporate Background and Experience
Include background information on the firm and provide detailed information regarding the firm’s experience with similar projects. Provide a list of all similar contracts performed in the past 5 number of years, accompanied by at least 3 references (contact persons, firm, telephone number and email address).
Include the total amount invoiced for each listed project, the length of the project, and list of those involved in the project who are also proposed for the subject project named in this solicitation. Failure to provide a list of all similar contracts in the specified period may result in the rejection of the firm’s proposal. The evaluation team reserves the right to contact any or all listed references, and to contact other public entities regarding past performance on similar projects.
2.1.3. Section/Tab 3: Financial Information
Review and provide one of the following three (3) financial statement options:
1. Recent audited or reviewed financial statements prepared by an independent certified public accountant (CPA) that shall include, at a minimum, a balance sheet, income statement (i.e., profit/loss statement) and cash flow statement and, if the audited or reviewed financial statements were prepared more than six (6) months prior to the issuance of this RFP, the Proposer shall submit its most recent internal financial statements (balance sheet, income statement and cash flow statement or budget with entries reflecting revenues and expenditures from the date of the audited or reviewed financial statements to the end of the most recent financial reporting period (i.e., the quarter or month preceding the issuance date of this RFP)).
OR
2. Recent compiled financial statements prepared by an independent CPA that shall include, at a minimum, a balance sheet, income statement (i.e., profit/loss statement) and cash flow statement and, if the compiled financial statements were prepared more than three (3) months prior to the issuance of this RFP, the Proposer shall submit its most recent internal financial statements (balance sheet, income statement and cash flow statement or budget with entries reflecting revenues and expenditures to date), and other evidence of financial stability such as most recently filed income tax return, evidence of a line of credit/loans/other type of financing with statement of amount in use/outstanding balance (e.g., a complete copy commitment letter, loan agreement, billing statement reflecting the line of credit or statement from lender acknowledging the commitment to fund the Proposer’s stated financing), personal guaranty with copies of personal income tax filing and statement of net worth or such other evidence that is accurate, reliable and trustworthy regarding the Proposer’s financial stability.
OR
3. Include a certified, signed statement from a licensed CPA regularly engaged in the review of the firm’s financial information verifying the financial viability of the firm.
All financial information, statements and/or documents provided in response to this solicitation shall be kept confidential provided that EACH PAGE is marked as follows:
“CONFIDENTIAL – DO NOT DISCLOSE EXCEPT FOR THE EXPRESS PURPOSE OF
PROPOSAL EVALUATION.“
“Recent” shall be defined as financial statements that were prepared within the 12 months preceding the issuance date of this RFP.
Consolidated financial statements of the Proposer’s parent or related corporation/business entity shall not be considered, unless: (1) the Proposer’s actual financial performance for the designated period is separately identified in and/or attached to the consolidated statements, (2) the parent or related corporation/business entity provides the State with a document wherein the parent or related corporation/business entity will be financially responsible for the Proposer’s performance of the contract and the consolidated statement demonstrates the parent or related corporation’s/business entity’s financial ability to perform the contract, financial stability and/or such other financial considerations identified in the evaluation criteria; and/or (3) Proposer provides its own internally prepared financial statements and such other evidence of its own financial stability identified above.
The firm’s failure to provide any of the above-referenced financial statements may result in the proposal being removed from consideration. Proposers are also encouraged to explain any negative financial information, and to provide documentation supporting those explanations and demonstrating the financial strength of the firm.
2.1.4. Section/Tab 4: Project Understanding, Approach and Schedule Provide a comprehensive narrative, outline, and/or graph demonstrating the firm's understanding and approach to accomplishing the tasks outlined in the Scope of Work section of this RFP. A description of each task and deliverable and the schedule for accomplishing each shall be included.
