AG-9AB5-S-17-0045_Solicitation.pdf
PDF 354 KB Posted
- Attached to
- 2017 Forest Wide Roof Repair and Replacement
- Solicitation number
- AG-9AB5-S-17-0045
About this file
Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PPQ.docx | DOCX document | |
| Fire_Plan.pdf | ||
| Project_Experience_Questionnaire.docx | DOCX document | |
| DBA.pdf | ||
| SPECIFICATIONS.pdf | ||
| VICINITY_MAP.pdf | ||
| DRAWINGS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
849859
USDA FOREST SERVICE
R5 SO-CAL ACQ SERVICE AREA SCASA
701 N SANTA ANITA AVE
ARCADIA CA 91006
9AB5
Vincent Chua
701 N Santa Anita Ave.
Arcadia, CA 91006
VINCENT CHUA 626-574-5326
1x 04/21/2017
AG-9AB5-S-17-0045
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
2017 Forest-Wide Roof Repair and Replacement
The purpose and intent of this solicitation is for removing existing roofing systems, disposing and recycling of the removed material, installing new roofing system or making repairs to damaged sections at various locations on the Angeles
National Forest (ANF), following 2016-2017 Winter storms.
Upon award of the Contract, the Contractor shall provide labor, materials, equipment, supervision, and incidentals necessary to perform the work specified in this Statement of Work.
Pursuant to 40 U.S.C 3132 and FAR Part 52.228-13,a payment bond shall be required if the construction award exceeds $35,000. The bond must be from an approved source.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 75 calendar days and complete it within ________________ ________________ calendar days after receiving
05/22/2017
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA FOREST SERVICE
R5 SO-CAL ACQ SERVICE AREA SCASA
701 N SANTA ANITA AVE
ARCADIA CA 91006
9AB5
VINCENT CHUA
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 45
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
AG-9AB5-S-17-0045
FOB: Destination
Period of Performance: 08/01/2017 to 11/17/2017
001 2017 Forest-Wide Roof Repair and Replacement
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
AG-9AB5-S-17-0045 Page 4 of 45
QUOTER COVER SHEET/CHECKLIST
This requirement is being procured under Part 13, Simplified Acquisition Procedures.
QUOTATIONS ARE TO BE RECEIVED BY THE DUE DATE AND TIME.
NO PAPER DOCUMENTS OVER 8 ½ X 11, AND NO BROCHURES ARE TO BE SUBMITTED AS PART OF YOUR
QUOTE.
OFFERORS ARE TO RETURN to the address in Block 5a of the SF 1442:
1. Completed SF 1442
2. Completed Part 1- The Schedule (Pricing)
3. Addressed Evaluation Factors
4. This page with the following questions answered:
HAVE YOU OBTAINED A DUNS NUMBER?____________________________________
WHAT IS YOUR DUNS NUMBER?_____________________________________________
ARE YOU REGISTERED IN SAM?
Have you completed your annual recertification requirements?________ https://www.sam.gov/portal/public/SAM/
There is no fee to register on the official government web site.
Is your banking information correct and current in SAM?___________________
NOTE: Failure to obtain a DUNS number and register in SAM by the quotation due date will result in the quoter being ineligible for award of a contract. Quoters are encouraged to promptly obtain a DUNS number and register in SAM now, if submitting a quotation to this solicitation.
HAVE YOU READ THE STATEMENT OF WORK AND ADDRESSED ALL OF THE SUBMITTAL
INFORMATION AND EVALUATION INFORMATION?____________
ACKNOWLEDGE AMENDMENTS (See amendments for proper acknowledgement)
AG-9AB5-S-17-0045 Page 5 of 45
SECTION A - Solicitation/Contract Form
NOTICE TO CONTRACTOR – Superintendent Requirement
The Government will hold the Contractor in strict compliance of 52.236-6, Superintendence by the Contractor, contained herein Section A. After issuance of the award and prior to issuance of the Notice to Proceed, the Contractor shall submit to the Government the name and qualifications of the Superintendent on the Contractor’s official letterhead. The Superintendent shall be a current employee on the Contractor’s payroll; or the Contractor shall hire the Superintendent with the intent of the Contractor issuing an IRS form 1099-Misc. The Superintendent shall not be an employee of the Subcontractor that is hired by the Contractor to perform the work. The Contractor shall incorporate this cost into the proposal prior to submitting it to the Government. Failure of the Contractor to comply with this requirement will be subject to termination.
