SECTION 01720
AS-BUILT DRAWING
PART 1 GENERAL
1.01
DESCRIPTION OF WORK
This Section describes the contractor’s responsibility to providing complete and accurate as-built drawings, meeting the requirements of this Section.
PART 2 PRODUCTS
2.01
MEDIA
Contractor shall be required to update all drawing monthly. The Contractor will be provided five full size (11X17) paper prints of the original drawings and an electronic file with drawings in Auto-CAD 2010 format. The Contractor shall mark one set of original paper prints and make the changes on each sheet of the contract drawings on Auto-CAD 2010. The drawings and the Auto-CAD information, in CD format, shall be returned to the Government. The Contractor shall also provide to the Government at contract closeout a final plot of as-build drawings on .004 clear film and one set of blue line or black line paper prints.
PART 3 EXECUTION
3.01
REQUIREMENTS
The Contractor shall revise the drawing to reflect changes in the project as construction progresses. These drawings shall be updated at least monthly to reflect the approved changes. The paper copy shall be kept current and be available at all times at the project site. If the Contractor fails to keep AS BUILT drawings current, progress payments will be delayed until the requirements of this section are met.
At the close of the project, the Contractor shall provide final drawings conforming to requirements in Part 2.
Each drawing shall contain the words “AS-BUILT” in a conspicuous location and in the same location on each drawing. The Government will review the as-built drawings, and if revisions are required, the revised as-built drawing will be so noted with the revision date indicated. Final payment under this contract will be withheld until receipt of final, approved as-built drawings. (Also see Section 01442, 3.03 RECORDS).
END OF SECTION