2.1.5. Section/Tab 5: Team Firm, Experience and Certifications This section must include the proposed staffing, deployment and firm of personnel to be assigned to this project. The Proposer shall provide information as to the Proposals and experience of all executive, managerial, legal, and professional personnel to be assigned to this project, including resumes citing experience with similar projects and the responsibilities to be assigned to each person. A project-specific firm chart which clearly illustrates the roles, responsibilities, and the reporting relationships of each team member should be included.
2.1.6. Section/Tab 6: Cost
In a separate sealed envelope provide a minimum of three (3) complete copies of the Proposal Cost Form and any additional itemized cost breakdown or price schedule.
Hourly rates shall be fully burdened to include all costs, all applicable overhead and profit (including lodging, meals, and transportation). Attach any additional pricing details.
2.2 RFP Documents
This RFP is comprised of the base RFP document, any attachments, and any addenda released before the contract is awarded. All attachments and addenda released for this RFP in advance of any contract award are incorporated herein by reference.
3 PROPOSAL EVALUATION
3.1 Proposal Evaluation Criteria (Stage 1)
This is not a bid. There will not be a public opening. The proposals received in response to this RFP will be evaluated and ranked by the evaluation committee in accordance with the process and evaluation criteria contained below. Responses will be evaluated in light of the material and substantiating evidence presented in the response and not based on what is inferred. After thoroughly reading and reviewing this RFP, each evaluation committee member shall conduct his or her independent evaluation of the proposals received and grade the responses on their merit in accordance with the evaluation criteria set forth in the following table.
The maximum interview/demonstration points a Proposer can receive is five (5) points.
The Proposers selected for interviews/demonstrations under this section will be notified in writing of the date and time. The Proposers’ interview/demonstrations shall be based solely upon information provided in each Proposer’s original proposal. No new information may be presented.
Criteria (a) Weight
(b) Score (0-3)
(a) x (b) Weighted
Score
Corporate Background and Experience 15
Firm Financial Stability 10
Project Understanding 25
Project Approach 25
Proposed Cost 25
Total Score
Score Points 0- Missing or Does Not Meet Expectation 2- Meets Expectation 1- Partially Meets Expectation 3- Exceeds Expectation
Cost Formula: The cost criterion is rated by giving the proposal with the lowest total cost the maximum number of Cost points available. The remaining proposals are rated by applying the following formula:
1 - B - A x C = D A
A—the lowest Proposer’s cost.
B—the Proposer’s cost being scored.
C—the maximum number of cost points available.
D—Proposer’s cost score (points).
Note: If the formula results in a negative number (which will occur when the Offeror’s cost is more than twice the lowest cost), zero points shall be assigned.
3.2 Interview/Demonstration (Stage 2)
A short-list of firms may be invited to Stage 2, Interview/Demonstration, step of the evaluation process. Interview/demonstrations are an important aspect of the evaluation process that offers the City an opportunity to see how the proposer’s solution meets the critical components of the RFP.
3.3 Final Selection
Proposals will be evaluated and ranked according to the criteria and weighted values set forth in Section 3.1. Either a final selection for recommendation will be made at this time or the short-list of firms will be invited to participate in Stage 2 of the evaluation process.
If Stage 2 is implemented, each firm will be evaluated and assigned a score to determine the best firm for recommendation.
After which negotiations of a contract with the most qualified firm will commence. If negotiations are unsuccessful, the City will then pursue negotiations with the next most qualified firm. All Proposers will be notified of their standing immediately following the City’s decision.
The City shall not be bound or in any way obligated until both parties have executed a contract. The City also reserves the right to delay the award of a contract or to not award a contract.
3.4 Notice to Proposers Regarding RFP Terms and Conditions
It shall be the Proposer’s responsibility to read the RFP Instructions, the City’s contract terms and conditions (within the sample City Service Contract provided in Appendix IV), all relevant exhibits, attachments, and any other components made a part of this RFP and comply with all requirements and specifications herein. Proposers are also responsible for obtaining and complying with all Addenda and other changes that may be issued in connection with this RFP.
