Amendment 03.docx
DOCX document 25 KB Posted
- Attached to
- Lucerne Campground Reconstruction Federal contract opportunity
- Solicitation number
- AG-84N8-S-11-0024
About this file
Amendment 03
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 02 Site Visit Notes.docx | DOCX document | |
| amendment 01.doc | DOC document | |
| Attachment 01 Specifications 05022011.doc | DOC document | |
| AG-84N8-S-11-0024.rtf | RTF text file | |
| Attachment 03 General Decision Number UT20080104.mht | MHT file | |
| Attachment 01Specifications.docm | DOCM document | |
| Attachment 02 Drawings.pdf | ||
| Attachment 04 General Decision Number UT20080076.mht | MHT file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| 4 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| 003 |
| 05/23/2011 |
| 6. ISSUED BY |
| CODE |
| 84N8 |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
| 84N8 |
U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.
Salt Lake City, UT 84119 U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.
Salt Lake City, UT 84119
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
| X |
| AG-84N8-S-11-0024 |
9B. DATED (SEE ITEM 11)
04/29/2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| (X) |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN |
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, X is required to sign this document and return 1_ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Replace table 014100-1 in amendment 02 with attached revision, 05/20/2011.
Replace page number 15 with attached. This is to clarify completion date: (c) complete the entire work ready for use ONE HUNDRED EIGHTY (180) calendar days after the date the contractor receives the notice to proceed.
Solicitation response date is NOT extended and all other terms and conditions remain the same.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
Brian Wharton
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| /s/Brain Wharton |
| 05/23/2011 |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
TABLE 014100-1 (revised, 5/20/11)
Item
Subsection Certification or Test Required
Frequency
| 033000 |
| 2.12 |
| Mixing and Delivery |
| Each Truck |
| 033000 |
| 3.12 |
| Concrete – Slump & Temperature |
| 1 per truck load |
| 033000 |
| 3.12 |
| Concrete – Composite |
| 1 test per 5 truck loads, min. 1 per day |
| 221100 |
| 3.2 |
| HDPE Pipe - Bent Strap Test |
| Once Daily |
| 221100 |
| 3.5 |
| Pressure and Leakage Test – Water Line |
| See Spec. |
| 221100 |
| 3.6 |
| Bacteriological Examination |
| After disinfection, before use |
| 312000 |
| 3.14C |
| Compaction Test – at Pipe Zone |
| One test – at each road crossing |
| 312000 |
| 3.14D |
| Compaction Test – above Pipe Zone |
| One test every other lift – at each road crossing |
| 312000 |
| 3.14I |
| Tracer Wire Conductivity Test |
| Until Passing |
| 312000 |
| 3.20D |
| Compaction Test – Exterior Concrete Slabs |
| See Spec. |
| 312225 |
| 3.11B |
| Moisture-Density Relationship |
| One Test for Each Soil Type Encountered |
| 312225 |
| 3.11B |
| Compaction – Subgrade |
| One test every 1000 sq. yd. of subgrade |
| 321200 |
| 3.9B |
| Gradation and Asphalt Content |
| One per 1000 tons or Min. of 3 per Project |
| 321200 |
| 3.9C |
| Field Density Tests – Asphalt |
| One test for every 800 sq. yd. of pavement |
| 321204 |
| 3.4A |
| Compaction Tests – Road Base |
| One test for every 1000 sq. yd. of |
aggregate
| 321204 |
| 3.4A |
| Compaction Tests – Aggregate Base for Concrete Slabs and Asphalt Path |
| One test for every five family units, two tests for each group unit, one test for every 30 square yards of sidewalk and one test for every 60 square yard of asphalt path. |
| 329310 |
| 1.4B |
| Topsoil Analysis |
| One test per source |
| 328000 |
| 3.16 |
| Irrigation Pressure Testing |
| Until Passing |
SECTION F - Deliveries or Performance
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use ONE HUNDRED EIGHTY (180) calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)
Within _10_calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.
The maximum workweek that will be approved is to be negotiated if needed.
Contract Time and Winter Weather Shutdown
(a) The count of calendar days to be charged against contract time will begin on the calendar day established by the Contracting Officer's written notice to the Contractor to proceed with the work, and will continue through the date of completion less time between Suspensions and Resume Work Orders. When winter weather sets in and the continuation of work is impractical, upon written request by the Contractor, the Contracting Officer may authorize a total suspension, until winter weather has passed and work can proceed.
(b) During period of total suspension, emergency work or minor operations not affected by nor connected with the cause of suspension may be permitted by the Contracting Officer without charge against contract time.