Supplemental Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S-15-0109_PAL_Fire_Plan_Aug_2012.doc | DOC document | |
| S-15-0109_Plans_-_Sheet_1_of_2.pdf | ||
| S-15-0109_Plans-_Sheet_2_of_2.docx | DOCX document | |
| S-15-0109_Map.pdf | ||
| AG9JGP-S-15-0109_PCT_Trailhead_Overlay.doc | DOC document | |
| S-15-0109_Davis_Bacon_WD.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
| Table of Contents | 1 | |
| Preface | 4 | |
| 101 - Terms, Format, and Definitions | 5 | |
| 101.01 Meaning of Terms | 5 | |
| 101.03 Abbreviations. | 5 | |
| 101.04 Definitions. | 5 | |
| 102 - Bid, Award, and Execution of Contract | 8 | |
| 102 Bid, Award, and Execution of Contract | 8 | |
| 103 - Scope of Work | 9 | |
| Deletions | 9 | |
| 104 - Control of Work | 10 | |
| Deletions | 10 | |
| 104.06 Use of Roads by Contractor | 10 | |
| 105 - Control of Material | 11 | |
| 105.02 Material Sources. | 11 | |
| 105.02(a) Government-provided sources. | 11 | |
| 105.05 Use of Material Found in the Work. | 11 | |
| 106 - Acceptance of Work | 12 | |
| 106.07 Delete | 12 | |
| 107 - Legal Relations and Responsibility to the Public | 13 | |
| 107.05 Responsibility for Damage Claims. | 13 | |
| 107.06 Contractor’s Responsibility for Work. | 13 | |
| 107.09 Legal Relationship of the Parties. | 13 | |
| 107.10 Environmental Protection. | 13 | |
| 107.02 | Protection and Restoration of Property and Landscape | 14 |
| 108 - Prosecution and Progress | 15 | |
| 108 Delete. | 15 | |
| 109 - Measurement and Payment | 16 | |
| 109 Deletions | 16 | |
| 109.02 Measurement Terms and Definitions. | 16 | |
| 155 - Schedules for Construction Contracts | 17 | |
| 155 Delete. | 17 | |
| 203 - Removal of Structures and Obstructions | 18 | |
| 203.01 Description. | 18 | |
| 203.05 Disposing of Material. | 18 | |
| 209 - Structure Excavation and Backfill | 20 | |
| 209.11 Compacting. | 20 | |
| Table 209-1 Sampling and Testing Requirements | 20 | |
| 308 - Minor Crushed Aggregate | 21 | |
| 403 - Hot Asphalt Concrete Pavement | 23 | |
| 403.06 Surface Preparation. | 23 | |
| 403.16 Pavement Smoothness. | 23 | |
| Table 403-1—Acceptance Sampling and Testing Requirements. | 24 | |
| 412 - Asphalt Tack Coat | 25 | |
| 601 - Minor Concrete | 26 | |
| 601.01 | 26 | |
| 633 - Permanent Traffic Control | 32 | |
| 633.02 Material. | 32 | |
| 633.03 General. | 32 | |
| 633.05 Panels. | 32 | |
| 718 - Traffic Signing and Marking Material | 33 | |
| 718.05 Aluminum Panels | 33 | |
| 818 - Asphalt Crack Cleaning and Sealing (5/97) | 33 | |
| 1. Description | 33 | |
| 2. Equipment | 33 | |
| 3. Materials | 33 | |
| 4. Requirements | 34 | |
| 5. Measurement | 34 | |
| 6. Payment | 34 |
Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006 Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
107.10_05_us_05_04_2007
107.02 Protection and Restoration of Property and Landscape
Add the following:
Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September 2000
108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.
Delete Section 155 in its entirety.
203 - Removal of Structures and Obstructions 203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
209 - Structure Excavation and Backfill 209.11_nat_us_02_24_2005
209.11 Compacting.
Delete the subsection and add the following:
Compact backfill using designated compaction method A, B, or C:
Method A. Ensure that backfill density exceeds the density of the surrounding embankment.
Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer using appropriate compaction equipment until visual displacement ceases. For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.
Method C. Determine optimum moisture content and maximum density according to AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
Table 209-1 Sampling and Testing Requirements
(2) Compaction methods (A) and (B) do not require AASHTO T-99 or T-310 test methods for foundation fill.