NOTICE TO CONTRACTOR – Construction Schedule
The Contractor shall submit to the Government a construction schedule which clearly identifies the Critical Path Method (CPM) and the percentage of work completed. The Contractor may use any industry software or published document that will incorporate these elements into the schedule. The Contractor shall submit the construction schedule in strict compliance with 52.236-15, Schedules for Construction Contracts, contained herein Section A.
Commencement, Prosecution, and Completion of Work. (APR 1984) 52.211-10
The Contractor shall be required to (a) commence work under this contract within 10 ten calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than sixty (60) calendar days. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.222-27
Payments under Fixed-Price Construction Contracts. (MAY 2014) 52.232-5
Performance of Work by the Contractor. (APR 1984) 52.236-1
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 100% of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
(End of Clause)
Differing Site Conditions. (APR 1984) 52.236-2
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of -
(1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract;
or
(2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
AG-9AB5-S-17-0045 Page 6 of 45
(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) of this clause for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
(End of Clause)
Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-3
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
(End of Clause)
Superintendence by the Contractor. (APR 1984) 52.236-6
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
(End of Clause)
Schedules for Construction Contracts. (APR 1984) 52.236-15
(a) The Contractor shall, within three (3) days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained. (c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by
AG-9AB5-S-17-0045 Page 7 of 45 the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
(End of Clause)
Layout of Work. (APR 1984) 52.236-17
The Contractor shall lay out its work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through its negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(End of Clause)
Default (Fixed-Price Construction). (APR 1984) 52.249-10
(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time,whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.
(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if -
(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include -
(i) Acts of God or of the public enemy,
(ii) Acts of the Government in either its sovereign or contractual capacity,
(iii) Acts of another Contractor in the performance of a contract with the Government,
(iv) Fires,
(v) Floods,
(vi) Epidemics,
(vii) Quarantine restrictions,
(viii) Strikes,
(ix) Freight embargoes,
(x) Unusually severe weather, or
(xi) Delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and
(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended. The findings of the Contracting Officer shall be final and conclusive on the parties, but subject to appeal under the Disputes clause. c) If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, AG-9AB5-S-17-0045 Page 8 of 45 or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.
(d) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.
(End of Clause)
Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999) 52.222-23
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade: 5%
Goals for Female Participation for Each Trade: 5%
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on
(1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4.
Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S.
Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the -
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is San Bernardino National Forest, San Bernardino County.
(End of Clause)
AG-9AB5-S-17-0045 Page 9 of 45
SECTION B - Supplies or Services and Prices/Costs
SCHEDULE OF ITEMS
BIDDERS PLEASE NOTE: Before preparing proposal, carefully read the contents of this solicitation.
Bidders are further cautioned to inspect the construction site and investigate transportation, weather, and local labor conditions.
2017 Forest Wide Roof Repair and Replacement, Angeles National Forest
ITEM ESTD. UNIT
NO. DESCRIPTION QUANT. UNIT PRICE AMOUNT
BASE BID ITEMS
1 Site 1: Big T Engine Garage - Replacement of Existing Roof 1 LSQ Replace with new rolled composition roofing 2 Site 2: Valyermo Barracks - Replacement of Existing Roof 1 LSQ Replace with new composition shingles roofing 3 Site 3: Acton DO Bldg - Repair Roof/Wall Leak 1 LSQ 4 Site 4: Mt Baldy VC - Repair Roof Leak 1 LSQ 5 Site 5: Crystal Lake CG Restroom - Replacement of Existing Roof 1 LSQ Replace with new cedar shake roofing 6 Site 6: Arcadia SO Bldg - Repair Roof Leak 1 LSQ
7 Facia Removal and Replacement 180 LF 8 Roof Decking Removal and Replacement 750 SF 9 Gutter and Downspout Removal and Replacement 250 LF
TOTAL
OPTION ITEMS
10 Site 1: Alternative - use built-up roofing material 1 LSQ 11 Site 5: Alternative - use standing seam metal roofing material 1 LSQ
TOTAL
NOTE: Any award will be to one bidder. Bids on all items and sub-items are for processing payments. If bids are not submitted on all items and sub-items, bid may be considered non-responsive.
