- EBBETT'S PASS SNOW-PARK CONSTRUCTION Federal contract opportunity
- Solicitation number
- AG-9JGP-S-15-0103
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Attendance_Ebbetts_Pass.docx | DOCX document | |
| Pre-Work_Meeting_Notes.docx | DOCX document | |
| CalTrans_Standard_Specs.pdf | ||
| Drawings-rev1.pdf | ||
| SF30_Amend_002_Ebbetts_Sno_Park.doc | DOC document | |
| Amendment_001.pdf | ||
| Project_Specifications.pdf | ||
| Wage_Determination.pdf | ||
| Drawings.pdf | ||
| Caltrans_Encroachment_Permit.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
www.acquisition.gov/far/
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-9JGP-S-15-0103
2. TYPE OF SOLICITATION
FORMCHECKBOX
SEALED BID (IFB)
FORMCHECKBOX
NEGOTIATED (RFP)
3. DATE ISSUED
PAGE
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
735903
6. PROJECT NO.
7. ISSUED BY
CODE
| 8. ADDRESS OFFER TO |
USDA Forest Service Central California Acquisitions
631 Coyote Street
Nevada City, CA 95959 USDA Forest Service
Central California Acquisitions
631 Coyote Street
Nevada City, CA 95959
9. FOR INFORMATION CALL:
A. NAME
Technical: Tim Hughes Contracting: Matthew Gagnon B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 209-532-3671 530-478-6826
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
EBBETTS PASS SNO-PARK CONSTRUCTION
STANISLAUS NATIONAL FOREST
Price Range The Government's estimate is between $250,000 and $500,000.
ORIGINAL bid bonds must be received before the due date and time in block 13.
Contractor MUST be registered the System for Award Management (www.sam.gov).
**Please provide the following information:**
DUNS#_____________
11. The Contractor shall begin performance within 10 calendar days and complete it within 54 calendar days after receiving
FORMCHECKBOX
award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
FORMCHECKBOX
YES
FORMCHECKBOX
NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.
Sealed, original offer to perform the work required are due at the place specified in Item 8 by 4:30 p.m. (hour) local time on September 8, 2015. (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B.
An offer guarantee
FORMCHECKBOX
is, FORMCHECKBOX is not required.
C.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.
Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
1442-101
STANDARD FORM 1442 (REV. 4-85)
Computer Generated
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE
FACILITY CODE
17.
The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
FORMCHECKBOX
10 U.S.C. 2304(c)( )
FORMCHECKBOX
41 U.S.C. 253(c)( 5 )
26. ADMINISTERED BY
CODE
| 27. PAYMENT WILL BE MADE BY |
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
FORMCHECKBOX
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
FORMCHECKBOX
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
MATTHEW GAGNON
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated
STANDARD FORM 1442 BACK (REV. 4-85)
PART 1: SCHEDULE OF ITEMS
SECTION B
SUPPLIES/SERVICES & PRICE/COSTS
| PROJECT |
| EBBETTS PASS SNO-PARK CONSTRUCTION |
| UNIT |
| STANISLAUS NATIONAL FOREST |
| SOLICITATION NO |
| AG-9JGP-S-15-0103 |
| ITEM NO. |
| ITEM |
| DESCRIPTION |
| METHOD OF MEASURE |
| UNIT |
| QUANTITY |
| UNIT PRICE |
| TOTAL PRICE |
| Mobilization |
| DQ |
| LS |
| 1 |
| 2 |
| 17005 |
| Develop water supply & water |
| LSQ |
| LS |
| 1 |
| Prepare WPCP |
| LSQ |
| LS |
| 1 |
| Rough Grading |
| DQ |
| LS |
| 1 |
| Import & final Grading |
| DQ |
| LS |
| 1 |
| Place 3” PVC underground (electric) |
| DQ |
| LF |
| 340 |
| Place 2” PVC Waterline |
| DQ |
| LF |
| 340 |
| 8 |
| 30115 |
| Aggregate surface course (Type B, |
Compaction method C
| CQ |
| CY |
| 335 |
| 9 |
| 40401 |
| 3” Deep minor hot bituminous concrete |
| CQ |
| CY |
| 115 |
| 10 |
| 63359 |
| Installing signs |
| LSQ |
| LS |
| 1 |
| Striping |
| LSQ |
| LF |
| 1 |
| 12 |
| 63501 |
| Temporary traffic control |
| LSQ |
| LS |
| 1 |
| Install vault toilet |
| LSQ |
| LS |
| 1 |
TOTAL:
NOTES
1.) Respondent must price each item to be considered for an award.
