Appendix_C.pdf
PDF 518 KB Posted
- Attached to
- Johnny O'Neil Stewardship
- Solicitation number
- AG-9AC7-S-14-0131
About this file
Appendix C
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend4.pdf | ||
| Appendix_A_RevAmd4.pdf | ||
| Amend3.pdf | ||
| WD_77_Rev45.pdf | ||
| MAP_JohnnyONeil_Product_Removal.pdf | ||
| Amend2.pdf | ||
| MAP_JohnnyONeil_Service_Work.pdf | ||
| Amend1.pdf | ||
| JohnnyONeil_cruise_06042014.pdf | ||
| Map1_JohnnyONeil.pdf | ||
| Appendix_B.pdf | ||
| Map2_JohnnyONeil.pdf | ||
| AG9AC7S140131.pdf | ||
| Appendix_A.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJ NAME: Johnny O’Neil Stewardship UNIT: Klamath National Forest
AG-9AC7-S-14-0131 Appendix C PAGE 1 of 22
Appendix C
Road Maintenance
Road Maintenance T-Specifications
Applicable T-Spec. No. Specification Title
X T-800 Definitions
X T-801 Slide and Slump Repair
X T-802 Ditch Cleaning
X T-803 Surface Blading
X T-804 Surfacing Repair
T-805 Drainage Structures
X T-806 Dust Abatement
X T-807 Roadway Vegetation
T-808 Miscellaneous Structures
T-809 Waterbars
T-810 Barriers
T-811 Surface Treatment
AG-9AC7-S-14-0131 Appendix C PAGE 2 of 22
SPECIFICATION T-800 DEFINITIONS
Wherever the following terms or pronouns are used in Specifications T-801 through T-811, the intent and meaning shall be interpreted as follows:
800-1.1 - Agreement. Maintenance projects require a mutually acceptable method to resolve the problems which arise when incompatible situations arise between drawings and specifications and actual conditions on the ground to allow orderly and satisfactory progress of the maintenance.
These specifications have been developed in anticipation of those problem areas and have provided that such changes will be by Agreement.
It is intended that drawings and specifications will govern unless "on-the-ground" conditions warrant otherwise, when specifications call for "Agreement", "agreed", or "approval" such Agreement or approval shall be promptly confirmed in writing.
800-1.2 - Annual Road Maintenance Plan. A plan prepared by various users of one or several roads. The plan is an
Agreement on maintenance responsibilities to be performed for the coming year.
800-1.3 - Base Course. Material used to reinforce Subgrade or, as shown on drawings, placed on Subgrade to distribute wheel loads.
800-1.4 - Berm. Curb or dike constructed to prevent Roadway runoff water from discharging onto embankment slope.
800-1.5 - Borrow. Select Material taken from designated borrow sites.
800-1.6 - Crown, Inslope, and Outslope. The cross slope of the Traveled Way to aid in drainage and traffic maneuverability.
800-1.7 - Culverts. A conduit or passageway under a road, trail, or other obstruction. A culvert differs from a bridge in that it is usually entirely below the elevation of the Traveled Way.
800-1.8 - Drainage Dip. A dip in the Traveled Way which intercepts surface runoff and diverts the water off the Traveled
Way. A Drainage Dip does not block the movement of traffic.
800-1.9 - Drainage Structures. Manufactured structures which control the runoff of water from the Roadway including
Inslope, overside drains, aprons, flumes, downdrains, downpipes, and the like.
800-1.10 - Dust Abatement Plan. A table which lists the road, dust palliative, application rates, and estimated number of subsequent applications.
800-1.11 - Lead-off Ditches. A ditch used to transmit water from a Drainage Structure or Drainage Dip outlet to the natural drainage area.
800-1.12 - Material. Any substances specified for use in the performance of the work.
800-1.13 - Prehaul Maintenance. Road maintenance work which the Contractor determines must be accomplished to maintain the roads to a satisfactory condition commensurate with the Contractor’s use, provided Contractor’s Operations do not damage improvements or National Forest resources and hauling can be done safely. This work will be shown in the
Annual Road Maintenance Plan.
Prehaul Maintenance work the Contractor elects to perform will be in compliance with the Road Maintenance T-
Specifications.
800-1.14 - Roadbed. The portion of a road between the intersection of Subgrade and sideslopes, excluding that portion of the ditch below Subgrade.
AG-9AC7-S-14-0131 Appendix C PAGE 3 of 22
800-1.15 - Road Maintenance Plan. A table which shows applicable road maintenance specifications to be performed by
Contractor on specific roads.
800-1.16 - Roadside. A general term denoting the area adjoining the outer edge of the Roadway.
800-1.17 - Roadway. The portion of a road within the limits of excavation and embankment.
800-1.18 - Shoulder. That portion of Roadway contiguous with Traveled Way for accommodation of stopped vehicles, for emergency use, and lateral support of base and Surface Course, if any.
800-1.19 - Slide. A concentrated deposit of Materials from above or on backslope extending onto the Traveled Way or
Shoulders, whether caused by mass land movements or accumulated ravelling.
800-1.20 - Slough. Material eroded from the backslope which partially or completely blocks the ditch, but does not encroach on the Traveled Way so as to block passage of traffic.
800-1.21 - Slump. A localized portion of the Roadbed which has slipped or otherwise become lower than that of the adjacent
Roadbed and constitutes a hazard to traffic.
800-1.22 - Special Project Specifications. Specifications which detail conditions and requirements peculiar to the individual project.
