Amendment 02 Site Visit Notes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 03.docx | DOCX document | |
| amendment 01.doc | DOC document | |
| Attachment 01 Specifications 05022011.doc | DOC document | |
| Attachment 04 General Decision Number UT20080076.mht | MHT file | |
| AG-84N8-S-11-0024.rtf | RTF text file | |
| Attachment 03 General Decision Number UT20080104.mht | MHT file | |
| Attachment 01Specifications.docm | DOCM document | |
| Attachment 02 Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| 6 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| 002 |
| 05/19/2001 |
| 6. ISSUED BY |
| CODE |
| 84N8 |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
| 84N8 |
U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.
Salt Lake City, UT 84119 U.S. Department of Agriculture – Forest Service Utah Acquisition Support Center 2222 W. 2300 S.
Salt Lake City, UT 84119
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
9B. DATED (SEE ITEM 11)
| X |
| 10A. MODIFICATION OF CONTRACT/ORDER NO. |
AG-84N8-S-11-0024
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
04/29/2011
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| (X) |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN |
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, X is required to sign this document and return 1_ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
This amendment is to incorporate the Site Visit note from May 13, 2011.
Solicitation response date is NOT extended and all other terms and conditions remain the same.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
Brian Wharton
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| /s/Brain Wharton |
| 05/19/2011 |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
AG-84N8-S-11-0024
Lucerne Campground Reconstruction Ashley National Forest
Site Visit Notes on May 13, 2011
Forest Service Representatives
| Jammie Lindsay, CO | USDA Forest Service | |
| Lance Valentine, COR | USDA Forest Service | |
| April McKeon, Inspector | USDA Forest Service | |
| Scott Bingham, COTR | USDA Forest Service |
Contractors Marlin Wright, Jwright John Arnold, Lewis & Lewis INC Dave Coyner Quality Paving Dueane Calvin, Synergy Construction, LLC Gregg Sorensen, Landscapes Unlimited/HCI Construction Gary Webb, GK Perry Construction/Ascent Construction Tim Baird, C.T.I.
Jerry Bublitz, EHC, LLC James Messa, JM Electrical Services Don Wang, ACCU Construction INC Corey Snyder, SCI INC Jim Jewell, C-2 Construction Stephanie Anderson, Eagle Feather Construction INC Jeff Vernon, Geary Construction Dan Flint, Hughes General Contractors Ken Kunz, Morton Electric INC Dennis Toone, E-Corp Gregg Chambers, Gregg Chambers & Sons LLC Scott Croft, Allstate Construction Randall Bradford, RB Construction & Concrete Bert Bradford, Bert Bradford Construction LLC Travis Wilson, WW Construction INC Sterling Stoddard, Edstrom Construction Doug Harletun, Landmark Company
Opening Instructions:
1. This is a construction project, therefore, Davis Bacon Wages does apply; certified payrolls will have to be submitted with payment requests. Two wages determination apply to this solicitation.
1. This is a Hubzone set-aside. Contract must be certified Hubzone in order to be awarded to.
1. Make sure you are registered and or CURRENT in CCR and ORCA.
1. Bid bond is required with each proposal.
1. Follow instruction in Section L when submitting.
1. Require 3 copies of both Technical and Financial proposal. Technical and Financial proposals should be submitted separately.
1. Evaluation of proposals based on criteria in Section M.
1. Closing date is May 31, 2011 – CO will upload notes and attendance list as an amendment to the solicitation shortly after this meeting.
1. Faxes will NOT be accepted.
1. If there are any questions asked at this meeting that representative cannot answer it will be addressed by the CO in the Site visit notes via Amend to the solicitation.
1. This project is ESTIMATED in the range of $1,000,000 - $5,000,000.
1. COR will be Lance Valentine
1. A 100% Payment/Performance Bond will be required 10 days of contract award.
Questions & Clarifications:
Q. Can personal property that is included in the required Demolition be recycled, sold, or given away (i.e. picnic shelters, concrete barriers, etc.) by the contractor?
A. The metal picnic shelters can be recycled. The concrete barriers can be recycled, sold, or given away.
Q. Is there lead-based paint on the shelters? If so, can they be sold for scrap metal and recycled?
A. The paint on the picnic shelters was tested for lead-based paint. The analysis showed that the paint on the picnic shelters is not lead-based paint. There are no environmental issues with either landfilling or recycling the picnic shelters.
Q. Is removal of concrete barriers around the Amphitheater part of the work?
A. No. Drawing DE1 and DE2 show the areas and items of demolition. The amphitheater parking area is to remain as is.
Q. Can the contractor use the existing hydrants in the campground for their supply of water for construction purposes rather than pumping directly from the reservoir?