308 - Minor Crushed Aggregate 308.00_01_us_10_11_2006 Delete section 308 in its entirety and replace with the following:
Description
308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.
Material
308.02 Conform to the following Subsections:
| Crushed aggregate | 703.06 | |
| Water | 725.01 |
Construction Requirements
308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.
308.04 Placing Crushed Aggregate.
(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.
(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.
308.05 Compacting and Finishing Crushed Aggregate.
(a) Roadway aggregate. Compact using the methods below, specified in the Schedule of Items.
(1) Method 1. Operate equipment over the full width of spread aggregate.
(2) Method 2. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at a moisture content suitable for compaction.
(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.
308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03. Furnish a production certification including gradation and quality properties for each source.
Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and 106.04. Method 2 compaction will be evaluated under Section 106.04.
Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.
Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.
Measurement
308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure crushed aggregate by the cubic yard in-place on the road.
Measure width horizontally to include the top of aggregate width including designed widenings. Measure the length horizontally along the centerline of the roadway.
Payment
308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
403 - Hot Asphalt Concrete Pavement 403.06_nat_us_05_17_2005
403.06 Surface Preparation.
Add the following:
Prelevel dips, depressions, sags, excessive or nonexistent crown, or other surface irregularities with hot asphalt concrete according to Section 404. Spread and compact the hot asphalt concrete in layers parallel to the grade line not exceeding 2 inches in compacted depth.
403.16_nat_us_03_02_2005
403.16 Pavement Smoothness.
Delete the heading and replace with the following:
Pavement Smoothness and Surface Tolerance Add the following:
The maximum variation from the compacted width is 3 inches and the average width of 4 or measurements for any ½ mile of road segment is the specified width.
The maximum variation from the compacted specified thickness is ¼ inch and the average thickness of 4 measurements for any ½ mile of road segment is the specified thickness
403.17_nat_us_03_02_2005
Table 403-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Pavement Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mile |
| Pavement after compaction |
| - |
| 4 Hours |
| Pavement Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mile |
| Pavement after compaction |
| - |
| 4 Hours |
412 - Asphalt Tack Coat 412.07_nat_us_07_03_2007 Measurement
412.07 Acceptance
Delete the first paragraph and replace with the following:
Emulsified asphalt will be evaluated under Subsections 106.02, 106.03, and 702.07.
601 - Minor Concrete 601.00_nat_us_02_27_2007 Delete the entire specification and replace it with the following:
Description
601.01 This work consists of constructing minor concrete structures.
Material
601.02 Conform to the following Subsections:
| Air-entraining admixtures |
| 711.02 |
| Chemical admixtures |
| 711.03 |
| Coarse aggregate |
| 703.02 |
| Concrete coloring agents |
| 711.05 |
| Curing material |
| 711.01 |
| Fine aggregate |
| 703.01 |
| Fly ash |
| 725.04 |
| Hydraulic Cement |
| 701.01 |
| Joint fillers |
| 702.01 |
| Precast concrete curbing |
| 725.06 |
| Precast concrete units |
| 725.11 |
| Reinforcing steel |
| 709.01 |
| Structural steel |
| 717.01 |
| Water |
| 725.01 |
601.03 Concrete Composition. Use the designated concrete composition:
(a) Method A. Submit a mix design showing the proposed masses of aggregate, water, and cement per cubic yard of concrete a minimum of 7 days prior to beginning placement. Proportion the cement, aggregate, and water to obtain concrete with good workability.
Composition of Minor Structure Concrete
| Property |
| Specification |
| Test Method |
| Slump |
| 4 in maximum |
| AASHTO T 119 |
| Air content |
| 5 to 7 percent |
| AASHTO T 152 or T 196 |
| 28-day compressive strength |
| 3000 psi |
| AASHTO T 23 and T 22 |
(b) Method B. Submit the following information a minimum of 7 days prior to beginning placement:
(1) Type, grading, and sources of aggregate.
(2) Type and source of cement, blended cement, or fly ash.
(3) Saturated surface dry weights of the fine and coarse aggregate in pounds per cubic yard of concrete.
(4) Weight of mixing water in pounds per cubic yard of concrete.
(5) Weight of cement in pounds per cubic yard of concrete.
(6) Admixture type, quantity, and certification by manufacturer.
(7) Air content.
(8) Slump.