800-1.23 - Subgrade. Top surface of Roadbed upon which Base Course or Surface Course is constructed. For roads without
Base Course or Surface Course, that portion of Roadbed prepared as the finished wearing surface.
800-1.24 - Surface Course. The Material placed on Base Course or Subgrade primarily to resist abrasion and the effects of climate. Surface Course may be referred to as surfacing.
800-1.25 - Surface Treatment Plan. A table which lists the roads and surface treatments to be applied.
800-1.26 - Traveled Way. That portion of Roadway, excluding Shoulders, used for the movement of vehicles.
800-1.27 - Turnouts. That portion of the Traveled Way constructed as additional width on single lane roads to allow for safe passing of vehicles.
800-1.28 - Water Source. A place designated on the Road Maintenance Map for acquiring water for road maintenance purposes.
800-1.29 - Waterbar. A dip in the Roadbed which intercepts surface runoff and diverts the water off the Roadway. A
Waterbar is not designed to be traversable by logging trucks.
AG-9AC7-S-14-0131 Appendix C PAGE 4 of 22
SPECIFICATION T-801 SLIDE AND SLUMP REPAIR
DESCRIPTION
1.1 Slide removal is the removal from Roadway and disposal of any Material, such as soil, rock, and vegetation that cannot be routinely handled by a motorgrader during Ditch Cleaning, T-802, and Surface Blading, T-803
Operations.
Slump repair is the filling of depressions or washouts in Roadway which cannot be routinely filled by a motor grader during Surface Blading, T-803 Operations.
Slide removal and Slump repair includes excavation, loading, hauling, placing, and compacting of waste or replacement Material and the development of disposal or borrow areas.
REQUIREMENTS
3.1 Slide Material, including soil, rock and vegetative matter which encroaches into the Roadway, shall be removed. The slope which generated the Slide Material shall be reshaped during the removal of the Slide Material with the excavation and loading equipment. Slide Material deposited on the fillslope and below the Traveled Way will not be removed unless needed for slope stability or to protect adjacent resources.
Surface and Base Courses shall not be excavated during Slide removal operations.
Slide Material which cannot be used for other beneficial purposes shall be disposed of at disposal sites shown on
Contract Area Map. Material placed in disposal sites will not require compaction unless compaction is shown on
Road Maintenance Plan.
3.2 When filling Slumps or washouts, Material shall be moved from agreed locations or borrow sites shown on
Contract Area Map, placed in layers, and compacted by operating the hauling and spreading equipment uniformly over the full width of each layer.
Existing aggregate surfacing shall be salvaged when practical and relaid after depressions have been filled.
Damaged aggregate base, aggregate surfacing, and bituminous pavement shall be repaired under Specification T-
804 Surfacing Repair.
The repaired areas of the Slump shall conform to the cross-section which existed prior to the Slump and shall blend with the adjacent undisturbed Traveled Way.
3.3 The maximum volume of Contractor responsibility for Slide and Slump repair is shown on Road Maintenance
Plan. Greater volumes of Slide and Slump repair not qualifying as Catastrophic Damage are Forest Service responsibility.
AG-9AC7-S-14-0131 Appendix C PAGE 5 of 22
SPECIFICATION T-802 DITCH CLEANING
1.1 Ditch cleaning is removing and disposing of all Slough Material from Roadway ditches to provide a free-draining waterway.
3.1 Ditch cleaning shall be repeated during the year as often as necessary to facilitate proper drainage.
3.2 All Slough Material or other debris which might obstruct water flow in the Roadway ditch shall be removed.
Material removed from the ditch, if suitable, may be blended into existing native road surface or Shoulder or placed in designated Berms in conjunction with Surface Blading T-803 operations.
Material removed from ditches that is not by Agreement blended into existing roads or placed in Berms shall be loaded and hauled to the disposal site shown on Contract Area Map.
3.3 Roadway backslope or Berm shall not be undercut.
AG-9AC7-S-14-0131 Appendix C PAGE 6 of 22
SPECIFICATION T-803 SURFACE BLADING
1.1 Surface blading is keeping a native or aggregate Roadbed in a condition to facilitate traffic and provide proper drainage. It includes maintaining the Crown, Inslope or Outslope of the Traveled Way, Turnouts, and Shoulder;
repairing Berms; blending approach road intersections; and cleaning bridge decks, Drainage Dips, and Lead-off
Ditches.
3.1 Surface blading shall be performed before, during, and after Contractor's use as often as necessary to facilitate traffic and proper drainage.
3.2 The surface blading shall preserve the existing cross-section. Surface irregularities shall be eliminated and the surface left in a free-draining state and to a smoothness needed to facilitate traffic. Surface Material which has been displaced to the Shoulders or Turnouts shall be returned to the Traveled Way. The blading operation shall be conducted to prevent the loss of surface Material and to provide for a thorough mixing of the Material being worked.
3.3 Water, taken from Water Sources designated on Contract Area Map, shall be applied during blading if sufficient moisture is not present to cut, mix, or compact the surface Material.
3.4 On native surfaced roads, Material generated from backslope Sloughing, and ditch cleaning may be blended with the surface Material being worked. On aggregate surfaced roads this Material shall not be blended with
Surface or Base Course Material unless agreed otherwise.
3.5 Roadway backslopes or Berms shall not be undercut, nor shall new Berms be established unless agreed otherwise.
Berms shall be repaired by placing Material, as needed to restore the Berm, to reasonably blend with existing line, grade, and cross-section.
