Amendment 03.docx

DOCX document 25 KB Posted

Attached to
Lucerne Campground Reconstruction Federal contract opportunity
Solicitation number
AG-84N8-S-11-0024
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

Amendment 03

View the file

Other files for this federal contract opportunity

Other files attached to Lucerne Campground Reconstruction, newest first.
File Type Posted
Amendment 02 Site Visit Notes.docx DOCX document
amendment 01.doc DOC document
Attachment 01 Specifications 05022011.doc DOC document
AG-84N8-S-11-0024.rtf RTF text file
Attachment 03 General Decision Number UT20080104.mht MHT file
Attachment 01Specifications.docm DOCM document
Attachment 02 Drawings.pdf PDF
Attachment 04 General Decision Number UT20080076.mht MHT file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE OF PAGES
1
4
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
003
05/23/2011
6. ISSUED BY
CODE
84N8
7. ADMINISTERED BY (If other than Item 6)
CODE
84N8

U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.

Salt Lake City, UT 84119 U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.

Salt Lake City, UT 84119

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
(X)
9A. AMENDMENT OF SOLICITATION NO.
X
AG-84N8-S-11-0024

9B. DATED (SEE ITEM 11)

04/29/2011

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, X is required to sign this document and return 1_ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

Replace table 014100-1 in amendment 02 with attached revision, 05/20/2011.

Replace page number 15 with attached. This is to clarify completion date: (c) complete the entire work ready for use ONE HUNDRED EIGHTY (180) calendar days after the date the contractor receives the notice to proceed.

Solicitation response date is NOT extended and all other terms and conditions remain the same.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Brian Wharton

15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE SIGNED
/s/Brain Wharton
05/23/2011

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105
STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

TABLE 014100-1 (revised, 5/20/11)

Item

Subsection Certification or Test Required

Frequency

033000
2.12
Mixing and Delivery
Each Truck
033000
3.12
Concrete – Slump & Temperature
1 per truck load
033000
3.12
Concrete – Composite
1 test per 5 truck loads, min. 1 per day
221100
3.2
HDPE Pipe - Bent Strap Test
Once Daily
221100
3.5
Pressure and Leakage Test – Water Line
See Spec.
221100
3.6
Bacteriological Examination
After disinfection, before use
312000
3.14C
Compaction Test – at Pipe Zone
One test – at each road crossing
312000
3.14D
Compaction Test – above Pipe Zone
One test every other lift – at each road crossing
312000
3.14I
Tracer Wire Conductivity Test
Until Passing
312000
3.20D
Compaction Test – Exterior Concrete Slabs
See Spec.
312225
3.11B
Moisture-Density Relationship
One Test for Each Soil Type Encountered
312225
3.11B
Compaction – Subgrade
One test every 1000 sq. yd. of subgrade
321200
3.9B
Gradation and Asphalt Content
One per 1000 tons or Min. of 3 per Project
321200
3.9C
Field Density Tests – Asphalt
One test for every 800 sq. yd. of pavement
321204
3.4A
Compaction Tests – Road Base
One test for every 1000 sq. yd. of

aggregate

321204
3.4A
Compaction Tests – Aggregate Base for Concrete Slabs and Asphalt Path
One test for every five family units, two tests for each group unit, one test for every 30 square yards of sidewalk and one test for every 60 square yard of asphalt path.
329310
1.4B
Topsoil Analysis
One test per source
328000
3.16
Irrigation Pressure Testing
Until Passing

SECTION F - Deliveries or Performance

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use ONE HUNDRED EIGHTY (180) calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)

Within _10_calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is to be negotiated if needed.

Contract Time and Winter Weather Shutdown

(a) The count of calendar days to be charged against contract time will begin on the calendar day established by the Contracting Officer's written notice to the Contractor to proceed with the work, and will continue through the date of completion less time between Suspensions and Resume Work Orders. When winter weather sets in and the continuation of work is impractical, upon written request by the Contractor, the Contracting Officer may authorize a total suspension, until winter weather has passed and work can proceed.

(b) During period of total suspension, emergency work or minor operations not affected by nor connected with the cause of suspension may be permitted by the Contracting Officer without charge against contract time.

File details come from the government source that posted it. Updated .