3.5 Contract Term
The contract issued by the City to the awarded proposer will define either a completion date by which the services are to be completed and finished, or a term date by which the services will begin and be provided repeatedly over a specific period. The details of the contract term and any options to renew or extend the contract, will be stated in the contract issued by the City. See Appendix IV for a sample-version of the City’s contract for services.
4 SCOPE OF SERVICES
Awarded proposer shall provide services, all as set forth in this RFP and more particularly described in this Section 4.
Background and Purpose
Raleigh Water’s Resource Recovery Division operates a Cambi B6-4 Thermal Hydrolysis Process (THP) system at the Neuse River Resource Recovery Facility (NRRRF). The THP system is integral to solids conditioning prior to anaerobic digestion and includes the pulper, reactor feed and pulper recirculation pumps, hydrolysis reactors, flash tank, and digester feed pumps. The City seeks an OEM qualified Contractor to perform a planned annual maintenance shutdown to safely remove the system from service, clean, inspect, service, repair (as authorized), reassemble, and return the THP to operation.
Objective: Maintain system safety, reliability, and performance; proactively identify and address wear, leaks, instrumentation issues, and developing deficiencies to prevent unplanned outages or impacts to solids processing and digestion operations.
4.1. Contract Period
• Contract Term: Estimated five (5) years.
• Service Requests: Services will be requested on an as-needed basis via purchase orders issued by Raleigh Water under the resulting contract.
• Scheduling: Annual shutdowns are set for five (5) working days, depending on site readiness and approved schedules. If extra time is needed, City authorization is required. Shutdowns usually happen in October and are scheduled two months ahead.
• Emergency / on-call Requests: These requests are if needed during the contract term and separate from the annual scheduled shutdowns.
4.2. Minimum Contractor Qualifications
• Demonstrated minimum 5-year experience providing OEM-level THP maintenance for systems equivalent to Cambi B6-4, including inspection and refurbishment of wear components and pressure/safety devices.
• Ability to provide qualified personnel, supervision, and technical guidance for shutdown, isolation, inspection, and return-to-service.
• Capacity to coordinate with City staff and third-party contractors (e.g., jet washing).
4.3. Pre-Shutdown Planning and Coordination
The Contractor shall lead and document pre-shutdown planning, including:
• Review of THP operating history, maintenance records, previous findings, and known deficiencies.
• Development of a detailed shutdown work plan and schedule, sequence of tasks, resource needs, and risk controls.
• Identification of anticipated wear parts, replacement parts, consumables, and special tools.
4.4. City Shutdown Preparation (Prior to Contractor Mobilization)
Raleigh Water will conduct the operational shutdown and make the THP safe for maintenance by:
• Isolating process streams and energy sources; depressurizing and draining applicable equipment; performing LOTO for electrical, mechanical, hydraulic, pneumatic, steam, and other hazardous energies.
• Cleaning and preparation of vessels to support safe access and adequate inspection.
• Providing access equipment and lifting/rigging for reactor hatches and extruder removal if needed (e.g., bucket truck, crane).
4.5. Vessel Jet Washing and Cleaning (By City or City’s Contractor)
• The City will procure a qualified jet washing contractor capable of 3D rotating head cleaning at approximately 20,000 psi and 54 gpm. The Contractor shall provide specifications and onsite supervision/coordination of cleaning as needed.
• The City will furnish water, cleaning resources, wastewater collection and disposal, and coordinate access for cleaning activities.
4.6. Contractor’s Technical Scope (Inspection & Preventive Maintenance)
The Contractor shall inspect and assess THP equipment/components and perform preventive maintenance per OEM recommendations, including:
• Pulper System - Inspect for wear, corrosion, deformation, buildup, leakage; condition of internals, wear surfaces/parts, piping connections, recirculation equipment, access covers, seals, gaskets, and hardware. Recommend refurbishment/replacement where needed.
• Pumps (Pulper Recirculation & Reactor Feed) - Inspect mechanical condition, leakage, wear, seals, couplings, bearings/lubrication, alignment, associated valves/piping, and general operating condition; document deficiencies and recommendations.