3.6 Drainage Dips and Lead-off Ditches shall be cleaned and maintained to reasonably blend with existing line, grade, and cross-section.
3.7 Intersecting roads shall be bladed for a distance of 50 feet to assure proper blending of the two riding surfaces.
3.8 Rocks or other Material remaining on the Traveled Way after the final pass that are larger than 4 inches in diameter or are larger than the maximum size of imported surfacing shall be removed from the Traveled Way. The oversized Material shall be disposed of by sidecasting, unless shown otherwise on Contract Area Map. Sidecasting into streams, lakes, or water courses will not be permitted.
3.9 Material resulting from work under this specification shall not remain on or in structures, such as Culverts, overside drains, cattleguards, ditches, Drainage Dips, and the like.
3.10 Material resulting from work under this specification, plus any accumulated debris, shall be removed from bridge decks and the deck drains opened.
AG-9AC7-S-14-0131 Appendix C PAGE 7 of 22
SPECIFICATION T-804 SURFACING REPAIR
1.1 Surfacing repair is repairing potholes or small soft areas in the Traveled Way. It includes area preparation and furnishing and placing all necessary Materials, and other work necessary to repair the surface.
MATERIALS
2.1 Material used in the repair of soft areas on aggregate or native surfaced roads may be acquired from approved commercial sources, Forest Service Borrow areas shown on Contract Area Map, or Borrow sources agreed to. The quality and quantity of the imported Material used in the repair will be limited to that needed to provide a stable
Traveled Way for hauling and to minimize damage to the road and adjacent resources. The quantity of imported surface repair Material used in the appraisal estimate will be shown on Road Maintenance Plan. However, the magnitude of the work may vary depending on Contractor’s hauling schedule and ground conditions.
2.2 Material used in the repair of bituminous pavements may be acquired from local commercial sources. If a mixing table is required, the location shall be approved by the Forest Service. The bituminous mixture to be used by the Contractor shall be approved by the Forest Service. The Contractor’s share of the quantity of bituminous mixture used in the appraisal estimate will be shown on Road Maintenance Plan. However, Contractor's share of the work may vary depending on Contractor's hauling schedule, ground conditions, other traffic, etc.
3.1 Work under this specification shall be performed in a timely manner to reduce further deterioration of the
Traveled Way.
3.2 Soft spots on aggregate or native surfaces shall be repaired by placing the imported Surface Course on top of the soft spot. Layers of imported Material shall be placed until a firm surface is produced.
3.3 Bituminous Pavement Repairs. The areas to receive bituminous pavement repairs will be marked on the road surface by the Forest Service just prior to Contractor performing the work.
3.4 Potholes (deep patch). Surface Course and Base Course Materials shall be excavated to a depth necessary to reach firm, suitable Material. The minimum depth of excavation shall be 2 inches and the maximum depth of excavation shall be to the top of the Subgrade.
The edges of the prepared hole shall be extended to form a vertical face in unfractured asphalt surfacing. The prepared hole shall generally be circular or rectangular in shape, dry, and cleaned of all loose Material.
Prepared potholes shall be patched or barricaded immediately.
The faces of the prepared hole shall be tacked with a slow-setting emulsified asphalt.
The bituminous mixture shall be placed in layers not exceeding a compacted depth of 2 inches. Each layer shall be compacted thoroughly with hand or mechanical tampers or rollers. Compaction shall not be done with equipment wheels.
Upon completion, the compacted patch in the pothole shall be flush, with a tolerance or approximately ¼ inch to ½ inch above the level of the adjacent pavement.
AG-9AC7-S-14-0131 Appendix C PAGE 8 of 22
3.5 Skin Patches. Bituminous mixture shall be distributed uniformly with feathered edges in layers not to exceed
2 inches compacted depth. When multiple layers are ordered, joints shall be offset at least 6 inches between layers.
Each layer shall be compacted by two passes with a 7-10 ton steel roller or comparable vibratory roller.
3.6 Asphalt Berm. Damaged segments of Berm shall be removed and the exposed ends beveled at approximately
45 degrees from vertical. The Berm foundation shall be cleaned and patched as necessary. The foundation and joining surfaces shall be coated with a slow-setting emulsified asphalt. Asphalt mix shall be placed and compacted to conform with the shape and alignment of the undamaged segment.
3.7 Disposal. All Materials removed from potholes, patches, and Berms shall be disposed of at disposal sites shown on Contract Area Map.
Johnny O’Neil Stewardship Waterhole Improvement Specifications:
Clean, angular 1-1/2” aggregate shall be placed over non-woven geotextile fabric and compacted to a minimum depth of 6 inches. Rocking area shall be approximately 16 feet wide x 100 feet in length. Weed free straw bales or wattles shall be placed the full width between the edge of the rocked way and the watercourse. Stakes shall securely anchor the bales or wattles into the ground at a minimum on center spacing of 2 feet unless otherwise approved by the engineer.
AG-9AC7-S-14-0131 Appendix C PAGE 9 of 22
SPECIFICATION T-806 DUST ABATEMENT
1.1 This work shall consist of preparing Traveled Way and furnishing and applying Materials to abate dust.
MATERIALS
2.1 The roads requiring dust abatement, type of dust abatement Material to be used, the rates of application, and frequency of applications will be shown on Dust Abatement Plan. The Dust Abatement Plan may be changed by written Agreement.