(9) 28-day compressive strength.
Furnish concrete containing not less than 680 pound of cement per cubic yard. Ensure that slump is 4 inches or less, as determined by AASHTO T 119.
(c) Method C. Make the concrete using a dry, preproportioned, blended, and bagged mix meeting the requirements of ASTM C 387 and mixed at the jobsite according to the manufacturer’s recommendations.
(d) Fly Ash- or Pozzolan-Modified Concrete. Fly ash may be substituted for cement at the rate of 20 ounces of fly ash per 16 ounces of Portland cement. After substitution, reduce the design aggregate volumes by an amount equal to the net increase in volume of the combined cement and fly ash. Replace no less than 10 percent and no more than 20 percent of the weight of Portland cement required with fly ash at the above rate. For purposes of controlling the maximum water/cement ratio of 0.49, make the water/cement ratio for fly-ash-modified concrete the ratio of the weight of water to the combined weights of Portland cement and 60 percent of the weight of the fly ash.
Extend the standard 28-day curing period for compressive-strength tests for fly-ash modified concrete by 1 day (rounded to the nearest whole day) for each 1.5 percent of Portland cement replaced with fly ash at the selected rate. (Example: If the maximum of 20 percent cement is replaced, the curing period for cylinders is 41 days.)
Construction Requirements
601.04 General. Perform excavation and backfill work according to Section 209. When concrete is cracked, spalling, or scaling, remove concrete to the nearest joint.
Design and construct forms that are free of bulge and warp and allow for removal without injuring the concrete. When concrete contains a retarding admixture, fly ash, or other pozzolan replacement for cement, design the forms for a lateral pressure equal to that exerted by a fluid with a mass of 2.5 ton per cubic yard.
Use wood, metal, or other suitable material for forms. Keep forms clean and coat with a form release agent or form oil before placing concrete.
Place and fasten reinforcing steel according to Subsection 554.08.
601.05 Placing Concrete. Place all reinforcing steel in position and ensure that it is securely held in place by approved supports during placing of concrete. Do not place concrete until the grading, forms, and steel reinforcements have been inspected and approved by the COR. Provide 24 hours written notice prior to placement of any concrete.
Place reinforcing steel according to Section 554.
Discharge all concrete prepared using methods A and B into the forms within the time limits shown in table 601-1. These time limits are based on jobsite ambient air temperature, cement type, and admixture used. Begin counting time from when the cement is introduced into the aggregate. Discharge concrete prepared using method C into the forms within 1-1/2 hours after introducing water to the mixture. Do not retemper concrete. When required cement must be added to the mixer at the jobsite. Do not mix or place concrete when the temperature is, or is expected to be, less than 40 °F unless adequate provisions are made to protect the concrete.
Place concrete to avoid segregation. Use high-frequency internal vibrators for consolidating concrete in the forms. Operate vibrators to produce concrete free of voids, but do not hold them in one place long enough to result in segregation or formation of laitance on the surface.
Method C concrete may be rodded instead of internally vibrated as necessary to remove voids.
Do not use aluminum pipe, conduit, or troughs for transporting concrete. When concrete is pumped, take samples from the discharge stream at the point of placement. Do not apply water to plastic concrete surfaces during finishing operations.
Table 601-1 Concrete discharge time limits.
| Cement Type With and Without Admixtures |
| Time limit (hour) |
| < 85 oF1 |
| >85 oF1 |
| Type I, IA, II, or IIA |
| 2.0 |
| 1.5 |
| Type I, IA, II, or IIA with water reducing or retarding admixture |
| 3.0 |
| 2.0 |
| Type III |
| 1.5 |
| 1.0 |
| Type III with water reducing or retarding admixture |
| 2.0 |
| 1.5 |
1 Ambient air temperature.
601.06 Curing Concrete. Cure concrete a minimum of 7 days. If high early strength cement is used, cure concrete a minimum of 3 days. Cure according to Subsection 552.15. Finish according to Subsection 552.16 Class 1- Ordinary Surface Finish.
601.07 Acceptance. Material for minor concrete structures including reinforcing steel, and structural steel for minor structures will be evaluated under Subsections 106.03. The concrete mixture's slump, air content, unit mass, and temperature will be evaluated under Subsections 106.02 and 106.04. See Tables 552-1 and 552-2 for specification limits.