SECTION C - Description/Specifications/Statement of Work
Forest Service Specifications for 2017 Forest Wide Roof Repair and Replacement, Angeles National Forest
C.1 SCOPE
The purpose and intent of this requirement is for removing existing roofing systems, disposing and recycling of the removed material, installing new roofing system or making repairs to damaged sections at various locations on the Angeles National Forest (ANF), following 2016-2017 Winter storms.
The Contractor shall provide labor, materials, equipment, supervision, and incidentals necessary to perform the work specified in this Statement of Work.
The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract. The Contractor shall verify all quantities, dimensions and description of the work visually in the field
AG-9AB5-S-17-0045 Page 10 of 45 and inform the ANF of any deviations in the contract documents.
C.2 PROJECT DESCRIPTION
This project includes removing existing roofing materials, including shingles, built-up roofing system, roofing underlayment, drip edges, gutters and down spouts, flashing and where necessary decking material. At repair locations, the Contractor shall make necessary repairs to mitigate water leaks as needed. At replacement locations, the Contractor shall install new underlayment, flashing, drip edges, gutters and down spouts, shingles, modified bitumen, polymeric base shake, ridge venting and where necessary new decking material. All new roof installations shall include demolition and disposal of damaged material (to be replaced), repair work, joint sealants and new materials for a complete water tight roof system as shown on the sketches and as noted in the specifications. All protruding nails and screws shall be removed prior to installation of new roof.
With all roofing material removed, the Contractor shall assess the condition of the existing decking, rafters, joists and connections and report to the Contracting Officer’s Representative any deficiencies to the structural integrity of the roof exceeding 10% of the total area. Payment for removal and replacement of decking will be made per square foot (not to exceed 10% of the total area) at the unit price provided in the Schedule of Items. Payment for removal and replacement of fascia shall be made per linear foot at the unit price provided in the Schedule of Items. Gutters and downspouts may require removal and replacement as to facilitate the roofing operation. Payment for removal and replacement of gutters and downspouts shall be made per linear foot at the unit price provided in the Schedule of Items. Where fascia and exposed decking are replaced, the material shall be painted with a primer and finish coat with a color to match existing prior to installation. All buildings are accessible for loading roofing materials with mechanical equipment. The warranty period shall be a minimum of 15 years or as specified in the specifications by material.
The locations and brief description are as follows:
Site Location Description 1 Big Tujunga
Station Engine Garage (FS Bldg #1517)
Replacement of existing flat roof (approximately 34’-0” x 62’-4”) made up of 4-ft rolled composition gravel, including underlayment and structural elements that have major deterioration; New roof replacement shall be rolled composition roofing or built-up roofing (Option Item).
2 Valyermo Station Barracks Building (FS Bldg#1324)
Replacement of existing roofing (approximately 60’-0” x 32’-0”) with a pitch of 9:12, including three porches (approximately 7’-0” x 18’-0”; Existing roof is made up of asphalt shingles; New roof replacement shall be in-kind with new composition shingles roofing and new underlayment.
3 Acton District Office (DO) Building (FS Bldg #2019)
Roof leak at existing interaction of pitched section with concrete wall, AS SHOWN ON THE DRAWINGS; Metal roofing shall be exposed to determine location of water leak; Repair as needed and test repair with water pressure to ensure mitigation is completed.
4 Mt Baldy Visitor Center (VIS) Building (FS Bldg
#A2009VC)
Roof leak at existing flat roof location, AS SHOWN ON THE DRAWINGS; Asphalt roofing shall be exposed to determine location of water leak; Repair as needed and test repair with water pressure to ensure mitigation is completed.
5 Crystal Lake CG Restroom Building (FS Bldg #A2001R4)
Replacement of existing pitched roof (approximately 37’-6” x 28’- 6”) with a pitch of 9:12; Existing roof is made up of cedar shake shingles; New roof replacement shall be in-kind with new cedar shake roofing and new underlayment or standing seam metal roofing (Option Item).
6 Arcadia Supervisor’s Office (SO)
Roof leak at existing valley of pitched roof, AS SHOWN ON THE DRAWINGS; Metal roofing shall be exposed to determine location of water leak; Repair as needed and test repair with water pressure
AG-9AB5-S-17-0045 Page 11 of 45
Building (FS Bldg #2038) to ensure mitigation is completed.