2.) Responses for quantities less than those listed may be rejected
3.) If award is made in the excess of $30,000.00, bonds will be required.
4.) If response is greater than $150,000, include bid bond=20%of the total price.
5.) Following are abbreviation definitions from FP=03, Section 109 that may appear in the “Unit" COLUMN OF THE Schedule of Items;
AC=Acre, CQ=Contract Quantity, CY= Cubic Yard, EA=Each, GAL=Gallon, HR=Hour, LF=Linear Foot, LS=Lump Sum, MI=Mile, LB=Pound, SF=Square Foot, SY=Square yard, ST=Station, TON=Ton. CQ and LS will be measured and paid as stated in FP-03, Section 109-02. All other Units will be paid according to FAR clause 52.211-18, Variation in
Estimated Quantity.
PRICE SUBMITTED BY:
Signature
Phone
Vendor Name
Fax
Address
DUNS Number
Contact
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
The project will allow safe year-round parking and pull-through for vehicles during winter recreation as well as provide restroom facilities. Additionally, the project is the next step in creating a visitor information and interpretation center with high scenic, natural, and cultural values. The future relocation and ADA retrofitting of a historic guard station will provide visitors with information, maps, and interpretive products. The parking lot construction is part of the previously approved site plan and the improved health and safety conditions are consistent with Corridor Management Plan.
Project Location
From Sonora, CA, travel north on CA-49 N/S Washington St. Continue to follow CA-49N 2.4 miles. Turn right onto Broadway St / Parrots Ferry Rd (Signs for Parrots Ferry Rd / Columbia / County Road E18). Continue on Parrots Ferry Rd 11.8 miles. Turn right onto CA-4 E (Signs for Murphys). Continue on CA-4E for 42.6 miles. Turn right onto Silvertip Campground Road. Project location is immediately to the left.
NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)
Price Range The Government's estimate is between $250,000 and $500,000.
Estimated Start Date: September 8th, 2015 Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section F for additional information.
Restrictions on Work
Time of Work Restricted to Monday through Friday from 0700 to 1700.
1. In accordance with the fire plan, if included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
Worker's Compensation Insurance
The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
Camping and Housing (see also Section H, Camping Permit Compliance)
Camping is not permitted in US Forest Service campgrounds. Contractor will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
Maps
INCLUDED WITH DRAWINGS
Drawings and Specifications
Project Drawings: The following drawings are part of this solicitation:
(1) Title Sheet, Vicinity Map, (2) Construction Layout Plan, (3) Sign and Striping Plan, (4) Sign and Striping Details, (5) Section Views, (6) Details, (7) Accessible Parking Details, (8) Erosion Control Plan.
Specifications:
Construction Standard Institute (CSI) specifications
These specifications are physically incorporated in the solicitation.
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects
FP-03 (US Customary Units)
This document is incorporated by reference and is available on the web in either MS Word
(http://www.wfl.fha.dot.gov/design/specs/English/FP03_USCust_final_111403.doc) or Acrobat
(http://www.wfl.fha.dot.gov/design/specs/English/FP03_USCust_final_111403.pdf)
It is also available as a wire-bound book that can be purchased from the US Government Printing
Office:
Superintendent of Documents U.S. Government Printing Office Internet: bookstore.gpo.gov Phone: (toll free) 866.512.1800 Fax: 202.512.2250 Mail: Stop SSOP, Washington, DC 20402-0001
Stock Number: 050-001-00341-4 (U.S. Customary)
1996 road and bridge specifications-- Standard Specifications applicable to this project can be found in Forest Service Specifications for Construction of Roads & Bridges, August 1996 (EM-7720-100), which is incorporated by reference. The publication is available for purchase from the Superintendent of Documents, US Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00660-2. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad 1985 road and bridge specifications-- Standard Specifications applicable to this project can be found in Forest Service Specifications for Construction of Roads & Bridges, April 1985, which is incorporated by reference. The publication is out of print. Contact the issuing office for copies of relevant specifications.
Trail specifications-- Standard Specifications applicable to this project can be found in Standard Specifications for Construction and Maintenance of Trails, September 1996 (EM-7720-103), which is incorporated by reference. The publication is available for purchase from the Superintendent of Documents, US Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00661-1. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad
Special Project Specifications are physically incorporated within this solicitation, beginning on the next page.