A. No. The contractor shall not take water from the hydrants within the campground or the Lucerne Complex. Water for construction purposes is available by pumping directly from the reservoir per Section 000001.1.3.6. Pumping from the reservoir can occur in the vicinity of the irrigation barge with an access road down to the shore of the reservoir. The public use concrete boat ramp shall not be used for pumping from the reservoir.
Q. What is the location and limits of the temporary fence?
A. Section 000001.3.A.1 states in part that, “the Contractor shall construct a temporary fence with appropriate signing along the West side of Loop D, the North side of the Entrance Road, and at other locations necessary to keep the public out of the work area.” As further clarification, the fence along the North side of the Entrance Road shall extend to the east to a point directly across from Loop B.
Q. Is a SWPP plan required?
A. No. However a detailed Sediment and Erosion Control Plan is required in accordance with Section 023701.
Q. To clarify the comment made at the site visit concerning “tax exempt project” A. The contractor is responsible for all Federal, State, and local taxes associated with the contract performance. There is no tax exempt status for this project.
Q. Do the borrow sites need to be re-seeded and re-shaped or just re-shaped upon completion of the work?
A. It is not necessary to re-seed the borrow sites. Section 312010.3.4.C outlines the requirements for re-shaping the borrow sites.
Q. For the irrigation loop prints IR-2 thru IR-5 shows a # 12/19 and also a #14/3. Was this designed to have one cable each coming from the pump house all the way through Loop D, or is each loop getting its own set individually from the pump house? Can you tell me who the utility for the power is going to be?
A. The irrigation sheets (pages 61-69) show the locations for the different cables. Specifically there are 2 #12/19 cables that are for valve control, one in each direction from the control location, the #14/3 was called for remote pump control. The power utility company for this area is Bridger Valley Electric with offices in Lyman, WY.
Specification Revisions
I. Revise QC Table 014100-1 II. Section 024102 section 1.1 item C. change to: The work also includes scarifying and recontouring of the areas under and around removed structures.
III. Section 024102 section 3.5 item A. Delete “if required” IV. Section 312000 section 3.20 item D. 1c.) change to: Sidewalks:1 test for every 30 square yards of sidewalk.
TABLE 014100-1 (revised)
Item
Subsection Certification or Test Required
Frequency
| 033000 |
| 2.12 |
| Mixing and Delivery |
| Each Truck |
| 033000 |
| 3.12 |
| Concrete – Slump & Temperature |
| 1 per truck load |
| 033000 |
| 3.12 |
| Concrete – Composite |
| 1 test per 5 truck loads, min. 1 per day |
| 221100 |
| 3.2 |
| HDPE Pipe - Bent Strap Test |
| Once Daily |
| 221100 |
| 3.5 |
| Pressure and Leakage Test – Water Line |
| See Spec. |
| 221100 |
| 3.6 |
| Bacteriological Examination |
| After disinfection, before use |
| 312000 |
| 3.14C |
| Compaction Test – at Pipe Zone |
| One test – at each road crossing |
| 312000 |
| 3.14D |
| Compaction Test – above Pipe Zone |
| One test every other lift – at each road crossing |
| 312000 |
| 3.14I |
| Tracer Wire Conductivity Test |
| Until Passing |
| 312000 |
| 3.20D |
| Compaction Test – Exterior Concrete Slabs |
| See Spec. |
| 312225 |
| 3.11B |
| Moisture-Density Relationship |
| One Test for Each Soil Type Encountered |
| 312225 |
| 3.11B |
| Compaction – Subgrade |
| One test every 1000 sq. yd. of subgrade |
| 321200 |
| 3.9B |
| Gradation and Asphalt Content |
| One per 1000 tons or Min. of 3 per Project |
| 321200 |
| 3.9C |
| Field Density Tests – Asphalt |
| One test for every 800 sq. yd. of pavement |
| 321204 |
| 3.4A |
| Compaction Tests – Road Base |
| One test for every 1000 sq. yd. of |
aggregate
| 321204 |
| 3.4A |
| Compaction Tests – Aggregate Base for Concrete Slabs and Asphalt Path |
| One test for every five family units, two tests for each group unit, one test for every square yard of sidewalk and one test for every 60 square yard of asphalt path. |
| 329310 |
| 1.4B |
| Topsoil Analysis |
| One test per source |
| 328000 |
| 3.16 |
| Irrigation Pressure Testing |
| Until Passing |