A job walk will not be provided for this project. Contractors are encouraged to visit the sites on their own during normal business hours (non-holidays, Monday – Friday 8 a.m. to 4:30 p.m.). Forest Service personnel at the sites will be notified that contractors may be inspecting the proposed work. When Forest Service personnel are available at the site, please check in with them to announce your visit.
C.3 LOCATIONS & DIRECTIONS
A vicinity map is provided to locate the project sites. Each of the sites are listed with approximate directions from one or two locations.
Site Location Directions 1 Big Tujunga Station
Engine Garage From Pasadena: Take the I-210 towards San Fernando. Exit on Sunland Blvd and make a right. Make a left on Oro Vista Ave.
and drive north. Continue northeast on Big Tujunga Canyon Road for approximately 8 miles. Make a right on Stonyvale Road and follow the signs to the fire station.
2 Valyermo Station Barracks Building
From I-15 on the east: Take CA-138 exit and turn west toward Wrightwood and Palmdale. Continue on CA-138 and turn left onto 165th Street. Continue straight on 165th Street to go onto Bobs Gap Road. Turn right onto Valyermo Road and continue to the station.
From CA-14 on the west: Take the Angeles Forest Highway exit, Exit 30, toward Pearblossom Hwy. Turn onto Sierra Hwy and continue straight onto Pearblossom Hwy. Make a slight right turn at the junction of CA-138. Continue to 82nd Street East and turn right. Continue on 82nd Street East and turn left onto Fort Tejon Road. Turn left onto Pallet Creek road and then right onto Valyermo Road and continue to the station.
3 Acton District Office (DO) Building
The Acton District Office, formally known as the Santa Clara/ Mojave Rivers Ranger District Office (SCMRRD) is located at 33708 Crown Valley Road, Acton CA 93510; Telephone: (661) 269-2808.
From CA-14, take the Crown Valley Road Exit and proceed north past the intersection with Sierra Highway about 430 feet. The visitor’s parking lot is located on the right.
4 Mt Baldy Visitor Center (VIS) Building
From Arcadia, CA: Take the I-210 East from Arcadia and follow the I-210 and CA-210 to Claremont for approximately 19 miles.
Take the Base Line Road exit from CA-210, make a left turn.
Following the freeway over-ramp, turn right on Padua Ave. and travel for approximately 1.7 miles. Turn right on Mt Baldy Road and drive for approximately 7.3 miles. Arrive at Mt Baldy Visitor Center (on the left). Approximate address: 6778 Mt Baldy Road, Mount Baldy, CA 91759; Telephone: (909) 982-2829
5 Crystal Lake CG Restroom Building
From Arcadia, CA: Take the I-210 Freeway East and exit on the Azusa Ave. off ramp, Hwy 39. Proceed north on Highway 39 for approximately 20 miles to the Crystal Lake Campground turnoff.
The restroom is located past the Crystal Lake Café. At Loop I, the restroom is located near Campsite #199. A map of the
AG-9AB5-S-17-0045 Page 12 of 45 campground will be provided upon award.
6 Arcadia
Supervisor’s Office (SO) Building
The Supervisor’s Office building is located on the ANF Headquarters compound. The Compound is located at 701 N Santa Anita Ave, Arcadia, CA 91006; Telephone: (626)574-1613.
From I-210, take the Santa Anita Avenue Exit and proceed south about 100 feet. The compound is located in the south west corner of the intersection of I-210 and Santa Anita Avenue.
C.3 CONTRACT DOCUMENTS
Reference Drawings, Specifications, Schedule of Items, Fire Plan, Vicinity Map, and this Statement of Work. The contractor shall comply with the C.S.I. specifications listed in this contract.
C.4 ANTICIPATED START DATE : August, 2017
C.5 CONTRACT TIME: 75 Calendar Days
SECTION D - Packaging and Marking Payment of Postage and Fees
All postage and fees related to submitting information including submittals, forms, reports, etc., to the Contracting Officer or the Contracting Specialist shall be paid by the Contractor.