The following Standard and Special Project Specifications are applicable to this contract:
| Document |
| Description |
| Date |
| 1 |
| Contract Documents (CALTrans) |
| 2/7/2013 |
The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-4 Inspection of Services--Fixed-Price (AUG 1996)
E.1 QUALITY CONTROL PLAN – The Contractor shall conduct inspections on all units in accordance with his/her Quality Control Plan (QCP). The Contractor’s Quality Control Plan shall be submitted and accepted by the Government prior to any work starting.
E.2 GOVERNMENT INSPECTIONS
Government inspections are for the purpose of satisfying the Government that the services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control.
The Contracting Officer's Representative or designated inspector will conduct all inspections. The Contractor (or designated representative) is encouraged to be present to observe inspections. Summary results will be made available on request.
Compliance Inspections. Visual compliance inspections will be made on a periodic basis. Such inspections are not final and do not constitute acceptance by the Government.
Final Inspections. Final (formal) inspections for payment will be made on completed sub-items only. Contractor shall request final inspections in writing and give the Forest Service at least two working days advanced notice. Inspections will be completed within four working days after the notice is received If the work is not ready for inspection at the time specified by the Contractor, the cost associated with the inspection attempt may be charged to the Contractor.
Disputed Inspection.
The Contractor may request reinspection without rework if the results are unacceptable. Reinspection must be requested in writing within 48 hours after receiving written notice of the inspection results. Reinspection will be accomplished within five working days after receipt of the contractor's written request.
The same sampling and inspection procedures will be used, but new samples will be taken. The inspection pattern will be shifted so that new samples will not overlap previously inspected samples. Results will be rounded to the nearest whole percent.
If reinspection results are within five percentage points of the first inspection, the original inspection result will be used in determining acceptability and payment. If reinspection results are greater than five percentage points above or below the first inspection, the reinspection results will be used.
If the reinspection results are within five percentage points of the first inspection, the Contractor shall pay the actual costs of the reinspection.
Reinspection after Rework. Where rework after a failed inspection may improve the inspection results, the Contractor may rework the area and request (in writing) a second inspection. The Government will charge to the Contractor the cost of this additional inspection. Reinspection will be accomplished within five working days after the notice is received. The results of the second inspection will be final, and no further rework will be permitted. Areas not ready for reinspection at the time specified by the Contractor will not be reinspected, and the results of the first inspection will be final.
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 54 days after the effective date of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
Work Timing
Delays due to normal adverse weather, weekends, and holidays have been included in the calculation of contract time.
Winter Shutdown
When winter weather sets in and the continuation of work is impractical, the Contracting Officer may authorize a total suspension until such time as work can proceed. During the period of total suspension, the calendar days elapsed will not be charged against the contract time specified.
SECTION G--CONTRACT ADMINISTRATION DATA
GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
TWO (2) CXT VAULT TOILETS
Invoices
Payment will be made from the contractor’s invoice. All invoices are to be submitted via the electronic Invoice Processing Platform (IPP). This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. There is no pre-award registration.
After award of a contract, please make sure that your company registers promptly at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. PRIOR to starting the IPP enrollment process, please verify that the point of contact’s (POC’s) email address is up to date in your company’s System for Award Management (SAM) account at www.sam.gov and that any recent update(s) have been allowed time to process resulting in an “Active” status on the SAM account. The one-time enrollment in IPP means a series of emails will be sent to the SAM POC. If you have questions on the IPP enrollment process, the help desk phone number is 1-866-973-3131.
Payment for Materials Off Site
In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary. The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.
Incidental Items
The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment of items shown.
Preconstruction Conference
This required conference will be scheduled by the COR. (See also Section I, Clause 52.236-26.)
PAYMENT CERTIFICATION
I hereby certify, to the best of my knowledge and belief, that—
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
(Name)
(Title)
(Date)
(Invoiced Timeframe)
SECTION H--SPECIAL CONTRACT REQUIREMENTS
Emergencies
Fire Plan: See Section J, Fire Plan
Area of Responsibility for Fire. Unless otherwise noted elsewhere in the contract, the following define the limits of a contractor's area of responsibility for fire under the terms of the Fire Plan (Section J):
Special for this project:
Utility Services
NONE
Superintendence by Contractor
In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.
Loss, Damage or Destruction
Equipment Furnished with Operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.
Other. Even though this contract may provide for performing services at the direction of Government personnel, the contract is not for personal services, and neither the Contractor nor his or her personnel are Government employees. The Government assumes no liability for injury occurring to Contractor personnel or to third parties, or for loss, damage, or destruction involving third parties' property as a result of the Contractor's operation. Except that the Government is liable for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) acting within the scope of their employment.