2.2 Water. The locations of Water Sources are shown on Contract Area Map.
Operating Guidelines:
1. Operations are restricted to one hour after sunrise to one hour before sunset.
2. Pumping rate shall not exceed 350 gallons per minute.
3. The pumping rate shall not exceed ten percent of the stream flow.
4. Seek streams and pools where water is deep and flowing, as opposed to streams with low flow and small isolated pools.
5. Pumping shall be terminated when the tank is full. The effect of single pumping operations, or multiple pumping operations at the same location, shall not result in obvious draw-down of either upstream or downstream pools.
6. Each pumping operations shall use a fish screen. The screen face should be oriented parallel to flow for best screening performance. The screen shall be designed and used such that it can be submerged with at least one-screen-geight clearance above and below the screen.
7. Operators shall keep a log on the truck containing the following information:
a. Operator’s Name
b. Date
c. Time
d. Pump Rate
e. Filling Time
f. Screen Cleaned (Y or N)
g. Screen condition
h. Comments
Screen Construction Criteria:
1. Surface Area:
a. The total (unobstructed) surface area of the screen shall be at least 2.5 square feet, based on the upper limit of pumping of 350 gpm. Larger surface areas are recommended where debris buildup is anticipated, and where stream depth is adequate to keep the screen submerged at approximately middepth.
2. Screen Mesh:
a. Screen Mesh must be in good repair and present a sealed, positive barrier effectively preventing entry of the “design fish” into the intake. The design fish in this case is an immature (20-30mm) salmon or steelhead fry.
b. The screen mesh size shall be: round openings – maximum 3/32 inch diameter (.09 inch)
c. Square openings – maximum 3/32 inch diagonal (.09 inch)
d. Slotted openings – maximum 1/16 inch width (.07 inch)
AG-9AC7-S-14-0131 Appendix C PAGE 10 of 22
3. Screen Design:
a. Water drafting screens maybe off-the-shelf products, but they are often custom-made devices appropriate to the scale and duration of pumping operation. To keep the screen supported and correctly positioned in the water column, adjustable support legs are advised. Screen geometry can be configured either as rectangular or cylindrical, e.e. as a shallow “box-shape” or tubular.
b. The intake structure shall be designed to promote uniform velocity distribution at all external mesh surfaces. This can be accomplished with a simple internal baffle devise that distributes the flow evenly across the entire surface of the screen. In order to accomplish this, the designer needs to understand the hydraulic characteristics of these devices. There is a tendency for most of the intake water to enter the screen near the hose end, so a typical internal baffle would consist of a pipe (or manifolded set of pipes) which have variable porosity holes at predetermine spacing. We recommend starting near the hose end with approximately 5 – 10% average open area, and gradually increasing the porisity toward the length of the sceen. At a point where screen length exceeds three times the diameter of the suction hose, the baffling effect tends to diminish rapidly.
At this point the baffle porosity may approach 100%. A successful baffle system will functionally distribute flow to all areas of the screen. A poorly designed screen may result in high-velocity “hot spots”, which could lead to fish impingement on the screen face.
c. Hydraulic testing of prototype screen designs is recommended where the application is on-going and extensive.
4. Screen Structure:
a. The screen frame must be strong enough to withstand the hydraulic forces it will experience.
However, the structural frames, braces, and other elements that block the flow, change flow direction, or otherwise decrease the screen surface area should be minimized.
5. Screen Cleaning:
a. The screen shall be cleaned as often as necessary to prevent approach velocity from exceeding 0.33 feet per second. Operators should withdraw the screen and clean it after each use, or as necessary to keep screen face free of debris. Pumping should stop of screen cleaning when approximately fifteen percent or more of the screen area is occluded by debris. A suitable brush shall be on board the truck for this cleaning operation.
b. If the operator notes (1) impingement of any juvenile fissh on the screen face or (2) entrainment of any fish through the screen mesh, he/she should stop operations and notify the Department of Fish
& Game and/or NMFS hydraulic engineering staff:
National Marine Fisheries Service
Engineering Section
777 Sonoma Avenue, Suite 325
Santa Rosa, CA 95404
(707) 575-6050
2.3 Dust abatement Materials shall meet the requirements of the following subsections of Forest Service
Specifications for Construction of Roads and Bridges or attached Special Project Specifications.
Emulsified Asphalt 702
Blotter Material 703.12
Magnesium or Calcium Chloride Brine 723.01
Calcium Chloride Flake 723.02
Lignin Sulfonate 723.03
2.4 Testing of Materials. Certification and sampling of bituminous Materials lignin sulfonate, and magnesium chloride shall be in accordance with subsections 105.04 or 723.04 of Forest Service Specifications for Construction of Roads and Bridges.
AG-9AC7-S-14-0131 Appendix C PAGE 11 of 22
3.1 General. Dust abatement Materials shall be applied to the road surface as necessary to control road surface loss, provide for road user safety, and minimize damage to adjacent resources.
3.2 Compaction. When the methods listed below specify compaction, Traveled Way shall be compacted by an 8 to 10 ton pneumatic, steel-wheeled or equivalent vibrating roller making 2 passes over the full Traveled Way and
Shoulder width, unless compaction is not required on the Dust Abatement Plan.
3.3 Preparation to Dust Abatement Materials Other Than Water. The following applies to all methods of preparation:
Bituminous residue shall be scarified and pulverized to produce loosened Material not exceeding 4 inches in greatest dimension.