• Hydrolysis Reactors - Internal condition; corrosion/erosion/wear; access points/covers;
gaskets and seals; leakage; associated piping/connections; wear components;
mechanical integrity and performance impacts.
• Flash Tank - Internal condition; corrosion/erosion; material buildup; wear; leakage;
access covers/gaskets; associated piping/valves; mechanical condition.
• Digester Feed Pumps - Mechanical condition; leakage; seals; bearings; couplings;
lubrication; alignment; valves/piping; abnormal wear/vibration.
• Valves & Process Piping - Leakage; corrosion; damage; operation; valve seats/seals/packing; expansion joints and flexible connections; abnormal vibration/movement; lubricate/service per OEM procedures.
• Wear & Tear Components - Inspect wear plates/surfaces; seals/gaskets; packing;
mechanical seals; bearings; valve components; other consumables; identify components worn beyond limits and recommend refurbishment or replacement.
• Pressure & Safety Devices - Inspect rupture discs, pressure switches, safety valves, relief devices, related instrumentation and connections; install City-provided calibrated PRVs during the shutdown; document any damaged/expired/deficient devices.
• Instrumentation & Controls (within THP scope) - Visual inspection of instruments/connections; damaged/deteriorated wiring/tubing; verify instrument condition; review known deficiencies; pressure-related instrumentation verification;
functional checks; identify devices requiring calibration/repair/replacement; perform calibrations per OEM as applicable or document for City follow-up.
• Lubrication & Preventive Maintenance - Lubricate mechanical components;
inspect/service bearings, seals, packing, valves; replace routine wear components as authorized; inspect mechanical connections/fasteners; leaks; housekeeping.
4.7. Refurbishment & Corrective Maintenance (As Authorized)
Based on inspection findings, the Contractor shall identify equipment needing refurbishment, repair, or replacement (e.g., worn components, seals/gaskets, valve work, pressure-related components, leak repairs, minor mechanical corrections). Replacement parts should be genuine OEM-approved to ensure compatibility, integrity, warranty, and support. Additional work requires a detailed proposal and City authorization before any additional work is provided.
4.8. Supervision, Assembly, and Return-to-Service
Contractor shall supervise maintenance, verify proper reassembly; confirm covers/guards/protective devices; restore valves/components to correct positions; ensure PRVs are installed; support functional checks and readiness for City to place THP back in service; and provide a safe handover.
4.9. Safety & Compliance
All work shall comply with City of Raleigh, Raleigh Water, NRRRF site requirements, and applicable OSHA and safety standards, including LOTO, confined space, fall protection, working at heights, electrical safety, pressure systems, steam/high-temperature hazards, chemical/biological hazards, hot work, crane/rigging, PPE, and emergency procedures.
Contractor staff shall coordinate with the City’s designated site representative.
4.10. City-Provided Resources
The City will provide, when required by the schedule and scope:
• Access/lifting equipment (cranes, manlifts, bucket trucks) and rigging, including access to reactor hatches and extruder removal if required.
• Calibrated PRVs for installation by Contractor.
• Vessel jetting/cleaning services, water and cleaning resources, wastewater collection/disposal.
• Site access, utilities, security clearances, site-specific safety requirements, auxiliary staff, technical documents/operating information, and coordination with other City contractors.
4.11. Contractor-Provided Resources
The Contractor shall provide:
• Qualified OEM-level personnel and supervision; tools, equipment, and consumables necessary to execute the shutdown scope (excluding City-listed resources).
• Technical guidance to assist the City with shutdown preparation and startup support.
• Onsite supervision and coordination throughout maintenance activities to ensure safe, efficient completion consistent with OEM requirements.
4.12. Deliverables
Pre-Shutdown Submittals
• Work Plan & Schedule: Activities, sequencing, staffing, durations, risk controls, and required City-provided resources.