Camping Permit Compliance
Contractor shall comply with all terms and conditions of any camping permit issued to allow use of premises. Any non-compliance will result in suspension of work until compliance is achieved.
Archaeological and Historic Sites
Location of known archaeological, historic, or pre-historic materials--such as Amerind artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (l6 USC 433)--will be identified for the contractor before work commences.
Spill Plan
If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a registered professional engineer. The Contractor under the direction of the Contracting Officer, or in the absence of said officer, acting independently, shall immediately take action to contain and clean up, without expense to the Government, all petroleum products spills on or in the vicinity of the project which are caused by the Contractor's employees directly or indirectly as a result of contract operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government for the containment and clean up of petroleum products spills caused by Contractor's employees or resulting from contract operations. The Contractor shall immediately report all petroleum products spills to the Contracting Officer.
Equipment Cleaning
All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use.
Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection.
If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es) www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (May2014))
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures (May 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal
Transactions (SEP 2007)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double- Sided on Recycled Paper (MAY 2011)
52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011 52.204-14 Service Contract Reporting Requirements (Jan 2014) (Pub. L. 111-117, section 743 of Div. C).
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013)
52.215-2 Audit and Records -- Negotiation (OCT 2010)
52.219-3 Notice of Total HUBZone Set-Aside (NOV 2011)
52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-9 Small Business Subcontracting Plan (JAN 2011) (Applicable if > $1.5 Million)
Alternate II (Oct2014) 52.219-16 Liquidated Damages --Subcontracting Plan (JAN 1999) (Applicable if > $1 Million) 52.219-28 Post Award Small Business Program Representations (JUL 2013)
52.219-29
(JUL 2013)
52.222-3 Convict Labor (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (MAY 2014)
52.222-6 Davis-Bacon Act (MAY 2014)
52.222-7 Withholding of Funds (MAY 2014)
52.222-8 Payrolls and Basic Records (MAY 2014)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations (MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015)
52.222-26 Equal Opportunity (APR 2015)
52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-35 Equal Opportunity for Veterans (JUL 2014)
52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014)
52.222-37 Employment Reports on Veterans (JUL 2014)
52.222-50 Combating Trafficking In Persons (MAR 2015)
52.223-1 Biobased Product Certification (MAY 2012)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
52.223-6 Drug-Free Workplace (MAY 2001)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-1 Authorization and Consent (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)
52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997)
52.228-11 Pledges of Assets (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014)
52.228-14 Irrevocable Letter of Credit (NOV 2014)
52.228-15 Performance and Payment Bonds – Construction (OCT 2010)
52.229-3 Federal, State, and Local Taxes (FEB 2013)
52.229-4 Federal, State, and Local Taxes (State and Local Adjustments) (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014)
52.232-9 Limitation on Withholding of Payments (APR 1984)
52.232-17 Interest (MAY 2014)
52.232-23 Assignment of Claims (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer— System for Award Management (JUL 2013)
52.233-1 Disputes (MAY 2014)--Alternate I (DEC 1991)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by The Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984)
Alternate I (APR 1984)
52.236-17 Layout of Work (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997)
52.236-26 Preconstruction Conference (FEB 1995)
52.242-13 Bankruptcy (JUL 1995)
52.243-4 Changes (JUN 2007)
52.244-6 Subcontracts for Commercial Items (APR 2015)
52.245-1 Government Property (APR 2012) Applicable if govt property is provided under this contract.
52.245-9 Use and Charges (APR 2012) Applicable if govt property is provided under this contract.
52.246-21 Warranty of Construction (MAR 1994) Alternate I (APR 1984)
52.248-3 Value Engineering – Construction (OCT 2010)
52.249-2 Termination for Convenience of the Government (APR 2012)--Alternate I (SEP 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
52.211-6 Brand Name or Equal (Aug 1999)
(a) If an item in this solicitation is identified as “brand name or equal,” the purchase description reflects the characteristics and level of quality that will satisfy the Government’s needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation.
(b) To be considered for award, offers of “equal” products, including “equal” products of the brand name manufacturer, must—
(1) Meet the salient physical, functional, or performance characteristic specified in this solicitation;
(2) Clearly identify the item by—
(i) Brand name, if any; and
(ii) Make or model number;
(3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer; and
(4) Clearly describe any modifications the offeror plans to make in a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modifications.
(c) The Contracting Officer will evaluate “equal” products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.
