Attach-01 Specifications

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Grand Mesa Visitor Center Water System Improvements

Grand Mesa Visitor Center Water System Improvements - Specifications

2017-05-09

CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 01 1000 – SUMMARY OF WORK

DIVISION 02 – EXISTING CONDITIONS

SECTION 02 4119 – SELECTIVE DEMOLITION

DIVISION 13 - SPECIAL CONSTRUCTION

SECTION 13 3460 - PRECAST CONCRETE UTILITY BUILDING

DIVISION 22 – PLUMBING

SECTION 22 0500 – BASIC PLUMBING MATERIALS AND METHODS

SECTION 22 1100 - TREATMENT BUILDING PLUMBING

SECTION 22 1119 – DISINFECTANT FEED EQUIPMENT

SECTION 22 1123 – HYDROPNEUMATIC PRESSURE TANK

SECTION 22 1124 - INDOOR POTABLE WATER RETENTION TANKS

SECTION 22 1199 – DISINFECTION OF WATER WORKS

DIVISION 26 - ELECTRIC

SECTION 26 0100 - GENERAL ELECTRICAL PROVISIONS

SECTION 26 0500 - BASIC ELECTRICAL MATERIALS AND METHODS

DIVISION 31 – EARTHWORK

SECTION 31 2317 – TRENCHING, BEDDING AND BACKFILL FOR UTILITIES

DIVISION 33 - UTILITIES

GRAND MESA VISITOR CENTER STORAGE TANK RELINING CONTENTS

SECTION 33 0920 - CONTROL AND INSTRUMENTATION

SECTION 33 1112 - WATER DISTRIBUTION

SECTION 33 1219 - WATER HYDRANTS

SECTION 33 2110 - GROUNDWATER SUPPLY WELLS

Grand Mesa Visitor Center Water System Improvements

Division 01 General Requirements

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 01 1000 - 1

SUMMARY OF WORK

SECTION 01 1000 - SUMMARY OF WORK

PART 1 - GENERAL

1.1. Summary

A. This project consists of construction of a drinking water treatment system and installation of approximately 2,500 feet of new buried water piping to serve the Grand

Mesa Visitor Center, Cobbett Campground and Ward Lake Campground. Other work items include replacement of an existing well pump and extension of the well casing height above ground.

B. Optional items include rehabilitation of a 2,000 gallon concrete water storage tank and repair or replacement of 11 campground water hydrants.

C. Optional items may be awarded at the time of the base contract subject to funds availability and other terms and conditions of this contract, or up to 6 months after award of the base items.

1.2. Location

A. This project is located at the Grand Mesa Visitor Center, Cobbett Campground and Ward

Lake Campground on the Grand Mesa National Forest. The project is approximately 15 miles north of Cedaredge, CO along Colorado Highway 65.

1.3. General Site Conditions and Weather

A. The elevation of the site is approximately 10,300 feet above mean sea level. During the summer, the site experiences large mosquito populations. During the winter, the site experiences heavy snowfall and extremely cold temperatures, with snow on the ground typically from November through July.

1.4. Use of Premises

A. Visitor Center Main Building and Restrooms: The Visitor Center is typically open to the public from late May through September, with expected average visitation of about 300 persons per day, and peak visitation of about 2,000 persons on popular days such as

Moose Day and Color Sunday. The restrooms will be open to the public until contract performance interrupts water flow to flush the toilets and urinal, at which point the restrooms will be closed to the public until the water flow can be resumed.

B. Pedestrian Hiking Trails in Work Area: The work area is in a popular recreation area, with sanctioned and unsanctioned pedestrian hiking trails in the area.

C. Cobbett Campground and Ward Lake Campground: The campgrounds in which work is to be performed will be open to campers from about June through October.

1.5. Contractor’s Responsibilities

A. Confine storage of materials to areas as approved by the CO.

B. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 01 1000 - 2

C. Preservation of Natural Features: Confines all operations to work limits of the project.

Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect existing trees and plants and root zones.

2. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with CO and remove agreed-on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.

1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the

Government.

2. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.

1.6. Work Restrictions

A. Smoking is not permitted within the Visitor Center buildings or within 25 feet (8 meters) of entrances, operable windows, or outdoor air intakes.

1.7. Field Verification

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.8. Cleaning of Equipment to Prevent Spread of Weeds and Disease

A. Construction equipment must be washed to remove seeds, plants, plant fragments and soil which may contain such material before it is brought onto National Forest lands.

B. Notify the CO at least 5 days before moving any construction equipment onto National

Forest System lands.

C. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest

System lands.

D. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.

1.9. Permits.

A. The Government will apply for approval from the Colorado Department of Public Health and Environment (CDPHE) to make modifications to the existing public drinking water system.

B. Special permits for electrical work or any other permits—including confined space permits as applicable—required by County, State, or Federal laws or regulations shall be obtained by the Contractor.