Traveled Way shall be bladed in accordance with T-803.
Prior to applying DO-6BA, DO-6PA, or DO-8, the top 2 inches of Traveled Way shall contain not less than 80 percent nor more than 120 percent of optimum moisture as determined by AASHTO T-99, Method C. Prior to applying other bituminous Material, Traveled Way shall have a moisture content between 1 and 3 percent.
If surface dusting prevents the bituminous Material from penetrating, a light application of water shall be applied just prior to applying the bituminous Material.
Lignin Sulfonate and magnesium chloride shall be applied when the top 1 inch of Traveled Way contains not less than 3 percent moisture, nor more than 120 percent of optimum moisture as determined by AASHTO T-99, Method C.
Moisture content will be determined in accordance with AASHTO T-217 OR T-239.
One or more of the following methods shall be used, as specified in the Dust Abatement Plan.
Method 1. Compact Traveled Way and apply the dust abatement Material.
Method 2. Develop a layer of loose Material approximately 1 inch in depth for the full width of Traveled Way.
Apply the dust abatement Material to this loose Material and compact after penetration. If traffic makes maintenance of the loose Material difficult, 1 inch of the Material may be bladed into a windrow along the
Shoulder. The specified moisture content shall be maintained in the windrow and the top 1 inch of Traveled Way.
The windrow shall be bladed to a uniform Material. When the dust abatement Material has penetrated, Traveled
Way shall be compacted.
Method 3. Blade 1 inch of Material from Traveled Way into a windrow along the Shoulder. Maintain the specified moisture content in the windrow and the top inch of Traveled Way. Apply half the dust abatement
Material. When the dust abatement Material has penetrated, the windrow shall be bladed to a uniform depth across dust abatement Traveled Way, and the remaining dust abatement Material shall be applied. Traveled Way shall be compacted.
Method 4. Develop a layer of loose Material approximately 2 inches in depth for the full width of Traveled Way.
Apply half the dust abatement Material to the loose Material. Blade the top 2 inches into a windrow along the
Shoulder. Apply the remaining dust abatement Material to Traveled Way and the Berm. Spread the Berm evenly across Traveled Way and compact.
AG-9AC7-S-14-0131 Appendix C PAGE 12 of 22
3.4 Preparation for Dust Abatement with Water. Traveled Way shall be prepared in accordance with Specification
T-803 Surface Blading when required.
3.5 Application Tolerance. Dust abatement Materials other than water shall be applied within 0.05 gallons per square yard of the rate specified.
3.6 Mixing Requirements. DO-6BA, DO-6PA, and DO-8 shall be thoroughly circulated in the distributor within 1 hour of application.
3.7 Weather Limitations. Dust abatement Materials shall not be applied when it is raining.
Bituminous Material shall be applied when the surface temperature of Traveled Way is 50 degrees Fahrenheit or higher.
Lignin sulfonate and magnesium chloride shall be applied when the atmospheric temperature is 40 degrees
Fahrenheit or higher.
3.8 Blotter Material. Blotter Material shall be spread in a sufficient quantity to prevent tire pickup.
Dust Abatement Plan
Material Type: WATER, Magneium Chloride or Approved Alternate
Frequency of application:
Abate dust to promote safe use of road and to prevent excessive loss of road material (fines). Dust abatement is required throughout the day while hauling is in progress near resedents, camping areas, or the like. Dust abatement is required as shown below when dust is present during haul:
1. Complete, thorough watering is required once per day over full traveled width of road surface when truck volume is 10 round trips per day or less. example: 1 truck makes 10 round trips, or 10 trucks make 1 round trip each.
2. Complete, thorough watering is required throughout the day over full traveled width of road surface when truck volume exceeds 10 round trips per day.
3. Dust abatement other than water must be approved by the Forest Service prior to use.
Preparation Method: Compaction not required.
Roads to be abated with
WATER, Magneium Chloride or Approved alternate
See Road Maintenance Requirements Summary Table for list of roads. All roads listed shall be abated with water, magesium chloride or approved alternate.