Excavation and backfill will be evaluated under Section 209.
Construction of minor concrete structures will be evaluated under Subsections 106.02 and 106.04.
Measurement
601.08 Measure the Section 601 items listed in the bid schedule according to Subsection 109.02.
Payment
601.09 The accepted quantities will be paid at the contract price per unit of measurement for the Section 601 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
The concrete lump sum item will be prorated based on the progress of the work under this Section.
633 - Permanent Traffic Control 633.02_nat_us_03_03_2005
633.02 Material.
Add the following subsections
| Protective Overlay Film |
| 718.02 |
| Edge Film |
| 718.02 |
633.03_nat_us_03_03_2005
633.03 General.
Delete the subsection and add the following:
Furnish traffic control devices and guide signs according to the MUTCD, approved USDA-FS and state supplements, the current edition of USDA-FS EM-7100-15 Sign and Poster Guidelines for the Forest Service, and Standard Highway Signs published by FHWA. Submit the sign list for approval before ordering.
633.05_nat_us_03_03_2005
633.05 Panels.
Add the following:
Apply protective overlay film and top edge film as required and according to with manufacturer’s recommendations.
Delete the sentence: “Use antitheft fasteners where possible” in the fifth paragraph and replace it with the following: “For each sign panel use at least one antitheft fastener.”
718 - Traffic Signing and Marking Material 718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
818 - Asphalt Crack Cleaning and Sealing (5/97)
1. Description This work shall consist of cleaning and filling cracks in existing asphalt concrete surfaces that are 1/4-inch wide and wider. This work shall be performed and paid for in accordance with the following specifications.
2. Equipment All methods employed in performing the work and all equipment, tools and machinery used for handling the material and executing any part of the work shall be subject to the approval of the Government before the work is started, and whenever unsatisfactory, they shall be changed or improved as required. All equipment, tools, machinery and containers must be kept clean and maintained in satisfactory condition.
Sealing equipment shall consist of a double boiler type machine, capable of maintaining the temperature of the material in the range of 350 to 400 degrees Fahrenheit, with continuous circulation and agitation. Material shall never be heated above 400 degrees Fahrenheit.
3. Materials The sealing material shall comply with the requirements of ASTM D 3405-78 and AASHTO M 301-85. The Contractor shall submit a certificate of compliance signed by the manufacturer certifying that the material meets these requirements. The certificate shall be submitted prior to the use of the material in the work.
4. Requirements
| a. Cleaning of cracks: The cracks shall be steel wire brushed, broomed, cleaned using compressed air or pressurized water jet, or cleaned and dried using a hot lance (use of a back-pack hot air blower will not be sufficient), as shown in the Schedule of Items, in order to remove all loose material, vegetation, and other objectionable material. |
| b. Filling: Filling of cracks and voids shall not commence until they are clean and dry. When the use of a hot lance is required, filling should closely follow cleaning. The cracks shall be sealed from the bottom up. The filler material shall be placed within 1/8-inch of the top of the crack. Any excess material shall be leveled flush to the surface with a "V" shaped squeegee device. The excess material will be squeegeed so as not to exceed 1 1/2-inches on each side of the crack. Excess material remaining in the squeegee at the end of the crack will be distributed over the crack in a return motion. If settlement of the filler material occurs, the cracks shall be refilled until they are again within 1/8-inch of the finished surface. No excess build-up of filler material will be permitted. Any spillage or loose material shall be removed from the surface. |
| c. Weather Limitations: The filler material shall not be applied when it is raining, excessive moisture is present, or either atmospheric or pavement temperature is 45 degrees Fahrenheit and falling. Filler material may be applied when moisture is not present and either the atmospheric or pavement temperature is 40 degrees Fahrenheit and rising. |
5. Measurement The quantity will be measured by the linear foot, lump sum, or pound of filler material used as shown in the Schedule of Items. When measurement by the pound is specified, the Government may require the weighing of equipment for determination of actual quantities of material used. Payment by the pound will not include any materials wasted or not used as specified.
6. Payment
| a. Payment shall be made at the contract unit price for cracks repaired as specified. This payment shall be full compensation for all labor, equipment, materials, traffic control, tools and incidentals necessary to complete the work. |
| b. Payment will be made under: |
Pay Item Pay Unit 818(1) Crack Cleaning and Sealing Lump Sum image1.png