1.10. Camping

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 01 1000 - 3

A. With approval by the Grand Valley Ranger District, National Forest Service lands may be used by the Contractor to have one fully contained recreation vehicle which may remain at this site during the period of performance.

1.11. Disposal Site

A. The contractor shall dispose of materials left from the construction and any demolition operations off National Forest lands at an approved sanitary landfill.

PART 2 - DEFINITIONS OF ITEMS AND PAYMENT

2.1. DESCRIPTION

A. This section explains what is and what is not included in each pay item; the limits or cutoff points where one item ends and another begins; and basis of payment for work items listed in the Schedule of Items.

B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings

2.2. SCHEDULE OF ITEMS

A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items will be awarded based on available project funding. Note:

Optional Items may be awarded up to 6 months after award of base items.

Contractor must guarantee pricing for 6 months after award of base items.

B. Base Items (BI):

1. Base Item No. 1 - General Requirements/Mobilization

a. Payment: The contract lump sum price as shown in the Schedule of

Items includes all materials, equipment, labor and incidentals to perform work at the Grand Mesa Visitor Center and Cobbett and Ward

Lake Campgrounds.

b. Description: Mobilization. All preparatory work and operations necessary for the movement of personnel, equipment, supplies, bonding and incidentals to the project site; all quality control testing; all construction signing; any other work and operations that must be incurred prior to the beginning of work; and demobilization at the completion of work.

1) Measurement and payment: Payment will be made at the contract lump sum price.

2) Progress payments shall be made as follows:

a) When 5 percent or more of the original contract amount is earned from other base pay items (except

Base Pay Item No. 1), 50 percent of the amount of this

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 01 1000 - 4

base pay item or 2.5 percent of the original contract amount will be paid, whichever is less.

b) When 10 percent or more of the original contract amount is earned from other base pay items

(except Base Pay Item No. 1), 100 percent of the amount of this base pay item or 5 percent of the original contract amount will be paid, whichever is less.

c) Upon completion of all work on the project any unpaid amount for this item will be paid.

d) The total of all payments, including bonding, shall not exceed the original contract amount for this item.

2. Base Item No. 2 - Well Pump Replacement and Casing Extension

a. Payment: Lump Sum

b. Description: Includes all work associated with furnishing and installing the new well pump, performing the required yield tests and extending the well casing to 24" above the existing grade.

3. Base Item No. 3 - Utility Room Selective Demolition

a. Payment: Lump Sum

b. Description: Includes all work associated with removing or salvaging the water system components from the utility room indicated on the drawings.

4. Base Item No. 4 - Precast Concrete Utility Building

a. Payment: Lump Sum

b. Description: Includes all work associated with

1) Clearing, grubbing, grading, and providing compacted aggregate base course for the site on which the building will be placed

2) Furnishing and installing the building with electric breaker panel, lights, and receptacles

3) Does not include water or utility connections from outside of the building

5. Base Item No. 5 - Water Treatment System and Electrical Work

a. Payment: Lump Sum

b. Description: Includes supplying and installing the various water treatment components inside the treatment building, connecting the treatment building water and power to the main site supplies, and designing and implementing the controls and instrumentation describe in the specifications.

6. Base Item No. 6 - Waterline Installation

a. Payment: Unit price per linear foot of water pipe installed in the ground

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 01 1000 - 5

b. Description: Includes all staking and construction work associated with the waterline installation, including furnishing and installing all backfill materials, furnishing and installing all pipe, fittings, valves, valve boxes and appurtenances, including in the vicinity of the existing 2,000 gallon storage tank. Also includes testing and disinfection of installed lines.

C. Optional Items (OI):

1. Optional Item No. 7 - Campground Hydrant Faucet Installation

a. Payment: Unit price per hydrant.

b. Description: Includes all work associated with plumbing a faucet onto an existing campground hydrant stub.

c. This item will only be awarded if Optional Item 8 is NOT awarded.

2. Optional Item No. 8 - Campground Hydrant Complete Replacement

a. Payment: Unit price per hydrant.

b. Description: Includes all work associated with replacing a capped water campground water hydrant with a new hydrant, post, and curb box system.

c. This item will only be awarded if Optional Item 7 is NOT awarded.

3. Optional Item No. 9 - Existing Concrete Tank Rehabilitation

a. Payment: Lump Sum

b. Description: Includes all work and debris removal associated with cleaning the tank interior, roughing the interior walls in preparation for recoating, recoating, replacing the tank access ladder, and removal of old wiring in the tank.

4. Optional Item No. 10 - Precast Concrete Utility Building Insulation

a. Payment: Lump Sum

b. Description: Includes all work and materials involved in insulating building walls and roof as described on drawings.