12.01
12.02
12.03
12.04
12.05
46N50.1
46N50.2
46N50.9
46N50.8
46N60.3
47N69.1
47N69.2
47N69.5
AG-9AC7-S-14-0131 Appendix C PAGE 13 of 22
47N69.4
47N77.01
47N77.02
47N77.07
47N77.08
47N77.09
47N77.1
12.06
12.07
12.08
12.09
12.1
12.11
12B
46N37
47N27
46N60.1
46N60B
47N63
47N64
47N65
47N66.1
47N66.2
47N66A
47N67Y
47N68
47N69A
47N69B
47N69C
47N69D
47N77.03
47N77.04
47N77.05
47N77D
47N86
47N87
AG-9AC7-S-14-0131 Appendix C PAGE 14 of 22
Road Maintenance Requirements Summary Table
Termini Prehaul During Haul Post Haul
Road From To Miles T801 T802 T803 T804 T807 T803 T806 T803
12.01 8F001 47N69D 4.63 P P P P P
12.02 47N69D 47N05Y 0.62 P P P P P P
12.03 47N05Y 12.04 0.33 P P P P P
12.04 12.03 47N66 0.5 P P P P P
12.05 47N66 47N27 0.46 P P P P P
46N50.1 8F001 47N77.01 1.46 P P P P P P
46N50.2 47N77.01 47N69.5 1.63 P P P P P P
46N50.9 8D002 46N60.3 0.63 P P P P P
46N50.8 46N60.3 47N77.1 2.68 P P P P P
46N60.3 46N50.9 46N37 5.09 P P P P P P
47N69.1 12.01 47N69C 0.5 P P P P P P
47N69.2 47N69C 47N69B 0.58 P P P P P P P
47N69.5 46N50.2 47N68 1.37 P P P P P P
47N69.4 47N68 47N69A 1.03 P P P P P P P
47N77.01 46N50.1 47N77.02 1.38 P P P P P P
47N77.02 47N77.01 47N77.03 1.14 P P P P P
47N77.07 47N77D UNIT 424 2.47 P P P P P
47N77.08 47N87 47N77D 0.61 P P P P P
47N77.09 47N77.1 47N87 1.16 P P P P P
47N77.1 46N50.8 47N77.09 0.45 P P P P P
12.06 47N27 47N65 0.19 P P P P P
12.07 47N65 47N64 1.31 P P P P P
12.08 47N64 12B 0.58 P P P P P
12.09 12B 47N86 0.28 P P P P P
12.1 47N86 47N63 0.66 P P P P P
12.11 47N63 UNIT 481 0.13 P P P P P
12B 12.08 UNIT 465 0.34 P P P P P P
46N37 46N60.3 UNIT 429 1.34 P P P P P P
47N27 12.05 UNIT 462 0.15 P P P P P
46N60.1 8F001 46N60B 5.76 P P P P P P
46N60B 46N60.1 UNIT 502 1.87 P P P P P P
47N63 12.1 UNIT 482 0.38 P P P P P
47N64 12.07 UNIT 473 0.42 P P P P P
47N65 12.06 UNIT 469 1.18 P P P P P P
47N66.1 12.04 47N66A 0.73 P P P P P P
47N66.2 47N66A UNIT 500 0.11 P P P P P P
47N66A 47N66.1 UNIT 461 0.37 P P P P P P
47N67Y 12.1 UNIT 479 0.68 P P P P P P
47N68 47N69.5 UNIT 453 0.68 P P P P P P
47N69A 47N69.4 UNIT 442 0.33 P P P P P
47N69B 47N69.2 UNIT 453 1.14 P P P P P
47N69C 47N69.1 UNIT 447 0.46 P P P P P
47N69D 12.01 UNIT 449 0.58 P P P P P
47N77.03 47N77.02 47N77.04 1.65 P P P P P
47N77.04 47N77.03 47N77.05 0.28 P P P P P
AG-9AC7-S-14-0131 Appendix C PAGE 15 of 22
Termini Prehaul During Haul Post Haul
Road From To Miles T801 T802 T803 T804 T807 T803 T806 T803
47N77.05 47N77.04 UNIT 421 1.43 P P P P P
47N77D 47N77.08 UNIT 509 0.97 P P P P P P
47N86 12.09 UNIT 479 0.46 P P P P P
47N87 47N77.09 UNIT 434 0.77 P P P P P
AG-9AC7-S-14-0131 Appendix C PAGE 16 of 22
SPECIFICATION T-807 ROADWAY VEGETATION
1.1 This work includes removal of brush and trees from within the Roadway limits.
3.1 Vegetative matter within the Roadway which impedes vehicular travel or interferes with road maintenance operations, such as surface blading and ditch and culvert cleaning shall be removed. Downed timber meeting utilization standards shall be cut in appropriate lengths and decked along the Roadside in locations where the
Traveled Way or sight distances will not be impaired.
3.2 Vegetative matter removed from the Roadway shall be treated by the specified method shown on Contract
Area Map and as required by in Appendix A and or K-G.7#.
AG-9AC7-S-14-0131 Appendix C PAGE 17 of 22
WET WEATHER OPERATION STANDARDS
(05/16/02)
Project Clause - Use of Roads by Contractor, states in part "...Contractor is authorized to use existing National
Forest roads...when such use will not cause damage to the roads or National Forest resources and when hauling can be done safely." Clause titled Operating Schedule and Erosion Prevention and Control state in part Contractor’s operations may be conducted outside Normal Operating Season (October 16 through May 14, inclusive).
Logging operations may be conducted outside the Normal Operating Season (NOS), however, certain requirements must be met in order to have operations proceed during this period. Compliance with pertinent Best Management
Practices (BMPs) by the Contractor is necessary to meet water quality requirements as agreed to between the State of California and the US Forest Service. The following standards are intended to further clarify Project requirements by providing specific criteria for conducting sale operations during wet weather conditions and to facilitate consistent implementation across the Klamath National Forest.
The following guidelines are to be used to determine if conditions are favorable for wet weather/winter operations and to provide guidance as to when conditions warrant suspension of operations, when operations may begin or resume, or when and what remedies may be appropriate. These guidelines also apply within the Normal Operating
Season (NOS—May 15 through October 15) when prolonged periods of wet weather are encountered. These standards were developed to protect water quality. Protection measures for other resources and facilities, such soils and transportation system, are addressed in the Project and other Forest Service standards and guides.
A. General Guidelines:
* Operations will be continually monitored by the Contractor and the Forest Service, including: sale administration personnel, Contractor representatives, and resource specialists. Conditions may change as operations progress during the wet season. If detrimental effects to the transportation system, water quality, or soil resources are encountered by either party, immediate notification of designated sale administrative personnel by either the
Contractor or Forest Service shall occur. The Contractor and Forest Service will work together to develop actions necessary to alleviate these effects.
