Amendment 002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A1_CA4 _mod_2 _dated_022616.pdf | ||
| North_Fork_Eel_Stormproofing _Amendment_001.pdf | ||
| A5_SF_24_BID_BOND.pdf | ||
| A1_NFEel_lNotes_ _Road_Logs.pdf | ||
| A3_PAL_Fire_Plan.pdf | ||
| AG-9AC7-S-16-0032_Solicitation.pdf | ||
| A4_CA4 _Mod_1 _dated_012916_hwy_Humboldt_Co.pdf | ||
| A2_North_Fork_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-9AC7-S-16-0032
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
9AC7
REDDING CA 96002
3644 AVTECH PARKWAY SUITE 180
R5 NO-CAL ACQ SERVICE AREA NCASA
USDA FOREST SERVICE
02/08/2016000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/08/2016
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
North Fork Eel Stormproofing, Humboldt County
This amendment changes the Schedule of Items and the description in the Road Log. Quantity changes have been made to clearing and grubbing and the 48-inch culvert Specification
30303 has changed to 30301 Roadway Reconditioning and specification 20401 has changed to
20467-1 for Driveable Drainage Dip and modified 20467 to 20467-2 from rolling waterbar to
Driveable waterbar - no aggregate. Remove and replace the Schedule of Items in the solicitation (page 6) and Page 1 of the attachment Road Log.
The time for receipt of offers is not changed. All other terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MARILYN LADD
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
3/14/2016
North Fork Eel Stormproofing, Six Rivers NF -6- AG-9AC7-S-16-0032 – Amendment 2
PART I - SCHEDULE OF ITEMS
SECTION B - Supplies or Services and Prices/Costs Schedule of Items
North Fork Eel Stormproofing
Six Rivers National Forest
Item No. Item Description Unit Total Unit Total
15101 Mobilization LS All $______________ $_______________
15801 Watering for dust control MGAL 192 $______________ $_______________
20101 Clearing and Grubbing MI 4 $______________ $_______________
20305 Removal of Culverts (Method A) EA 8 $______________ $_______________
20467-1 Drivable Drainage Dip w/ aggregate EA 176 $______________ $_______________
20467-2 Drivable waterbar no aggregate EA 171 $______________ $_______________
30201 Spot surfacing TON 200 $______________ $_______________
30301 Roadway Reconditioning MI 48 $______________ $_______________
60201-1 18 Inch Pipe Culvert, 14 Gauge LF 120 $______________ $_______________
60201-2 24 Inch Pipe Culvert, 14 Gauge LF 60 $______________ $_______________
60201-3 48 inch Pipe Culvert LF 140 $______________ $_______________
60702 Cleaning drainage structures LS 176 $______________ $_______________
62540 Mulching, Straw Bales EA 24 $______________ $_______________
Total $_______________
B.2 Note Regarding Bond Premiums
Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under
151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
North Fork Eel Stormproofing 1 | P a g e AG-9AC7-S-16-0032 – Amendment 2
NORTH FORK EEL RIVER STROMPROOFING
GENERAL NOTES-ROAD LOGS
GENERAL NOTES
Section 201 – Clearing and Grubbing: This work consists of clearing and grubbing within the clearing limits designated in the plans.
Section 203 – Removal of Structures and Obstructions: All pipes being replaced (and their accessories) shall be removed and disposed off government land in compliance with state, federal and local regulations. This section does NOT include any excavation, only the removal of the pipe and accessories.
Section 303 – Reconditioning: This work consists of reconditioning ditches, shoulders, roadbeds, and aggregate surfaces of the entire roads listed in the road logs, including grading with water and culvert replacement where indicated on the road logs. Reconditioning will also include some slide and slough removal at locations noted in the road logs.
Section 602 – Culverts and Drains: As stated in the specification, the contractor shall determine the final location, skew, length, elevations, and grade. Do not order or install culverts until the CO has accepted the final structure size, length, and alignment.
Section 607 – Cleaning, Reconditioning, and Repairing Existing Drainage Structures - Work under this section includes specifically the cleaning of all culvert inlets and outlets up to 48” diameter and any material inside the culvert when noted in the road log. The road log will detail the items of work required under this pay item.
Final shaping of the road at culvert installation and replacement sites shall be constructed so no water diversion potential exists in case the culvert plugs and fails. This shall be accomplished by shaping a dip in the road over the culvert location, or installing a rolling dip downgrade of the culvert at the soonest possible location.
Pay Item 20467-1 – Drivable Drainage Dip: This pay item includes the excavation, shaping, and aggregate surfacing for rolling dip installation. The aggregate shall be spread the full length of the constructed dip, the full width of the road, and at a 4 inch compacted depth. Aggregate is incidental to the construction and shall be included in the price.
Pay Item 20467-2 – Drivable Water Bar: This pay item includes the excavation and shaping of drivable water bars in accordance with the typical drawing provided. Water bards shall be placed where flagged on the ground. Water bars do not require aggregate.
Pay Item 30802 30201 – Spot Surfacing Roadway Aggregate: This pay item includes aggregate surfacing over culvert locations, spot rocking at locations noted in the road logs and flagged on the ground, and where required in the general notes and plans.
Pay Item 62540 – Mulching, Straw Bales: Spread uniformly across disturbed ground on fill slopes at culvert installation sites, at rates noted on the plans.
| Amendment2_sf30 |
| Schedule_amendment2 |
| Road Log_amendment2 |