SPECIAL PROJECT SPECIFICATION
Section 101 – Terms, Format and Definitions
101.03 Abbreviations
Available Avail Coating Coat Construction Const
Contracting Officer Representative COR Government Gov’t.
Includes Culvert Excavation Incl Culv Exc Individual Removal of Trees Ind Removal/Trees Large Lg Left Lt Logs Log Medium Med Millimeter Mil One Thousand Gallons Mile M.Gals.MI. or MGM Options Opt Placement Method P.M.
Right Rt Slash Treatment S.T.
Small Sm
Steel Stl Structure Str Timber Tbr Treatment Treat Typical Typ
03 SPS 101 -1 DPG (3/16)
Section 101 – Terms, Format, and Definitions
101.04 Definitions
Add the following:
”Noxious Weeds or Weeds. Any exotic plant species established or that may be introduced in the State which may render land unfit for agriculture, forestry, livestock, wildlife or other beneficial uses and which is designated by the State’s Department of Agriculture, or by the County’s weed management district, or by other appropriate agencies having jurisdiction.
Weed Management District. A weed management district is any area of land identified for the purpose of weed management or control. Such an identified land area may be, but is not limited to one of the following: a project or job site, a County, two or more Counties or a National Grassland.”
Section 102 – Bid, Award and Execution of Contract
Delete entire section
Section 103 – Scope of Work
Delete Subections 103.02 – 103.05
Section 104 – Control of Work
Delete Subsections 104.03 and 104.04
03 SPS 101, 102, 103, 104 - 2 DPG (3/16)
Section 106 – Acceptance of Work
106.05 Statistical Evaluation of Work and Determination of Pay Factor (Value of Work)
Delete this subsection
106.07 Partial and Final Acceptance
Delete this subsection
Section 107 – Legal Relations and Responsibility to the Public
107.04 Railroad Protection
Delete this subsection
107.05 Responsibility for Damage Claims
Section 108 – Prosecution and Progress
Delete entire section
03 SPS 106, 107, 108 -1 DPG (3/16)
Section 109 - Measurement and Payment
109.02 Measurement Terms and Definitions
Under “(b) Cubic yard”
(1) Cubic Yard in place, “ add the following:
”(d) Aggregate Base or Surfacing, Compacted in Place. The measurement computed using measurements of material in the compacted state on the project.
109.06 Pricing of Adjustments
Delete this subsection
109.07 Eliminated Work
109.08 Progress Payments
109.09 Final Payment
03 SPS 109 – 1 DPG (3/16)
Section 203 – Removal of Structures and Obstructions
Delete the entire FP-03 specification and replace it with the following:
Description
203.01 This work shall consist of the requirements for the removal and disposing of the buildings, structures, obstructions, concrete slabs and debris, wood piles and the backfilling of the resultant holes and compaction requirements.
Material
203.02 Conform to the following:
Backfill material to be obtained from Government designated sources. Material to be free of excess moisture, muck, frozen lumps, roots, sod or other deleterious material.
Construction Requirements
203.03 Removing Material
Construct structurally adequate debris shields to contain debris within the construction limits. Do not permit debris to enter waterways, travel lanes open to public traffic, or areas designated not to be disturbed.
Raze and remove the buildings, foundations, structures, concrete slabs and other obstructions interfering with the work and not designated to remain.
In excavation areas, backfill and compact cavities left by structural removal with backfill material to the level of the finished ground and landscape so that water will drain away from the excavations. In the resultant excavations of the foundations for Items 203A and 203B, compact the backfill material by two (2) passes of mechanized, vibratory compaction equipment. One (1) pass is down and back on each twelve (12) lift at the width of the compactor. In the other items, compact the backfill material with the hauling and spreading equipment.
03 SPS 203-1 DPG (3/16)
203.04 Disposing of Material
Dispose of all materials and debris off the National Grasslands according to Federal, State and local regulations. Recycle or dispose of all materials legally off the project.
No burying of removed materials to be disposed is allowed on National Grasslands.
203.05 Acceptance
Removal and disposal of structures and obstructions will be evaluated under Subsection 106.02.
Measurements
203.06 Measure the Section 203 items listed in the bid schedule according to Subsection 109.02
Payment
203.07 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05
03 SPS 203-2 DPG (3/16)
Section 211 – Roadway Obliteration
211.01 – This work consists of obliterating a roadway by Method 1
Method 1. Obliterate the roadway by restoring to approximate original ground contours. Keep excavated material within the original construction limits. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Assure positive drainage from reclamation. Strip and stockpile topsoil prior to obliteration. Replace topsoil after contouring is finished after inspection of the obliteration by the COR.
03 SPS 211 -1 (5/16)
The Ebert’s Ranch Facilities Removal and Disposal Project
Phase 2 Photos
ITEM # 203A – South site garage, barn, silo slab, wood pile and cattleguards– Photos # 1 - 9
Photo #1 – South site garage, outside
Photo #2 – South site garage, inside
Photo #3 – South site garage
Photo #4 – South site barn, outside
Photo #5 – South site barn, inside
Photo #6 – South site grain bin concrete slab
Photo #7 – South site wood pile
Photo #8 – South site cattleguard #1 with bases and about 100 feet of fenceline to remove & dispose
Photo #9 – South site cattleguard #2 with bases and gate to remove & dispose. Install new barbed wire gate with braces and re-fence removed gate.
ITEM 203B – Main Ranch site concrete slabs, wood/refuse pit, old machinery and assorted debris. Photos # 10-28
Photo #10 – Main ranch site - grain bin slab #1
Photo #11 – Main ranch site - grain bin slab #2
Photo #12 – Main ranch site - barn concrete foundation
Photo #13 – Main ranch site - refuse pit
Photo #14 – Main ranch site - refuse pit
Photo #15 – Main ranch site - combine, sickle mower
Photo #16 – Main ranch site - machinery parts to remove located in vicinity of combine & mower
Photo #17 – Main ranch site - machinery parts to remove located in vicinity of combine & mower
Photo #18 – Main ranch - site concrete sidewalk
Photo #19 – Main ranch site - steel, 3” dia. Vent pipes
Photo #20 – Main ranch site - concrete debris
Photo #21 – Main ranch site - 2nd steel vent pipes
Photo #22 – Main ranch site - wood pile
Photo #23 – Main ranch site - concrete debris
Photo #24 – Main ranch site cattleguard #3 with bases to remove & dispose. Install new barbed wire gate with braces.
Photo #25 – Main ranch site cattleguard #3 with bases to remove & dispose. Install new barbed wire gate with braces.
Photo #26 – Main ranch site cattleguard #4 with bases to remove & dispose. Install new barbed wire gate with braces.
Photo # 27 - – Main ranch site cattleguard #5 with bases to remove & dispose
Photo # 28 – Main ranch site cattleguard # 6 to remove & dispose
Item 211 – C – Main Ranch site road to be reclaimed
Photo # 29 – beginning of 1,100 foot roadway to be reclaimed, typical