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 1000

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS

Division 02 Existing Conditions

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 02 4119 - 1

SELECTIVE STRUCTURE DEMOLITION

SECTION 02 4119 – SELECTIVE DEMOLITION

PART 1 – GENERAL

1.1. SUMMARY

A. This Section includes the following:

1. Removing selected below-grade construction.

2. Disconnecting, capping or sealing, and abandoning in-place selected site utilities.

3. Salvaging items for reuse by Government.

1.2. DEFINITIONS

A. Demolish: Completely remove and legally dispose of off-site.

B. Recycle: Recovery of demolition waste for subsequent processing in preparation for reuse.

C. Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Government ready for reuse. Include fasteners or brackets needed for reattachment elsewhere.

1.3. MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

PART 2 – PRODUCTS

2.1. REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

2. Use materials whose installed performance equals or surpasses that of existing materials.

PART 3 – EXECUTION

3.1. EXAMINATION

A. Inventory and record the condition of items to be removed and salvaged.

3.2. PREPARATION

A. Existing Utilities: Locate, identify, disconnect, and seal or cap off indicated utilities serving buildings and structures to be demolished.

1. Government will arrange to shut off indicated utilities when requested by

Contractor.

B. Removed, Salvaged and Reinstalled Items: Comply with the following:

1. Clean salvaged items of dirt and demolition debris.

2. Store items in a secure area until delivery to Government.

3. Protect items from damage during transport and storage.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 02 4119 - 2

SELECTIVE STRUCTURE DEMOLITION

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

3.3. DEMOLITION BY MECHANICAL MEANS

A. Existing Utilities: Abandon unnecessary existing utilities and below-grade utility structures. Cut back abandoned pipes to at least 1’ below grade.

3.4. SITE RESTORATION

A. Below-Grade Areas: Completely fill below-grade areas and voids resulting from structure demolition operations according to backfill requirements in Section 02 4160.

B. Clean area of debris caused by demolition operations.

3.5. SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

1. Neatly cut openings and holes plumb, square, and true to dimensions required.

Use cutting methods least likely to damage construction to remain or adjoining construction.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Dispose of Demolished items and materials promptly.

B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be re-moved to a suitable, protected storage location during selective demolition [and cleaned] and reinstalled in their original locations after selective demolition operations are complete.

END OF SECTION 02 4119

Division 7 - Thermal and Moisture Protection

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 07 1613 - 1

POLYMER MODIFIED CEMENT WATERPROOFING

SECTION 07 1613 - POLYMER MODIFIED CEMENT WATERPROOFING - (Option

Item)

PART 1 - GENERAL

1.1. SUMMARY

A. This section includes waterproof coating to interior of existing 2,000 gallon concrete water storage tank.

B. This section also includes preparing the tank interior surface for coating, replacement of the tank interior access ladder and removal of miscellaneous wiring from the tank.

1.2. QUALITY CONTROL

A. Provide materials that are ANSI / NSF 61 approved for contact with potable water.

B. Installer Qualifications:

1. Acceptable to manufacturer with documented experience on at least 2 projects of similar nature in past 2 years and/or training provided by the product manufacturer.

1.3. SUBMITTALS

A. Manufacturer's product data showing compliance with this specification and showing the product (or products) is recommend for this application.

1.4. PROJECT CONDITIONS

A. Maintain surf aces to be waterproofed/lined and surrounding air temperature at not less than 40°F (5°C) for at least 48 hours before, during and after application of coating.

B. Do not apply materials to frozen or frost-filled surfaces.

C. Exercise caution when temperatures exceed 86°F (30°C). It may be necessary to apply waterproofing/lining during times when the sun is not at its strongest (i.e. early morning, evening or night).

PART 2 - PRODUCTS

2.1. COATINGS

A. Acceptible products include:

1. Aquafin 1-K

2. Sherwin Williams Macropoxy 646

3. Other products will be considered if submitted to the CO 10 days prior to the offer due date.

2.2. ACCESS LADDER

A. Provide a ladder matching existing ladder construction but coated to prevent rust.

PART 3 - EXECUTION

3.1. GENERAL

A. Apply materials according to manufacturer's recommendation.

3.2. EXAMINATION

A. Examine substrates and adjoining construction, and conditions under which Work is to be installed. Do not proceed with Work until unsatisfactory conditions are corrected.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 07 1613 - 2

POLYMER MODIFIED CEMENT WATERPROOFING

B. Verify the following substrate conditions before application of waterproof lining:

1. That substrate condition is satisfactory and in accordance with manufacturer's instructions.

2. That concrete surfaces have open pores and wood float finish on horizontal surfaces.

3. That concrete surfaces are free of voids, spalled areas, loose aggregate and sharp protrusions, and with no coarse aggregate visible.