Correspondence/Submittals
Contractor initiated correspondence and submittals shall identify the contract number. All information shall be forwarded to the addresses found in Section G. Correspondence shall be provided in duplicate and mailed to the Contracting Officer (CO). This would include the Submittal Register and Construction Schedule/Reports. Submittals shall be submitted to the Contracting Officer Representative (COR) with a duplicate copy of the cover letter forwarded to the CO.
AG-9AB5-S-17-0045 Page 13 of 45
SECTION E - Inspection and Acceptance
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
52.246-1 Contractor Inspection Requirements. (APR 1984)
52.246-12 Inspection of Construction. (APR 1996)
52.236-5 Material and Workmanship. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.246-12 Inspection of Construction. (APR 1996)
(a) Definition. Work includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may -http://www.arnet.gov/far/ http://www.usda.gov/procurement/policy/agar.html
AG-9AB5-S-17-0045 Page 14 of 45
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
52.246-21 Warranty of Construction. (MAR 1994)
Pre-Final Inspection
The Contractor shall give written notice to the Contracting Officer at least 15 calendar days before the date the construction work will be completed and ready for final inspection. The contractor shall conduct a pre-final and final inspection in the presence of the Contracting Officer’s Representative (COR). Other Government personnel may attend both inspections. A Government Pre- Final Punch List may be developed as result of this inspection of any items not meeting Contract requirements for final acceptance. The list of deficiencies may include the estimated date by which the deficiencies will be corrected. Any discrepancies noted shall be corrected prior to final inspection. The Government reserves the right to request a pre-final Inspection or final inspection.
Final Inspection
(a) The Contracting Officer shall be notified in writing by the Contractor when the final inspection can be conducted. The final inspection shall be requested ten (10) calendar days before the desired date or required completion date of the contract.
(b) The final inspection shall be performed with the Contractor by the Contracting Officer's Representative and/or representatives of the using activity. The Contractor and/or the Project Supervisor shall be present at the job site during final inspection. The Contracting Officer will present to the Contractor, after inspection, a punch list of any items not meeting Contract requirements for final acceptance. This list will be confirmed in writing, and any items therein must be made acceptable before final payment will be made. Any discrepancies noted shall be corrected within the time specified in the contract for final completion. Only the Contracting Officer is authorized to accept work performed.
Inspection
(a) The Contracting Officer or the duly authorized representative will perform inspection of materials and services to be provided.
(b) For the purpose of this clause, Ricardo Lopez is the authorized representative of the Contracting Officer.
(c) Inspections will be performed at the construction site.
SECTION F - Deliveries or Performance
AG-9AB5-S-17-0045 Page 15 of 45
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 calendar days after Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
52.242-14 Suspension of Work. (APR 1984)
Contract Work Hours
The performance period established for this contract is based upon all work being conducted during regular working hours.
Regular working hours are limited to the time between 7:30am to 4:00pm, Monday through Friday, excluding Government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and Government holidays, a request must be submitted to the Contracting Officer Representative in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
(End of Clause)
SECTION G - Contract Administration Data
1. CONTRACT REPRESENTATIVE
Contracting Officer (CO) responsible for this contract: Vincent Chua USDA Forest Service 701 N. Santa Anita Ave.
Arcadia, CA 91006 Telephone Number: 626-574-5326 Email: vchua@fs.fed.us
Contracting Officer's Representative (COR) for this contract: Ricardo Lopez USDA Forest Service 701 N. Santa Anita Ave.
Arcadia, CA 91006 Telephone Number: 626-574-5295 Email: rlopez@fs.fed.us
2. CONTRACTING OFFICER'S REPRESENTATIVE – LIAISON
The COR will act as a liaison between the U.S. Forest Service herein referred to as "Service" and the Contractor, and, when necessary, will provide technical direction to the Contractor. The COR, however, is not authorized to change any of the terms and conditions of the contract, issue new assignments of work, make decisions concerning disputes arising under the contract, or resolve differing site condition matters. Neither the presence nor absence of a government representative shall relieve the Contractor of its responsibilities under the contract.