(d) Unless the offeror clearly indicates in its offer that the product being offered is an “equal” product, the offeror shall provide the brand name product referenced in the solicitation.
52.211-18 Variation in Estimated Quantity (Apr 2014)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
52.219-14 Limitations on Subcontracting (Nov 2011)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Applicability. This clause applies only to—
(1) Contracts that have been set aside or reserved for small business concerns or 8(a) concerns;
(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) concerns; and
(3) Orders set aside for small business or 8(a) concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) By submission of an offer and execution of a contract, the Offeror/Contractor agrees that in performance of the contract in the case of a contract for—
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.
52.222-40 – Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)
(a) During the term of this contract, the Contractor shall post an employee notice, of such size and in such form, and containing such content as prescribed by the Secretary of Labor, in conspicuous places in and about its plants and offices where employees covered by the national Labor Relations Act engage in activities relating to the performance of the contract, including all places where notices to employees are customarily posted both physically and electronically, in the languages employees speak, in accordance with 29 CFR 471.2(d) and (f).
(1) Physical posting of the employee notice shall be in conspicuous places in and about the Contractor’s plants and offices so that the notice is prominent and readily seen by employees who are covered by the National Labor Relations Act and engage in activities related to the performance of the contact.
(2) If the Contractor customarily posts notices to employees electronically, then the Contractor shall also post the required notice electronically by displaying prominently, on any Web site that is maintained by the Contractor and is customarily used for notices to employees about terms and conditions of employment, a link to the Department of Labor’s Web site that contains the full text of the poster. The link to the Department’s Web site, as referenced in (b)(3) of this section, must read, “Important Notice about Employee Rights to Organize and Bargain Collectively with Their Employers.”
(b) This required employee notice, printed by the Department of Labor, may be—
(1) Obtained from the Division of Interpretations and Standards, Office of Labor-Management Standards, U.S. Department of Labor, 200 Constitution Avenue, NW., Room N-5609, Washington, DC 20210, (202) 693-0123, or from any field office of the Office of Labor-Management Standards or Office of Federal Contract Compliance Programs;
(2) Provided by the Federal contracting agency if requested;
(3) Downloaded from the Office of Labor-management Standards Web site at http://www.dol.gov/olms/regs/compliance/EO13496.htm ; or
(4) Reproduced and used as exact duplicate copies of the Department of Labor’s official poster.
(c) The required text of the employee notice referred to in this clause is located at Appendix A, Subpart A, 29 CFR Part 471.
(d) The Contractor shall comply with all provisions of the employee notice and related rules, regulations, and orders of the Secretary of Labor.
(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 and subpart 9.4 Such other sanctions or remedies may be imposed as are provided by 29 CFR part 471, which implements Executive Order 13496 or as otherwise provided by law.
(f) Subcontracts.
(1) The Contractor shall include the substance of this clause, including this paragraph (f), in every subcontract that exceeds $10,000 and will be performed wholly or partially in the Unites States, unless exempted by the rules, regulations, or orders of the Secretary of Labor issued pursuant to section 3 of Executive Order 13496 of January 30, 2009, so that such provisions will be binding upon each subcontractor.
(2) The Contractor shall not procure supplies or services in a way designed to avoid the applicability of Executive Order 13496 or this clause.
(3) The Contractor shall take such action with respect to any such subcontract as may be directed by the Secretary of Labor as a means of enforcing such provisions, including the imposition of sanctions for noncompliance.
(4) However, if the Contractor becomes involved in litigation with a subcontractor, or is threatened with such involvement, as a result of such direction, the Contractor ma request the United States, through the Secretary of Labor, to enter into such litigation to protect the interests of the United States.
52.222-54 Employment Eligibility Verification (Aug 2013)
(a) Definitions. As used in this clause—
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply that is—
(i) A commercial item (as defined in paragraph (1) of the definition at 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products. Per 46 CFR 525.1 (c)(2), “bulk cargo” means cargo that is loaded and carried in bulk onboard ship without mark or count, in a loose unpackaged form, having homogenous characteristics. Bulk cargo loaded into intermodal equipment, except LASH or Seabee barges, is subject to mark and count and, therefore, ceases to be bulk cargo.
“Employee assigned to the contract” means an employee who was hired after November 6, 1986 (after November 27, 2009 in the Commonwealth of the Northern Mariana Islands), who is directly performing work, in the United States, under a contract that is required to include the clause prescribed at 22.1803. An employee is not considered to be directly performing work under a contract if the employee—
(1) Normally performs support work, such as indirect or overhead functions; and
(2) Does not perform any substantial duties applicable to the contract.
