This is Amendment 6 to a Request for Qualifications (RFQ #26-1363580) issued by Connecticut State Colleges and Universities (CSCU) for electricity supply services. The amendment addresses supplier questions and answers regarding fuel cell installations and usage credits across multiple CSCU facilities. The document confirms the operational status and projected timelines for behind-the-meter generation assets, specifically detailing usage credit adjustments for the Housatonic fuel cell facility expected to go live by the end of 2026 or early 2027. The amendment also verifies the presence of a 630 kW fuel cell at 201 Wintergreen Avenue in New Haven that was energized in March 2022. The original submission deadline was February 24, 2026, at 3:00 p.m., with the reverse auction scheduled for March 5, 2026. Bidders are required to acknowledge receipt of Amendment 6 along with all other amendments as part of their technical submission through the EnelX exchange portal.

The amendment provides specific consumption data across six metered service locations showing current and projected annual kilowatt-hour usage with corresponding credit adjustments. No pricing information, set-asides, incumbent vendors, or funding sources are detailed in this amendment. The document serves as a clarification mechanism within the broader procurement process and does not establish pricing terms or contract award conditions, which are addressed through the primary RFQ documentation and the reverse auction process. All qualified vendors remain eligible to respond regardless of disadvantaged enterprise status or prior CSCU supplier relationships.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 6 to CSCU RFQ 26-1363580 Supplier Q&A Part 2

1. Can you please verify that the usage credits for the Housatonic fuel cell are as follows? When is this expected to go live?

UI POD ID
Service Address
Current Annual KWH
Projected Annual KWH Credit
New Annual Projected KWH
2181003943002
900 Lafayette Blvd
1,679,200
1,700,400
-21,200
3000000015524
900 Lafayette Blvd
259,800
417,000
-157,200
3000000043955
900 Lafayette Blvd
444,400
458,560
-14,160
2181002974002
870 Lafayette Blvd
226,320
224,560
1,760
3000000029860
2 Church Street, South Building
1,502,000
513,800
988,200
3000000029838
20 Church St, North Building
1,504,400
513,800
990,600

Confirmed. HCC fuel cell should be online by end of this year/early 2027.

1. Can you please verify if there was a fuel cell installed at 1171007687002, 201 Wintergreen Ave in New Haven? It looks like there was a downturn in 2023/2024 (assuming construction), followed by an uptick in usage at reduced levels.

There is a 630 kW fuel cell at 201 Wintergreen that was energized in March of 2022. Please see excerpt from United Illuminating:

Please acknowledge receipt of this Amendment as part of your technical submission.

Printed Contractor Name

Proposer Name of Authorized Official

Signature of Authorized Official image1.png

File details come from the government source that posted it. Updated .