Post-Shutdown Report (within 15 business days of handover)
• Dates; participating personnel; summary of maintenance performed;
equipment/components inspected; condition assessments; wear components; items refurbished/replaced; pressure/safety devices inspected; PRVs installed;
instrumentation inspected/tested; deficiencies identified; corrective work completed;
corrective actions recommended; recommended replacement parts with priorities;
photos of significant findings; outstanding items; deferred work; recommended actions for the next cycle; confirmation of safe handover.
4.13. Schedule & Milestones
• Target Duration: Five (5) working days per annual shutdown. Extensions due to conditions outside Contractor control require City authorization prior to proceeding.
• Mobilization Notice: Contractor shall schedule site visits reasonably in advance and in alignment with City readiness and jetting contractor availability.
4.14. Performance Standards
• Work shall follow OEM maintenance procedures and recommendations and applicable manufacturer requirements.
• System shall be returned in a safe, reliable, and operational condition; any outstanding deficiencies shall be documented with corrective recommendations.
4.15. Constraints, Exclusions, and Authorization Requirements
Unless explicitly authorized by the City in writing, the base annual shutdown scope excludes spare/replacement parts, consumables, major equipment replacement, fabrication/modification, vessel cleaning/jetting, wastewater disposal, rental of cranes/manlifts/bucket trucks, weekend/holiday work, and corrective work outside the defined annual maintenance scope. All additional work requires prior City authorization.
4.16. Meetings & Communication
• In-Person Kickoff/Pre-Work Meeting: Confirm scope, schedule, access, safety, LOTO, confined-space plans, jetting contractor status, and PRV availability.
• Daily Progress Briefings: Safety, progress, risks, and resource needs.
• Closeout Meeting: Review findings, corrective actions completed, outstanding items, handover confirmation, and next steps.
4.17. Environmental Management System (EMS)
The City’s Resource Recovery Division operates ISO-certified treatment plants under an Environmental Management System (EMS). Contractors must acknowledge the EMS program by signing and submitting Appendix VI: EMS Acknowledgement Form. All work must be conducted in accordance with EMS protocols.
4.18. Invoicing Requirements
Invoices must include:
• Detailed description of work performed
• Hours worked and applicable hourly rates
• Itemized list of parts and materials with markup percentage (if applicable)
• Equipment/rental costs with markup percentage (if applicable)
• Original invoices for parts and materials (upon request)
• Associated PO number for payment processing
Failure to comply with invoicing requirements may result in payment delays without penalty to the City.
APPENDIX I
PROPOSAL COST FORM
The awarded proposer shall perform the services to be performed as set forth in this RFP and more particularly described in Section 4 for a not to exceed amount shown below.
Proposers shall complete the following price schedule. All prices shall include labor, supervision, tools, equipment, travel, mobilization, and all other direct/indirect costs unless otherwise noted. All pricing shall remain firm for the initial contract term unless otherwise permitted by City contract language.
Service Description Unit Bidder Price
1 Annual THP Maintenance Shutdown (5-Day Event). As described in the scope of services and including all travel-related costs. (A not to exceed cost)
Per Shutdown $__________
2 Additional Authorized Day Rate (Beyond 5-Day
Shutdown). Only performed with City approval.
Per Day $__________
3 Replacement Parts, Wear Components, Seals, Gaskets, Valves, etc. not included in shutdown (Markup over cost).
Percentage __________ %
4 Weekend or Holiday Service Request Hourly Rate
(Portal-to-Portal) Per Hour $__________
5 Emergency or On-Call Service Request Hourly Rate
(Portal-to-Portal).
Per Hour $__________
6 Round Trip Travel Costs (For Emergency or On-Call
Requests). Provide a markup over actual cost.
Percentage __________%
7 Estimated parts/materials allowance per year. Provide a recommended annual estimate for THP maintenance and include a list of common parts.
Per Year Est. $__________
Attach proposal cost itemization or breakdown to this Appendix I Proposal Cost Form.