3. JOB SITE ADMINISTRATION
The Government will designate a Construction Inspector (CI) (if applicable) who will be available at the site to inspect the work as it progresses. The CI will prepare an Inspector's Daily Log, beginning with the first day of the contract, detailing ground and weather conditions, work being performed, materials delivered, and notes of any problems or difficulties. Government inspections do not relieve the Contractor of responsibility for providing adequate quality control measures. At the end of every day of work on this contract, the Contractor's Superintendent, as defined below, shall contact the CI, review the daily log, and sign as the Contractor's representative. Unless the Contractor's Superintendent makes notations to the contrary on the daily log, the log shall be presumed to be accurate. The CI is not authorized to make technical decisions or give technical directions; the Contractor or the Contractor's Superintendent must contact the COR regarding such decisions and directions. The Contractor shall have a
AG-9AB5-S-17-0045 Page 16 of 45 competent superintendent (hereinafter referred to as the "Contractor's Superintendent") who is (i) deemed acceptable to the Government; (ii) authorized to act on the Contractor's behalf; and (iii) be present on the job site at all times when contract work is being performed. (See Superintendence by the Contractor, Section I, Federal Acquisition Regulation (FAR) Clause 52.236-6.)
4. ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PROCESSING PLATFORM (IPP)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform (IPP) System. “Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice
Prime contractor and subcontract payrolls (if applicable) Payment Request Certification Release of Claims (Final) SF 1413 – Statement and Acknowledgment Construction Schedule (Microsoft Project or other Industry Standard Software (if applicable)) Schedule of Values Owner/Operator manuals (if applicable) Warranty Certificates (if applicable)
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via e-mail ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Clause)
H - SECTION H - Special Contract Requirements
1. UTILITIES
In accordance with FAR 52.236-14, Availability and Use of Utility Services, utility services required on the job site for accomplishment of the work will be furnished at no additional cost to the contractor. The Government will make no connections or alterations to the existing utility facilities for accomplishment of this work. Any change required by the contractor will be at his own expense and at no additional cost to the Government.
The following utility services will be made available: none
2. GENERIC GENDER TERMINOLOGY
Except where stipulated by the Federal Acquisition Regulations, the use of terms such as he, she, his, and her are not to be interpreted as implying other than neutral gender terms such as "it" or "their".
3. SAFETY
a. The Contractor shall have the ultimate responsibility for safety on the project site at all times until final completion and acceptance of the project. b. The Contractor shall comply with all Occupational Safety and Health Administration (OSHA) regulations, as found in 29 CFR 1910 and 1926, which are applicable to the construction project, including requirements set forth within solicitation provisions and contract clauses. In addition to OSHA safety standards, the Contractor shall also adhere to all https://www.ipp.gov/
AG-9AB5-S-17-0045 Page 17 of 45 current local, federal, and state safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.
c. The Contractor shall initiate and maintain an effective safety program that provides adequate systematic policies, procedures, and practices to protect their employees from and allow them to recognize, job-related safety and health hazards. The program shall include provisions for the systematic identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections. Each employee must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.
d. The Contractor shall immediately notify the CO of any accident, incident, or exposure resulting in a fatality, lost-time injury, or property loss/damage of $2,500 or more arising out of work performed under this contract. The Contractor shall investigate all work-related accidents/incidents to the extent necessary to determine their cause(s) and furnish the CO an investigative report outlining findings and proposed or completed corrective actions. The contractor shall, when required by the CO, have a separate and complete independent investigation of the accident/incident, and submit a comprehensive report of findings and recommendations to the CO. The CO shall consult with the COR, CR and Service safety personnel in reviewing the investigation report and corrective actions.
If the contractor fails or refuses to institute prompt corrective action, the CO may invoke the suspension-of-work clause in this contract or any other remedy available to the government. Any delay or cost resulting from a safety-related suspension of work will be borne by the Contractor.
e. In the event of an accident/incident, the Contractor shall be responsible for providing and obtaining appropriate medical and emergency assistance. Except for rescue and emergency measures, the scene of the accident/incident shall not be disturbed or the operation resumed until the on-site aspect of the investigation has been completed. f. Service safety personnel and representatives from Federal, State, and local government agencies shall have the right to examine and conduct an investigation at sites or areas where work under this contract is being performed. The absence of such investigations shall not relieve the contractor of their safety program responsibilities.
4. ENVIRONMENTAL
The contractor is responsible for establishing and maintaining compliance with all applicable laws, regulations, rules, and standards, including without limitation, those regulations, rules, and standards, promulgated for the administration and enforcement of the following laws: the…
This is the start of the file's text. The full file is on GovTribe.