“Subcontract” means any contract, as defined in 2.101, entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.
“Subcontractor” means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime Contractor or another subcontractor.
“United States”, as defined in 8 U.S.C. 1101(a)(38), means the 50 States, the District of Columbia, Puerto Rico, Guam, the Commonwealth of the Northern Mariana Islands, and the U.S. Virgin Islands.
(b) Enrollment and verification requirements.
(1) If the Contractor is not enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall—
(i) Enroll. Enroll as a Federal Contractor in the E-Verify program within 30 calendar days of contract award;
(ii) Verify all new employees. Within 90 calendar days of enrollment in the E-Verify program, begin to use E-Verify to initiate verification of employment eligibility of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); and
(iii) Verify employees assigned to the contract. For each employee assigned to the contract, initiate verification within 90 calendar days after date of enrollment or within 30 calendar days of the employee’s assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).
(2) If the Contractor is enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall use E-Verify to initiate verification of employment eligibility of—
(i) All new employees.
(A) Enrolled 90 calendar days or more. The Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or
(B) Enrolled less than 90 calendar days. Within 90 calendar days after enrollment as a Federal Contractor in E-Verify, the Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or
(ii) Employees assigned to the contract. For each employee assigned to the contract, the Contractor shall initiate verification within 90 calendar days after date of contract award or within 30 days after assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).
(3) If the Contractor is an institution of higher education (as defined at 20 U.S.C. 1001(a)); a State or local government or the government of a Federally recognized Indian tribe; or a surety performing under a takeover agreement entered into with a Federal agency pursuant to a performance bond, the Contractor may choose to verify only employees assigned to the contract, whether existing employees or new hires. The Contractor shall follow the applicable verification requirements at (b)(1) or (b)(2) respectively, except that any requirement for verification of new employees applies only to new employees assigned to the contract.
(4) Option to verify employment eligibility of all employees. The Contractor may elect to verify all existing employees hired after November 6, 1986 (after November 27, 2009, in the Commonwealth of the Northern Mariana Islands), rather than just those employees assigned to the contract. The Contractor shall initiate verification for each existing employee working in the United States who was hired after November 6, 1986 (after November 27, 2009, in the Commonwealth of the Northern Mariana Islands), within 180 calendar days of—
(i) Enrollment in the E-Verify program; or
(ii) Notification to E-Verify Operations of the Contractor’s decision to exercise this option, using the contact information provided in the E-Verify program Memorandum of Understanding (MOU).
(5) The Contractor shall comply, for the period of performance of this contract, with the requirements of the E-Verify program MOU.
(i) The Department of Homeland Security (DHS) or the Social Security Administration (SSA) may terminate the Contractor’s MOU and deny access to the E-Verify system in accordance with the terms of the MOU. In such case, the Contractor will be referred to a suspension or debarment official.
(ii) During the period between termination of the MOU and a decision by the suspension or debarment official whether to suspend or debar, the Contractor is excused from its obligations under paragraph (b) of this clause. If the suspension or debarment official determines not to suspend or debar the Contractor, then the Contractor must reenroll in E-Verify.
(c) Web site. Information on registration for and use of the E-Verify program can be obtained via the Internet at the Department of Homeland Security Web site: http://www.dhs.
HYPERLINK "http://www.dhs.gov/E-Verify" gov/E-Verify.
(d) Individuals previously verified. The Contractor is not required by this clause to perform additional employment verification using E-Verify for any employee—
(1) Whose employment eligibility was previously verified by the Contractor through the E-Verify program;
(2) Who has been granted and holds an active U.S. Government security clearance for access to confidential, secret, or top secret information in accordance with the National Industrial Security Program Operating Manual; or
(3) Who has undergone a completed background investigation and been issued credentials pursuant to Homeland Security Presidential Directive (HSPD)-12, Policy for a Common Identification Standard for Federal Employees and Contractors.
(e) Subcontracts. The Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for identification of the parties), in each subcontract that—
(1) Is for—
(i) Commercial or noncommercial services (except for commercial services that are part of the purchase of a COTS item (or an item that would be a COTS item, but for minor modifications), performed by the COTS provider, and are normally provided for that COTS item); or
(ii) Construction;
(2) Has a value of more than $3,000; and
(3) Includes work performed in the United States.
FAR 52.225-9 Buy American Act—Construction Materials (MAY 2014)
(a) Definitions. As used in this clause- "Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Domestic construction material" means-
(1) An unmanufactured construction material mined or…