QUESTION 3.doc

DOC document 21 KB Posted

Attached to
YELLOW ROSE SPRINGS BARRIER INSTALLATION Federal contract opportunity
Solicitation number
AG-91U4-S-09-0008
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

QUESTION 3 AND ANSWER

View the file

Other files for this federal contract opportunity

Other files attached to YELLOW ROSE SPRINGS BARRIER INSTALLATION, newest first.
File Type Posted
QUESTION 2.doc DOC document
OhvBarriers SPECIFICATION.pdf PDF
AMENDMENT 2 - BOUNDRY RIDGE PROJECT - BARRIER DETAILS.pdf PDF
AMENDMENT 2 - BOUNDRY RIDGE PROJECT SITE MAP.pdf PDF
AMENDMENT 2 - BOUNDRY RIDGE PROJECT MAPS.pdf PDF
AMENDMENT 2 - BOUNDRY RIDGE PROJECT DRAWING.pdf PDF
AMENDMENT 2 - BOUNDRY RIDGE PROJECT DRAWING - 2.pdf PDF
ScheduleB - amendment 1.doc DOC document
Amend1_Statement of Work - AMENDMENT 1.doc DOC document
OHV_Barrier_Spec - AMENDMENT 1.doc DOC document
Yellow Rose.pdf PDF
AG-91U4-S-09-0008.doc DOC document
Yellow Rose.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION 3: To whom it may concern; Drawing# D4 (Barricade Details) shows 28 "T" posts in an X configuration placed in front of a Four foot high berm .My questions are 1. looking from the highway are the posts first and the berm second or vice versa? 2. Are the posts to be driven into existing soil or are they to be placed in a trench and backfilled with concrete? Clarification would be greatly appreciated . Thank You

ANSWER 3:

1.) Posts for the earthen barrier are first driven 2 feet into ground in ‘X’ pattern along the centerline of the barrier, then each set of two forming an ‘X’ are tied together with #10 or thicker wire three (3) feet above the ground and then the earthen barrier is formed up around the posts to a height of 4 feet, (thus burying the tie) and the 1 ½ to 2 feet of remaining post sticks out the top of the barrier down it’s centerline.

2.) Posts in the concrete trench are placed during the concrete pour and need not be driven into the soil.