Proposer/Company Name: ____________________________________________________
Authorized Signature _______________________________Date__________________
Signed by: _____________________________________________________________
[Type or Print Name] Title of Signer: _________________________________________________________
APPENDIX II
PROPOSER QUESTIONNAIRE
The following questions must be answered, and data given must be clear and comprehensive. If necessary, questions may be answered on separate sheets. The Proposer may submit any additional information desired.
Company Name: d/b/a (if applicable)
Street / PO Box:
City: State: Zip:
Phone: Fax: E-Mail:
Website (if applicable):
Sole Proprietor Partnership Corporation Other
Number of years in business under company’s present name:
Fed Tax ID #: DUNS # Are you registered with the North Carolina Secretary of State to conduct business (if required)? (Check One) YES: NO: Not Applicable:
Are you properly licensed/certified by the Federal and/or State of North Carolina to perform the specified work?
YES: NO: Not Applicable: ATTACH COPY OF ALL APPLICABLE LICENSING/CERTIFICATION DOCUMENTS Are/will you be properly insured to perform the work? YES: NO:
Contact for this Contract: Title:
Phone: Fax: E-Mail:
Have you ever defaulted or failed on a contract? (If yes, attach details) YES: NO:
List at least three (3) references for which you have provided these services (same scope/size) in the past three years - preferably government agencies. Do not include City of Raleigh as a reference to meet the requirement of listing at least (3) references.
PROPOSERS ARE RESPONSIBLE FOR SENDING REFERENCE QUESTIONNAIRE (APPENDIX III) TO THEIR
REFERENCES.
1. Company:
Contact Person: Title:
Phone: Fax: E-Mail:
Describe Scope of Work:
2. Company:
Contact Person: Title:
Phone: Fax: E-Mail:
Describe Scope of Work:
3. Company:
Contact Person: Title:
Phone: Fax: E-Mail:
Describe Scope of Work:
4. Company:
Contact Person: Title:
Phone: Fax: E-Mail:
Describe Scope of Work:
5. Company:
Contact Person: Title:
Phone: Fax: E-Mail:
Describe Scope of Work:
The undersigned swears to the truth and accuracy of all statements and answers contained herein:
Authorized Signature: Date:
APPENDIX III
REFERENCE QUESTIONNAIRE
(Instructions)
Title: Annual Thermal Hydrolysis Process (THP) Maintenance Shutdown – Neuse River Resource Recovery Facility
The City of Raleigh, as a part of the RFP, requires proposing companies to submit a minimum of three (3) business references as required within this document. The purpose of the references is to document the experience of the proposer relevant to the scope of services and assist in the evaluation process.
• The Proposer is required to send the reference form (the following two pages) to each business reference listed on Proposer Questionnaire.
• The business reference, in turn, is requested to submit the Reference Form directly to the City of Raleigh Point of Contact identified on the Reference Questionnaire form for inclusion in the evaluation process.
• The form and information provided will become a part of the submitted proposal. The business reference may be contacted for validation of the response.
• It is the Proposer’s responsibility to verify their references have been received by the City of Raleigh Point of Contact by the date indicated on the reference form.
APPENDIX III
REFERENCE QUESTIONNAIRE FORM
Title: Annual Thermal Hydrolysis Process (THP) Maintenance Shutdown – Neuse River Resource Recovery Facility
(Name of Business Requesting Reference)
This form is being submitted to your company for completion as a business reference for the company listed above.
This form is to be returned to the City of Raleigh, Jeffrey Bognar, via email to Jeffrey.Bognar@raleighnc.gov no later than September 8, 2026 by 1:00 p.m. EST, and MUST NOT be returned to the company requesting the reference.
For questions or concerns regarding this form, please contact the City of Raleigh, Point of Contact above.
Company Providing Reference
Contact Name and Title/Position
Contact Telephone Number
Contact Email Address
Questions:
1. In what capacity have you worked with this company in the past? If the company was under a contract, please acknowledge and explain briefly whether or not the contract was successful.
