AG-9AB5-S-17-0021_amend_2.pdf

PDF 93 KB Posted

Attached to
3N16 Road Washout Repairs Federal contract opportunity
Solicitation number
AG-9AB5-S-17-0021
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

View the file

Other files for this federal contract opportunity

Other files attached to 3N16 Road Washout Repairs, newest first.
File Type Posted
AG-9AB5-S-17-0021_mod_1.pdf PDF
Project_Experience_Questionnaire.docx DOCX document
PPQ.docx DOCX document
3N16_Slope_Failure_Repairs_Drawing_Sheets.pdf PDF
3N16_SBNF_Slope__Repair_Contract_Maps.pdf PDF
3N16_SBNF_Slope_Repair_-_Special_Project_Specifications_-_Final.pdf PDF
AG-9AB5-S-17-0021_solicitation.pdf PDF
DBA_CA27.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-9AB5-S-17-0021

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

9AB5

ARCADIA CA 91006

701 N SANTA ANITA AVE

R5 SO-CAL ACQ SERVICE AREA SCASA

USDA FOREST SERVICE

03/03/2017000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/06/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

3N16 Road Washout Repairs

A. The purpose of this amendment is as follows:

1. Extend the solicitation due date until March 9, 2017 at 10:00 am Local time.

2. To respond to the questions received.

a. Regarding 3N16 washout, Solicitation AG-9AB5-S-17-0021, on page 1 of 10 of drawings the first page references 3N21 and we want to ensure that there is no work to be performed at

3N21 for this project.

answer: 3N21 is not part of this contract.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

VINCENT CHUA

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

AG-9AB5-S-17-0021/000002

b. Additionally, in section 171.03, pg. 31 of 42, it is stated "perform all cleaning work at a commercial facility approved in writing by the contracting officer" What is meant by commercial facility? Typically we clean our equipment during demobilization when getting ready to mobilize to the next project. Is this not acceptable?

answer: This requirement will be satisfied as long as the equipment is cleaned and inspected by the government prior to off-loading on NF land.

c. On drawing page C6, titled Front Wall, drawing specifications show 3 foot lifts and to our understanding the max is 2 feet.

answer: The understanding is correct. The front wall detail from station 0+68 to 0+82 is shown incorrectly. Since the wall construction between these stations is welded wire facing as shown on the ¿Facing Summary¿ table, each facing level height should be shown as 2 foot height. The front wall detail shows 2 lifts/levels, when there will actually be 3 lifts/levels.

d. Additionally, on the same page, C6 "Wall

Section" drawing, is the wall battered?

answer: Wall batter shall be in accordance with the manufacturers standard installation guidelines.

e. Next, the Gabion Facing requires Class 1

Riprap, is this material price inclusive for bid item 255.08?

answer: Correct. All rock, gabion backets, reinforcing, and hardware are inclusive to item

255.08 in the schedule of items for site 3N16B.

f. Lastly for bid item 255.08 it states

"...(including connection to existing MSE Wall)" but we do not see an existing MSE Wall in the drawings or specifications, please clarify.

answer: The wording ¿¿(including connection to existing MSE wall)¿ should be deleted. An existing MSE wall does not exist at the site.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

AG-9AB5-S-17-0021/000002

B. All other terms and conditions remain unchanged and in full force and effect.

Period of Performance: 04/03/2017 to 05/22/2017

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110