* BMP guidelines dictate that no sediment/contaminant flow into stream courses from any facility used by the
Contractor, including B. Roads, C. Skid Trails, Cableways, or Harvest Areas, D. Landings, and E. Fueling
Locations, will be permitted at any time. BMP measurable thresholds, listed in paragraph “2)” under the major headings below (BMP indicators that operations should be curtailed and/or corrective actions implemented), warn the Contractor and the Forest Service that BMP violations are possible if action is not taken. Expression of any of these BMP indicators does not necessarily indicate BMP violation(s) and degradation of water quality has occurred.
B. Roads:
General - Hauling/Access Use:
* Required road work for prehaul must be accomplished prior to the wet season or periods of precipitation.
Saturated road surfaces should not be graded. At least 2" of snow should remain on the road surface after snow plowing. Road surfaces must be at a standard and maintenance level that will support the impacts of wet weather operations. This includes the following:
1) Actions that augment BMP compliance:
Wet Conditions
AG-9AC7-S-14-0131 Appendix C PAGE 18 of 22
* Drainage structures and erosion/sediment prevention actions will be in place and functioning prior to expected precipitation events.
* Roads will be properly graded and ditched or outsloped.
* Portions of roads that lie within Streamside Management Zones (SMZs) and road locations where eroded material is likely to enter channels will be rocked to Forest Service specifications and geotextile fabric used when appropriate, unless otherwise agreed, with input from a resource specialist and an engineer.
* Operations will be scheduled to use roads in order to avoid the risk of rutting during "precipitation events."
* By agreement, use of the variable tire pressure option can be used to reduce surface replacement and will reduce Contractor road maintenance costs.
Snow Conditions
* Snow will be removed without disturbing the road surface, cut bank, fill slope, or drainage structures. No soil or aggregate should be intermixed with the sidecast snow during plowing or grading. At least 2" of snow should remain on the road surface after snow plowing.
* Snow berms must be breached, except in sensitive areas, to allow proper road drainage. These outlets must be spaced so as not to concentrate road surface flows (usually spaced no more than 200 feet apart). Erosion control structures (straw bales or filter fence) may be required at the outlets to collect road generated sediment.
Frozen Conditions
* If the road surface freezes, the road surface segments must remain completely frozen and must be able to support the weight of any vehicle that will be driven on it. If the road thaws, see below...
* When any part of the active road length thaws and mitigations, such as rocking, cannot be implemented to ensure water quality protection, the road will not be used. This will preclude the use of the road by all vehicles (including administrative) unless the activity can be restricted to that portion of the road that remains frozen.
2) BMP indicators that operations should be curtailed and/or corrective action implemented:
CULVERTS:
[1] Sediment and/or debris is blocking 30% of inlet or outlet.
[2] More than 10% of the flow passes beneath or around culvert, or noticeable piping erosion evident, unless crossing is designed to do so (e.g., coarse material rock fill)
EROSION:
[3] Scour and/or sediment deposition evident, and extending more than 20 feet below outlet of cross drain or other drainage structure (e.g., culvert, rolling dip, waterbar).
[4] Scour &/or sediment movement into SMZ or drainageway from road surface, cut slope, or fill slope.
AG-9AC7-S-14-0131 Appendix C PAGE 19 of 22
[5] Material sidecast within 25 feet of a channel, ditch or drainageway, or onto slopes vegetated for erosion control.
PONDING:
[6] Ponding present on road surface that is causing fill subsidence or otherwise threatening integrity of fill.
RUTS/RILLS:
[7] More than 10% of road segment length has rills or ruts more than 2 inches deep and 20 feet in length which continue off road surface, with potential to deliver sediment to stream channel.
[8] Ruts formed that can channel water past erosion control structures.
[9] Numerous rills present at stream crossing (>1 rill per lineal 5 ft), apparently active or enlarging, evidence of some sediment delivery to stream.
3) Operating Requirements & Remedies:
* If more than 10 percent of the road segment length is rutted 2 inches in depth or greater, Contractors use of the road will be suspended. (Percentage will be determined in one mile increments if road is longer than one mile). If the road is to remain closed, it must have a barrier of some type installed to keep out all vehicular traffic and signed to keep traffic off road surface.
* If the roadway dries and can support vehicles without causing rutting, soil displacement, damage to drainage structures, and with no off-site sediment movement, it can be used. If not, it should remain unused.
* Roads damaged by Contractor's Operations and associated damage will be repaired at the Contractor's expense. A remedy plan will be prepared and implemented. Repair work shall be accomplished immediately when conditions are such that additional damage to the resources will not occur or when designated by the Forest Service.
Native Surfaced Roads and Other Roads Identified for Special Hauling Requirements
* The native surfaced roads and other roads listed below are located in sensitive soils that are prone to road surface damage during wet weather use. There shall be no log hauling on these roads during precipitation events. The timber sale operator shall allow an adequate drying period after a rain occurrence prior to resumption of hauling (normally 1 day depending on soil type and/or as determined by Contractor and Forest
Service Rep.).
Road Number Termini - Termini
N/A
Rocking Roads
* Locations where road rocking is required to harden the road surface for wet weather haul will be designated in writing and flagged on-the-ground by the Engineering Rep. or Sale Administrator. Minimum depth of rock that meets engineering specifications will be established in writing and inspected by the Forest
Service prior to use of the road for hauling outside the NOS.
AG-9AC7-S-14-0131 Appendix C PAGE 20 of 22
C. Skid Trails/Cableways/Harvest Areas:
Skid trails will be flagged by the Contractor and approved by the Forest Service in advance of falling.
General
* No more than 15% of the activity area (includes temporary roads, landings, skid trails, and cableways
[cable corridors]) should be subjected to detrimental ground-disturbing activities. Ground-disturbing activities produce adverse changes in soil porosity (compaction), soil cover, and soil organic matter.
Snow/Frozen Conditions
* Snow can act as a cushion to to protect wet soils. Unless otherwise agreed, within the operating area, a minimum of 6 inches of machine compacted snow with a minimum water content of 2 inches is required for over-the-snow logging or the soil should be frozen to a depth of 6 inches for logging operations to occur
(frozen soil occurs primarily on the Goosenest District). When the snow depth approaches this minimum, snow conditions must be monitored on a daily basis to verify snow depth is sufficient to start or continue operations. Approval to operate on snow less than indicated above must include an evaluation by a soil scientist or hydrologist. At least 90% of the skidding surfaces must meet the above snow cover standard at all times. If snow cover falls below 90%, see section 2) below for "bare ground" standards.
Wet Conditions
Skyline - No Specified pre-conditions.
Cut-to-Length System - Processing of material on the designated skid trails by a harvester may occur when soils are dry to a depth of 4 inches. Limit harvester to 1 or 2 passes over the same piece of ground. The forwarder will stay on designated skid trails covered with a minimum of 6 inches of slash.
Feller/Buncher System - Movement of material to the designated skid trails by a track laying feller/buncher may occur when soils are dry to a depth 4 inches. Feller/buncher will be limited to 1 or 2 passes over the same piece of ground. Skidding equipment will stay on designated skid trails until soils are dry to a depth of 10 inches.
Traditional Tractor Logging - Skidding may occur by conventional high-ground-pressure equipment when soils are dry to a depth of 4 inches. Equipment is restricted to the designated skid trails. Endlining will be used to move material to the designated skid trails until soils are dry to a depth of 10 inches. Equipment may, by agreement, leave designated skid trails when soils are dry to a depth of 10 inches.
2) BMP indicators that operations should be curtailed and/or corrective actions implemented:
[10] More than 20% of skid trail or cableway surface lengths have rills present that are over 2 inches deep and more than 10 feet in length.
[11] More than 10% of skid trail surface length has ruts greater than 2 inches deep.
AG-9AC7-S-14-0131 Appendix C PAGE 21 of 22
[12] Rills and/or sediment deposition extends more than 20 feet below waterbar outlet.
[13] More than 10% of waterbars fail to divert flow off skid trails or cableways.
[14] Erosion within or sediment movement into SMZ.
[15] Presence of gullies (erosional features greater than 4" deep and 6" wide).
* Skid trails, cableways and harvest areas damaged by Contractor's Operations and associated damage will be repaired at the Contractor's expense. A remedy plan will be prepared and implemented. Repair work shall be accomplished immediately when conditions are such that additional damage to the resources will not occur or when designated by the Forest Service. See the Wet Weather Operation Field Guide for a list of potential remedies.
D. Landings:
Landings will be agreed to by Contractor and designated sale administrative personnel prior to their construction and/or use. Landings will not be located within SMZs or Riparian Reserves unless a resource specialist (hydrologist, geologist, fisheries biologist) is consulted.
* Landings will be constructed to ensure proper drainage, compaction and stability. Landings will be monitored to ensure that drainage is effective. For example, landings will not create a depression which cannot be properly drained; upslope runoff will be diverted, to an appropriate location, around the activity.
* If rocking is required for wet weather operations, landings should be rocked before the surface becomes saturated.
* Landings should be identified well in advance of logging activities. This would allow construction be complete within the NOS. But if unavoidable and as a preventative measure, all landing fill slopes constructed outside of the Normal Operating Period should be mulched. Mulch material can consist of wood chips, certified weed-free straw, or any other Forest Service approved material which will provide slope protection against erosion and rilling. In addition, downslope perimeter erosion control will be required if a potential threat to water quality exists as determined by an earth scientist.
* The use of a heel boom loader may be required to minimize landing size and reduce excavation of the site.
2) BMP indicators that operations should be curtailed and/or corrective actions implemented:
[16] Rills (greater than 1/2" deep and 10' in length) and/or sediment deposition has extended more than 20 feet below the toe of the landing fill slope.
[17] More than 1 cubic yard of material (from erosion or slope failure) has moved into SMZ.
AG-9AC7-S-14-0131 Appendix C PAGE 22 of 22
* Landings damaged by Contractor's Operations and associated damage will be repaired at the Contractor's expense. Repair work shall be accomplished immediately when conditions are such that additional damage to the resources will not occur or when designated by the Forest Service.
E. Fueling Sites:
1) Action that augment BMP compliance:
* Contractor shall take additional appropriate measures documented in a wet weather fuel storage plan to prevent any oil or oil product spill from entering any stream or drainageway.
2) BMP indicators that operations should be curtailed and/or corrective measures implemented:
[18] Evidence of more than 10 gallons of fuel or oil products outside bermed containment area.
* Fueling sites damaged by Contractor's Operations and associated damage will be repaired at the
Contractor's expense. Repair work shall be accomplished immediately when conditions are such that additional damage to the resources will not occur or when designated by the Forest Service.
Forest Service retains the authority to suspend any or all of Contractor's operations as needed to protect resources.