Comments:
2. How would you rate this company’s knowledge and expertise?
3= Excellent 2= Satisfactory 1= Unsatisfactory 0= Unacceptable
3. How would you rate the company’s flexibility relative to changes in the scope and timelines?
4. What is your level of satisfaction with hard-copy materials, e.g. reports, logs, etc. produced by the company?
5. How would you rate the dynamics/interaction between the company and your staff?
6. Who were the company’s principle representatives involved in providing your service and how would you rate them individually? Would you comment on the skills, knowledge, behaviors or other factors on which you based the rating?
(3= Excellent; 2= Satisfactory; 1= Unsatisfactory; 0= Unacceptable)
Name: Rating:
7. With which aspect(s) of this company’s services are you most satisfied?
8. With which aspect(s) of this company’s services are you least satisfied?
9. Would you recommend this company’s services to your organization again?
APPENDIX IV
SAMPLE CONTRACT
NORTH CAROLINA
WAKE COUNTY
CONTRACT FOR SERVICES
THIS CONTRACT (“Contract”) is entered into by and between__________, hereinafter referred to as the “Contractor”, and the City of Raleigh, a North Carolina municipal corporation, hereinafter referred to as the “City”.
WITNESSETH:
WHEREAS, the City desires to procure a contractor to perform services; and WHEREAS, the City has completed necessary steps for retention of professional and other services under applicable City policies; and WHEREAS, the City has agreed to engage the Contractor, and the Contractor has agreed to contract with the City, for performance of services as described, and according to the further terms and conditions, set forth herein.
NOW THEREFORE, in consideration of sums to be paid to the Contractor, and other good and valuable consideration, the Contractor and City do contract and agree as follows:
1. Scope of Services The Contractor shall perform for the City the following described services:
2. Schedule/Time of Performance
[1.) For a One-time Service Completed by a Specific Date, use the following:]
In performing the services described in this Contract, it is mutually agreed that time is of the essence. The Contract shall be effective upon the date of the City’s signature.
The Contractor shall begin work on , and work shall be completed no later than .
In the event the services under the Contract are not completed by this date, the Contractor shall be assessed liquidated damages of for each day’s delay beyond the completion date.
[If liquidated damages are not applicable to this Contract, then remove this paragraph.]
[2.) For Repeated Services Over a Period of Time/Term (without renewal options), use the following:]
In performing the services described in this Contract, it is mutually agreed that time is of the essence. The Contract shall have a term of [written number (X) – example: five (5)] years, beginning on the Effective Date through and including [enter term end date].
[3.) For Repeated Services Over a Period of Time/Term (with Renewal Options), use the following:]
In performing the services described in this Contract, it is mutually agreed that time is of the essence. The Contract shall have an initial term of years, beginning on the Effective Date through and including [enter initial term end date].
Prior to the expiration of the initial term or any subsequent renewal terms, the City shall have the option, in its sole discretion, to renew the Contract on the same terms and conditions as are set forth herein for up to a total of additional one-year terms, for a maximum contract term not to exceed five (5) years. The City shall exercise each such renewal option no later than days before the end of the Contract’s then-current term.
The parties acknowledge and agree that a written notice exercising one of the City’s renewal options that is sent to the Contractor as an attachment to an e-mail (for example, as a PDF of a letter sent as an attachment to an e-mail), and which written notice does not contain an original, wet signature or a digital signature, shall nonetheless have the same force and effect as if such written notice contained an original, wet signature or digital signature.
Once the City has decided to exercise a renewal option as provided in this Section, the City hereby authorizes the director of the City department that is responsible for administering this Contract on behalf of the City to execute on behalf of the City the written notice to Contractor that so exercises one of the City’s renewal option(s), and the Contractor shall accept such written notice as the City’s exercise of the applicable renewal option. Notwithstanding anything herein to the contrary, for purposes of providing written notice of the City’s exercise of a renewal option as set forth herein, the parties acknowledge and agree that the City shall submit such written notice to Contractor by e-mail, to the attention of the Contractor representative specified in Section 4 below, “Notices”.
The Contractor shall be responsible for immediately notifying the City in writing of any changes to its contact information in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .