S140004_Preproposal_Conf_032614.docx
DOCX document 56 KB Posted
- Attached to
- Shoshone NF Integrated Resource Data Collection IDIQ Federal contract opportunity
- Solicitation number
- AG-8544-S-14-0004
About this file
Attachment to SF30 Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG8544S140004_Amd4.pdf | ||
| AtchS140004_0003.docx | DOCX document | |
| AG8544S140004_Amd3.pdf | ||
| AG8544S140004_Amd2.pdf | ||
| AG8544S140004_Amd.pdf | ||
| AG8544S140004_0001.docx | DOCX document | |
| ShoshoneResourceDataCollectionIDIQ_Final.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-8544-S-14-0004 – Shoshone National Forest Integrated Resources Data Collection IDIQ Amendment 0002 General Info:
· This contract is for Integrated Resource Data Collection on the Shoshone National Forest. It is an Indefinite Delivery Indefinite Quantity contract with a Base year and two one-year options to one or more awardees.
· Quantities are estimates only
· B.1 & B 2 Information on submitting prices
· You must provide prices on all items.
· Solicitation for Services - require the mobilization costs to be included in the line items.
· Your maximum prices must be competitive.
· Task orders will be issued in accordance with Section G.1 and will be competed between the awardees of the solicitation.
· Scope of project covers Service work.
· Task orders will advise you of the work to be performed.
· Service – Service Contract Act Wage rates apply for non-professional hires.
· 52.219-14 requires you to perform at least 50% of work by Contractor or employees – see clause for actual details.
· Quotes are due April 14, 2014 by 4:00 pm. Instructions for quoting – Section L – require three originals of your technical proposal and one original of your price proposal. Due to the size and requirement to submit 3 copies, faxes and emails will not be accepted.
· Refer to section K – must return completed certifications with your price proposal. Section M provides the technical proposal evaluation factors you need to address in your technical proposal. Return Experience Questionnaire with your technical proposal.
· Clarification on Section M Factor 3-Sustainable Procurement Program. This is a new required factor for all USDA procurements. Therefore the offeror must address this factor; however, it is much less important than Factor 1 – Technical Capability and Factor 2 – Past Performance.
Amendment 0001 – contained changes to Section M.
Replaced FAR 52.212-2 Evaluation – Commercial Items Added Factor 3- Sustainable Procurement Program Deleted Sections M.3.5 through M.3.6 and Added M.3.5 through M.3.8.
Sustainable Procurement Program because it is a newer requirement needs to be addressed in the proposal; however, it will be of less importance than technical and past performance.
Amendment 0002 – will contain the following changes with any notes, questions and answers, and attendees from the teleconference meeting.
Offeror must acknowledge each amendment by signing the SF30s Amendment to the Solicitation and submitting them with their proposal. The SF30s do not count towards the maximum pages.
DELETE SECTIONS L.4 AND L.4.1 IN THEIR ENTIRETY:
L.4 FAR 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: ATTN: Debbra Stulc
FAX#: (307) 578-5112
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document--
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal.
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timelines, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
(End of Provision)
L.4.1 – ADDENDUM TO 52.215-5 – EMAIL QUOTES.
Receipt of proposals cannot be guaranteed due to size of documents, gateway limitations, and traffic. Therefore, Emailed proposals will be acknowledged with a return acknowledgement.
AND REPLACE WITH THE FOLLOWING:
L.4 FACSIMILE AND EMAIL PROPOSALS:
Neither facsimile nor email proposals will be accepted; submit your proposal in accordance with Section L.3.
DELETE SECTION M.3.3.1 IN ITS ENTIRETY:
M.3.3.1 Past Performance:
The proposal must address past performance. Offerors shall submit the following information as part of their proposal for both the Offeror and proposed major subcontractors. Offerors should provide only the information listed below. General performance information will be received from references provided in “(a)” below.
(a) A list of all applicable contracts and subcontracts completed during the past three (3) years and all contracts and subcontracts currently in process. The list should include, but is not limited to, contracts and subcontracts similar in nature and complexity to that required by this solicitation. Contracts listed should include those entered into by the Federal Government, agencies of state and local governments, and commercial customers. Offerors that are newly formed entities, without prior contracts as an entity, should list contracts and subcontracts completed by all key personnel. Include the following information for each contract and subcontract:
1) Name of contracting activity
2) Contract Number
3) Contract Type
4) Total contract value
5) Completion date, or stage of completion if still in process
6) Contract work
7) Contracting Officer
8) Program manager
9) Second contact person
10) Administrative Contracting Officer, if different from Contracting Officer
11) List of major subcontractors
NOTE: For 7, 8, 9 and 10 provide Name, Address, Telephone and FAX number.
An “Owner/Client Past Performance Survey” is a method to provide references for previous work; and is included for your use. Submit to your past Owner – Client references to complete and direct them to return their responses to the Contracting Officer noted on the Survey. Offerors may also submit copies of any other past performance evaluations regardless of format.
At the option of the Offeror, this listing of performance references may be provided prior to the offer due date (Reference Block 8 of the Solicitation, Offer and Award form). However, listings must be provided NO LATER than the offer due date/time.
(b) The Offeror shall provide information on problems encountered on the contracts and subcontracts identified in a) above and corrective actions taken to resolve those problems.
(c) The Offeror may describe any quality awards or certifications that indicate the offeror possesses a high quality process for providing the products and services required. Describe when the award or certification was bestowed. If the award is over three years old, present evidence that the qualifications still apply.
(d) Performance information will be used as an evaluation factor against which offerors’ relative rankings will be compared to assure best value to the Government. Evaluation of past performance will allow the Government to determine whether the Offeror consistently delivered quality services in a timely manner. References other than those identified by the offeror, may be contacted by the Government, with the information received used in the responsibility determination and in evaluation of the offeror’s past performance.
(e) The Office of Management and Budget (OMB) has authorized Federal agencies to collect past performance information under OMP clearance number 9000-0142. Both, this information provided in the proposal, and Government records will be used to evaluate the Offeror’s past performance; however, references other than those listed may also be contacted.
AND REPLACE WITH THE FOLLOWING:
M.3.3.1 Past Performance:
The proposal must address past performance. Offerors shall submit the following information as part of their proposal for both the Offeror and proposed major subcontractors. Offerors should provide only the information listed below. General performance information will be received from references provided in “(a)” below.
(a) A list of all applicable contracts and subcontracts completed during the past three (3) years and all contracts and subcontracts currently in process. The list should include, but is not limited to, contracts and subcontracts similar in nature and complexity to that required by this solicitation. Contracts listed should include those entered into by the Federal Government, agencies of state and local governments, and commercial customers. Offerors that are newly formed entities, without prior contracts as an entity, should list contracts and subcontracts completed by all key personnel. Include the following information for each contract and subcontract:
1) Name of contracting activity
2) Contract Number
3) Contract Type
4) Total contract value
5) Completion date, or stage of completion if still in process
6) Contract work
7) Contracting Officer
8) Program manager
9) Second contact person
10) Administrative Contracting Officer, if different from Contracting Officer
11) List of major subcontractors
NOTE: For 7, 8, 9 and 10 provide Name, Address, Telephone and FAX number.
Offerors may submit copies of any other past performance evaluations regardless of format.
(b) The Offeror shall provide information on problems encountered on the contracts and subcontracts identified in a) above and corrective actions taken to resolve those problems.
(c) The Offeror may describe any quality awards or certifications that indicate the offeror possesses a high quality process for providing the products and services required. Describe when the award or certification was bestowed. If the award is over three years old, present evidence that the qualifications still apply.
(d) Performance information will be used as an evaluation factor against which offerors’ relative rankings will be compared to assure best value to the Government. Evaluation of past performance will allow the Government to determine whether the Offeror consistently delivered quality services in a timely manner. References other than those identified by the offeror, may be contacted by the Government, with the information received used in the responsibility determination and in evaluation of the offeror’s past performance.
(e) The Office of Management and Budget (OMB) has authorized Federal agencies to collect past performance information under OMP clearance number 9000-0142. Both, this information provided in the proposal, and Government records will be used to evaluate the Offeror’s past performance; however, references other than those listed may also be contacted.
QUESTIONS AND ANSWERS
Q. Page 1, Section B.2. What is meant by “Unit prices prevail”? – A. The unit price stated on the Schedule of Items is the price that is used for evaluation for pricing; if you made a mathematical error on your calculation then we will use the unit price times the estimated quantity for the total price of the line item.
Q. Page 3. Section B.2. How does the level of difficulty in Task Nos. 1 and 2 relate to that of Tasks 3, 4, and 5? The latter tasks do not have a level of difficulty listed. What should we assume? This question also applies to the Optional Years.
A. See Section C.1.6 and LEVELS OF DIFFICULTY ITEM CATEGORY (Page 25) and C.1.6.1.
Q. Page 27. Section C.1.8.5. Is Rosgen level 3 training genuinely necessary to perform the rather basic stream survey fieldwork specified in the solicitation? Can an equivalent or greater level of education, training, and experience be substituted?
A. The intent of this qualification is to ensure that individuals have the experience and training necessary to properly identify bankfull. This qualification is required.
Q. Page 27. Section C.1.8.5. Is the use of Trimble brand GPS hardware and software genuinely necessary? May we substitute equipment of equal or superior quality and specification, provided the contract deliverables are provided in the specified formats (e.g. shapefiles)?
A. The intended utility of this software was to allow for differential correction of GPS data to ensure that the precision was sub-meter. It is also a tool for smoothing the data lines and converting the data into shapefiles. If this can be accomplished through other means and still meets the precision, smoothing, and shapefile creation requirements, substitutions will be acceptable. Proponents will need to identify the substitution and demonstrate the equivalency.
Q. Page 94. Exhibit F, General Field Data form. What is the intended use of this form? Is it required that this form be completed for all sampling sites for all resources (range, wildlife, riparian, hydrology)?
A. Exhibit F pertains only to the Rangeland data collection. It will be completed for each sampling location.
Q. Page 140. The PERMANENT TRANSECT CLUSTER SUMMARY form includes 3 transect columns. Does this mean the Parker 3 Step procedure is to be performed for 3 transects at each “Transect” site?
A. No.
Q. Page 141. Can the same 100’ transect alignments be used for the Parker 3 step, Cover Frequency and the Sample Point Transect assessments?
A. Yes. They need to be.
Q. Page 241, Section L.3.1.6. The text states that proposals should be not more than 50 pages in length.
a) Does that page count apply to Volume I and Volume II individually, or to the total of both together?
A. Volume I - Technical proposal can be no more than 50 pages. It does include the Experience Questionnaire
b) Does the 50 page total include those pages from the Solicitation that must be filled out or signed and submitted (i.e. pages 3-21, all of Section K, signature page 218, the Experience Questionnaire, etc) which together amount to more than 40 pages?
A. L.3.1.1 (b) includes the SF-1449, Schedule of items and Section K. Volume II is limited to 60 pages.
| Q. | Does the 50 page limit include resume? |
| A. | Yes. |
Q. Page 242. Section L.4.1. It is indicated that a confirmation of email proposal submittal will be provided, but it is not stated explicitly that email submission of proposals is permitted.
a) Is email submission of a proposal in response to this solicitation permitted?
A. Due to the size of the anticipated proposals L.4 and L.4.1 will be deleted in their entirety and replaced with the following statement “Neither facsimile or email proposals will be accept; submit your proposal in accordance with Section L.3.”
b) If so, and what is the procedure? Is there a preferred file format? Are their file size limits or other considerations?
A. N/A
c) Are submissions via FTP or other electronic transfers permitted?
A. N/A
Q. Page 244. Section M.1. What is the relative weight assigned to each of the three evaluation criteria? The text states that criteria 1 & 2 are equally weighted, and that together they are larger than 3. Is that 26%, 26%, 48%? Or 45%, 45%, 10%? Or …?
A. See Amendment 0001 to the solicitation AG-8544-S-14-0004.
As amended the factors are as such: Factor 1 – Technical Capability and Factor 2 – Past Performance are of equal importance. Factor 3 – Sustainable Procurement Program is of less importance than Factor 1 and Factor 2. When combined Factors 1, 2, and 3 are more important than price.
There is no weighted assignment of the factors. The critical factor in making any cost/technical tradeoff is not the spread between the technical scores but, rather, the significance of that difference. The significance of the spread of scores will be determined on the basis of what the difference might mean in terms of performance and what it would cost the Government to take advantage of it. Award may not necessarily be made for technical capabilities that would appear to exceed those needed for the successful performance of the work. The Government reserves the right to make cost/technical trade-offs that are in the best interest and advantageous to the Government.
| Q. | It is not clear if the “Owner/Client Past Performance Survey” (p. 248) is required or is optional, please clarify. |
| See Answer below. |
Q. Page 248. Section M.3.3.1. The text states that an Owner/Client Past Performance Survey form is provided, but it is not to be found in the solicitation document.
a) Is this reference survey form required?
A. The solicitation will be amended to delete the following paragraphs in their entirety:
“An “Owner/Client Past Performance Survey” is a method to provide references for previous work; and is included for your use. Submit to your past Owner – Client references to complete and direct them to return their responses to the Contracting Officer noted on the Survey. Offeror may also submit copies of any other past performance evaluations regardless of format.”
At the option of the Offeror, this listing of performance references may be provided prior to the offer due date (Reference Block 8 of the Solicitation, Offer and Award form). However, listings must be provided NO LATER than the offer due date/time.”
And replace with “Offeror may submit copies of any other past performance evaluations regardless of form.”
b) If so, from where may we obtain it?
A. N/A
c) How many of the listed references need to complete the reference survey?
A. See Section M.3.3.1 for submitting information regarding past performance.
Q. Section K requires certification of the firm’s status with respect to service disabled veteran owned, woman owned small business, etc. Will preference for award of contracts under this solicitation be given for those categories?
A. See FAR Clause 52.219-6 (Page 78) this is a total small business set-a-side. FAR Clause 52.212-3 (page 222) is to be used to determine your company’s eligibility to meet this requirement.
| Q. | Will there be preference for or against firms that team with other firms to provide services in response to this solicitation? |
| A. | This is a small business set-aside. SBA is the Agency that makes the determination on business sizes for teaming and joint ventures; therefore you will need to contact the SBA for teaming or joint ventures because SBA will need to make a determination if you meet the small business set-aside status. (Neither for nor against). |
Q. Under the contracts awarded under this solicitation, is there a limit to the percentage of the work that may be sub-contracted?
A. See clause 52.219-14 Limitation on subcontracting. (Page 78)
Q. Has the Shoshone NF procured similar services for any of the item categories in the past and, if so, will you please provide the name(s) of the firms that performed those services?
A. The information you are requesting can be found on Federal Business Opportunities website https://www.fbo.gov/. You may search by resource area and Forest. It will provide information as to the awardee and award amount.
| Q. | What is the total estimated contract value for the requested services assuming the quantities and conditions contained in the solicitation? |
| A. | See AGAR 452.216-74 CEILING PRICE (FEB 1988). (Page 77) |
| Q. | Will this IDIQ be made available for use by other National Forests? |
| A. | The Scope of the Contract is limited to the Shoshone National Forest. |
| Q. | To how many contractors does the USFS anticipate awarding an IDIQ contract under this solicitation? |
| A. | See Section L.6 FAR Clause 52.216-27 Single or Multiple Awards. (Page 242) |
| Q. | Will Task Order Pre-work Conferences be held by telephone, online meeting, or in person? If in person, where will these meetings be held? |
| A. | The government reserves the method of meeting to be agreed upon with awarded contractor(s) as long as it is in compliance with Section G.2.1. |
| Q. | Is a Wildland Hydrology Level III River Assessment and Monitoring certification actually going to be required or will a Wildland Hydrology Level II River Morphology and Applications certification suffice? |
| A. | This is the same question and response as number 3. The intent of this qualification is to ensure that individuals have the experience and training necessary to properly identify bankfull. This qualification is required. |
| Q. | Will businesses be able to bid on individual portions of the project (example: bid on range and wildlife portions only)? |
| A. | See Section B.2 Estimated Quantity. In accordance with B.2 “… a unit price must be provided for all items even those estimated at zero. Failure to provide a unit price on all items may result in the Offeror’s proposal being found non-responsive.” |
| Q. | Will specific data point locations be available prior to bidding? |
| A. | See Section B.2 Estimated Quantity. Specific data point locations will be issued with each Task Order in accordance with G.1. |
| Q. | Can the criteria cited in C.1.8.1 be waived with proof of equivalent experience and knowledge? |
| A. | Clarification to C.1.8.1 and C.1.8.4: The Hydrology Crew Leader must have the Rosgen Level III training. Within the associated field data collection crew, one individual shall have a minimum of a Bachelor of Science degree in a field of natural resource management from an accredited college or university. |
| Q. | Survey Method for collecting data (Survey grade robotic total station & GPS) - Can the original criteria be waived with proof and demonstration that the methods that we use are equivalent or better within the field of stream survey? |
| A. | Requirements for survey equipment are listed in C.7.5, methodologies are described in C.8.4.1.5, and data forms to be utilized are identified in Section J (Exhibit Q). Alternative equipment and survey methods can be proposed, but the proponent must clearly describe how the alternative meets or exceeds the contract specifications. |
| Q. | Will the IDIQ only be awarded to the firms/teams or joint ventures who are able to perform all Contractor functions, i.e. Rangeland, Wildlife, Riparian and Hydrology? May we submit for only the Hydrology/Stream Survey portion and is this acceptable or considered beneficial to the issuing office? |
| A. | See Section B.2 Estimated Quantity. In accordance with B.2 “… a unit price must be provided for all items even those estimated at zero. Failure to provide a unit price on all items may result in the Offeror’s proposal being found non-responsive.” |
| Q. | Can the Level III Wildland Hydrology Course be completed after the award? |
| A. | Yes, but it must be completed prior to the initiation of any stream survey work. |
| Q. | We have done all of the monitoring items used in the MIM and PFC using the FS R2 Riparian Inventory Methods. We have this completed monitoring on over 600 stream miles on the Manti La Sal National Forest and the Fish Lake National Forest. We have also applied the Rosgen Level II survey protocol on these streams as well. Would we still have to take MIM and PFC training? |
| A. | Per section C.1.8.4, the Riparian Crew Leader must have one or more field seasons of experience in conducting PFC inventory, and/or one or more field seasons of experience as principle investigator on a PFC inventory project. |
For the MIM, the Crew Leader must have had either a one week formal MIM training, or have completed MIM for at least one field season under the supervision of someone who had completed the MIM training.
| Q. | Does the Shoshone National Forest have boreal owl, flammulated owl and northern goshawk call they would prefer us to use, if so will they be provided? |
| A. | Yes we have preferred calls, and they will be provided. |
| Q. | Do we have to prepare a cost proposal on every item for year one? |
| A. | See Section M.3.7 and M.3.8 (amendment 0001). Provide a general outline of how you arrived at the prices so that the Government can determine whether pricing is reasonable, balanced, and that there is an understanding of the work. |
| Q. | In the Evaluation Criteria, what is the difference between the submittal requirements for Key Personnel (M.3.2.1) and Qualifications (M.3.3.2)? |
| A. | For Key Personnel, this should be a concise list that correlates to the requirements listed in Section C.1.8.1. Explanations of qualifications should reiterate that all Key Personnel requirements have been met, but more importantly demonstrate the relevant past performance of listed Key Personnel and how they completed projects on time and within budget. |
| Q. | For Level IV difficulty (> 5 miles), is there a maximum distance for the level of difficulty? If not, how is one supposed to accurately bid on a task order when the distance could be 5.5 miles or 15 miles or more? |
| A. | The assumption was that anything over five miles would require more than one day to access, and all others would take a day or less. Generally, there would not be sites greater than 10 miles. |
| Q. | Will there be any areas where an outfitter is required? Again, this would significantly affect costs. |
| A. | The Forest Service will not require that proponents utilize outfitters. |
| Q. | In developing our maximum cost estimates, can we assume that all of the items listed within a Task No. will be completed within proximity (~10 miles) to one another? For example, would all of the rangeland transects identified in Task 1 for the base year (p. 3) be scattered throughout the Forest, or would they all be located in the same general area? |
| A. | Tasks will be grouped as much as possible within an allotment or watershed, but multiple watersheds across the Forest may be identified within a Task Order. See Section J, Exhibit B (example maps 1 and 2). |
| Q. | Should we assume that the rangeland inventories using the three different methods listed as base year Tasks 3, 4 and 5 (pp. 3 and 4) are the same transects that were relocated or newly established under Tasks 1 and 2? |
| A. | The Task Order will specify which protocols and if they are a new or relocate. |
| Q. | Can Task Orders be specific to a single discipline such as Hydrology, or will all Task Orders be multi-disciplinary? |
| A. | Task Orders are intended to be multi-disciplinary, but there may be instances where only one or two resource areas are the focus of a Task Order. |
| Q. | Are email submissions acceptable? |
| A. | No. See question number 10. |
| Q. | Will proposals be accepted for individual study types (i.e., Rangeland, Wildlife, Riparian and Hydrology)? Or, will only proposals that have capability for all study types be accepted? |
| A. | Proposals must address all study types. |
| Q. | What is the anticipated number of contract awards for this IDIQ? |
| A. | See Section L.6 FAR Clause 52.216-27 Single or Multiple Awards. (Page 242) |
| Q. | Are the PFC Lotic reaches historically assessed, or are these first time PFC assessments? |
| A. | Polygons are established, but these are first time assessments. |
| Q. | Who has done this work previously – USFS or contract? |
| A. | Both the USFS and contractors have completed similar work previously. |
| Q. | There are estimates for number of transects for Rangeland for the base year but none for Wildlife. Is it possible for you to provide an estimate of the number of Wildlife transects for base year by level of difficulty? |
| A. | Estimates have been provided in the Schedule of Items. |
| a) | Have wildlife plots been previously marked? |
| A. | See section C.8.2.1.1 and C.8.2.1.2. There are not permanent markers at each site. The contractor will locate plots using a GPS. |
| b) | Do the estimates for Rangeland, Riparian and Hydrology reflect “best guess” of work to be done this year? |
| A. | The estimates are a best guess, but could vary depending on unit prices provided. |
| Q. | Can you explain “must have a working knowledge of the local area”? Does this mean a current working knowledge or knowledge that can be obtained through Travel Management maps, Forest maps, GIS, etc. |
| A. | See section M.3.1.1(d). |
| Q. | C.5 Flagging Standards states that “Flagging will remain in place until the COR/inspector has completed field survey.” Please confirm that it will not be the responsibility of the Contractor to remove flagging. |
| A. | The contractor is not responsible for removing the flagging. |
| Q. | Deliverables for the wildlife data are described as paper forms and in electronic format. Please clarify what this means. Does this mean scanned copies of paper forms or something else? What are the data files referenced? Is it expected that Contractor will be responsible for creating a database or spreadsheet? |
| A. | The contractor is not responsible for creating a database or spreadsheet. |
| Q. | Lynx questions: |
| a) | How many winter plots are there and what is the level of difficulty of each? |
| A. | See the B.2 for the estimated quantities, and Section C.1.6 Levels of Difficulty Item Category. |
| b) | How many summer plots are there and what is the level of difficulty of each? |
| A. | See section B.2 for the estimated quantities. |
| c) | If there are both winter and summer plots are they the same plots? |
| A. | No. |
| d) | Are the plots marked and if so how? |
| A. | See section C.8.2.1.1 and C.8.2.1.2. There are not permanent markers at each site. The contractor will locate plots using a GPS. |
| Q. | Boreal owl questions: |
| a) | Do transects and points already exist or do we have to establish them? |
| A. | See section C.8.2.1.1, C.8.2.1.2, and C.8.2.3. There are not permanent markers at each site. The contractor will locate plots using a GPS. |
| b) | If transects exist how many are there and what is the level of difficulty of each? |
| A. | Estimated quantities are listed in B.2 |
| c) | Are transects all the same length with the same number of survey points on each? |
| A. | No. |
| d) | If they exist, are the transects and points marked and if so how? |
| A. | They are mapped and GPS coordinates are available. |
| e) | Do all owl detections need visual or is audio OK? |
| A. | Audio is acceptable. |
| Q. | Flammulated owl questions: |
| a) | Do transects and points already exist or do we have to establish them? |
| A. | See section C.8.2.1.1, C.8.2.1.2, and C.8.2.3. There are not permanent markers at each site. The contractor will locate plots using a GPS. |
| b) | If the transects exist how many are there and what is the level of difficulty of each? |
| A. | Estimated quantities are listed in B.2 |
| c) | Are transects all the same length with the same number of survey points on each? |
| A. | No. |
| d) | If they exist, are the transects and points marked and if so how? |
| A. | These are not permanent transects. The contractor will be provided maps and coordinates. |
| e) | Do all owl detections need visual or is audio OK? |
| A. | Audio is okay. |
| Q. | Northern goshawk questions: |
| a) | How many transects are there and what is the level of difficulty of each? |
| A. | See B.2 for estimated quantities and C.1.6 for levels of difficulty. See C.8.2.4 and C.8.2.4.1 for specifications. |
| b) | Transects appear to be grouped. How many are there in each group or survey block? |
| A. | This will vary depending on the area to be surveyed. The areas to be surveyed are unknown at this time. |
| c) | Are transects all the same length with the same number of survey points on each? |
| A. | See C.8.2.4.2. “Transects shall have call stations spaced 200 meters apart and will average 5 calling stations per transect.” |
| d) | Are the transects and points marked and if so how? |
| A. | No. Transects and points will be mapped with coordinates provided for points. |
| e) | Will location data for known nests be provided to facilitate more efficient nest locations in the event of a response from a nearby survey point? |
| A. | Yes. If known goshawk nests are nearby, their locations will be provided to the contractor. |
| Q. | If the successful contractor chooses to utilize packing/outfitting/camp support services, to facilitate travel to and from the task sites, does the packer/outfitter/sub-contractor need to be licensed as an outfitter, work under an outfitting permit, or will their professional services fall under the work of the contract? There is a need, at the very least in cases of projects that are 5 miles or farther from established and identified navigable roadways and trailheads, of a packer/outfitter to transport equipment and camp supplies to and from the project site. |
| A. | There is no requirement for a state outfitting license for this type of activity. If a service is necessary, it will be covered under the work of the contract from the Forest Service perspective. There is not a need to require the contractor to use either a state licensed or Shoshone Forest Outfitter. |
| Q. | Can a University be considered a small business? |
| A. | SBA has established numerical definitions of small businesses, or "size standards," for all for-profit industries. Size standards represent the largest size that a business (including its subsidiaries and affiliates) may be to remain classified as a small business concern. In determining what constitutes a small business, the definition will vary to reflect industry differences. These size standards are used to determine eligibility for SBA’s financial assistance and to its other programs, as well as to Federal government procurement programs designed to help small businesses. |
The SBA, for most industries, defines a "small business" either in terms of the average number of employees over the past 12 months, or average annual receipts over the past three years. In addition, SBA defines a U.S. small business as a concern that:
· Is organized for profit
· Has a place of business in the US
· Operates primarily within the U.S. or makes a significant contribution to the U.S. economy through payment of taxes or use of American products, materials or labor
· Is independently owned and operated
· Is not dominant in its field on a national basis The business may be a sole proprietorship, partnership, corporation, or any other legal form. In determining what constitutes a small business, the definition will vary to reflect industry differences, such as size standards.
SBA would have to make the determination if a University meets the small business criteria.
| Q. | Is the final product basically several datasets with accompanying filled-out data forms or is data analysis a part of the project? If yes, what general types of analysis is the forest looking for? |
| A. | "Data analysis is not a part of the project. The contract is for data collection." |
LIST OF ATTENDEES
| Company |
| Name of Attendee(s) |
| Holm Blough & Company (HBCO) |
| Shane Trotter Ben McDonald |
| Big Picture Conservation LLC |
| Bill Dunn |
| Ecological Solutions Group LLC |
| Max Thompson |
| Colorado State University |
| David Jones Paul Block |
| Three Parameters Plus, Inc. |
| Justin Miner Jeff Mason Cindy Correll |
| Resource Environmental Management Consultants, Inc. (REMC) |
| Lyndsey Fox Jim Fricke Dan Dean |
| Bear Creek Environmental Consultants LLC |
| Matt Schweich |
| Sundance Consulting, Inc. |
| Randi Thomson Eric Burr |
| Trillium Botanical & Ecological Services |
| David Buscher |
| Confluence Inc. |
| Mark Story Jim Johnson Jim Lovell |
| RESPEC Consulting |
| Richard McEldowney |
| RedFISH Environmental LLC |
| Ernesto de la Hoz Justin Baker |
| Shell Valley Consulting |
| Jeff Petty |
| Biota Research and Consulting |
| Hamilton Smith |
| Headwaters Engineering |
| Erik Ryan |
| Dixon Land Management and Consulting, Inc. |
| Paul Dixon |
| Alder Environmental |
| Megan Smith |
Page | 9