4. That curing compounds or surface hardeners incompatible with waterproof lining have not been used on concrete.

3.3. PREPARATION

A. Protect adjacent surfaces not designated to receive waterproof lining.

B. Substrate preparation:

1. Remove remaining concrete fins and projections, and general surface dirt.

2. Remove grease, oil and other contaminants. Use high-pressure water blasting, wet or dry sand blasting, or other methods recommended by waterproofing manufacturer to produce surfaces suitable for application of waterproofing.

3. Follow manufacturer's instructions to clean and prepare surfaces.

4. Repair cracks, honeycombs, unsound concrete and weak mortar joints.

5. Roughen form tie holes.

C. Rinse surfaces to be lined/waterproofed several times so that the concrete is thoroughly saturated. Surfaces shall be moist but not wet when waterproofing system is applied.

Remove any surface water on horizontal surfaces.

3.4. CURING

A. Protect exposed waterproofed/lined surfaces from premature drying out with polyethylene sheeting. Do not use burlap as this may stain the white surface.

B. Moisture cure exposed waterproofed/lined surfaces as per manufacturer's instructions.

END OF SECTION 07 1613

Division 13 Special Construction

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 1

PRECAST CONCRETE UTILITY BUILDING

SECTION 13 3460 - PRECAST CONCRETE UTILITY BUILDING

PART 1 – GENERAL

1.1. DESCRIPTION

A. The work of this section consists of preparing a surface at the site, prefabrication, on-site delivery, off loading and placement of precast concrete buildings.

B. This section includes specifications for the construction of precast concrete utility buildings. Examples of acceptable floor plans and exterior finishes are shown in the attached drawings.

C. Contractor shall coordinate order with manufacturer to include electric lighting for building.

D. Contractor shall coordinate order with manufacturer to ensure electrical and plumbing sleeves are installed as shown on the drawings.

1.2. OPTION ITEM: INSULATION

A. If Option Item 10 is awarded, provide a minimum of R-10 insulation for walls and doors and R-19 for ceiling.

1.3. DESIGN REQUIREMENTS

A. Structural Live Loads – Buildings shall be designed to meet the following load requirements in accordance with the International Building Code (IBC).

1. Snow Load – 250 psf

2. Wind Load – 120 mph (fastest mile) or 140 mph (3-second gust), Exposure C

3. Earthquake – Maximum considered ground motion shall be 175 (0.2 second spectral response acceleration) and 125 (1.0 second spectral response acceleration), Site Class D. Design requirements associated with Uniform

Building Code (UBC) Zone 4 are acceptable.

4. Floor – 50 psf

B. Other Loads

1. Contractor is responsible for adding reinforcement as needed to facilitate handling, assembling building components and transporting without incurring structural damage or cracking of the building components.

C. Standard Design Options:

1. Roof Texture – simulate ribbed metal

2. Wall Exterior Textures – Simulated barn wood, lap siding or board and batten

3. Screen Options – Full screen, open screen and through screen

4. Door size: Two (2) 3’-0” x 6’-8” doors

D. Tolerances

1. Precast concrete panels shall be cast within ¼” of dimensions shown on shop drawings.

1.4. QUALITY ASSURANCE

A. Reference Standards

1. ASTM C33 – Concrete Aggregates

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 2

2. ASTM C39 – Method of Test for Compressive Strength of Cylindrical Concrete

Specimens

3. ASTM C143 – Method of Test for Slump of Concrete

4. ASTM C150 – Standard Specification for Portland Cement

5. ASTM C192 – Method of Making and Curing Test Specimens in the Laboratory

6. ASTM C 595 Standard Specification for Blended Hydraulic Cements

7. ASTM C 618 Standard Specification for Coal Fly Ash and Raw or Calcined Natural

Pozzolan for Use in Concrete

8. ASTM 1211.1 – Recommended Practice for Selecting Proportions for Normal and Heavyweight Concrete.

9. PCI MNL 116 – Quality Control for Plants and Production of Precast Prestressed

Concrete Products

10. AISC - Specification for the Design, Fabrication and Erection of Structural

Steel Buildings

11. AWS D1.1 – Structural Welding Code

B. Minimum Contractor Requirements

1. Precast concrete manufacturing plant shall be Precast/Prestressed Concrete

Institute (PCI) certified.

2. Welders shall be currently qualified according to AWS D1.1.

C. Testing

1. The Contractor shall be responsible for all sampling and concrete testing.

2. Sampling and testing shall be conducted by an independent testing laboratory, unless otherwise approved by the Contracting Officer.

3. All testing shall be performed by qualified individuals who have been certified

ACI Technician Grade 1.

4. Sampling shall be in accordance with ASTM C172.

5. The following test shall be performed for first batch poured each day.

a. Slump, ASTM C143

b. Air content, ASTM C231

c. Compressive strength, ASTM C39

d. 1 cylinder at 7 days

e. 1 cylinder at 28 days

f. Contractor shall provide copies of test results to the Contracting Officer upon request.

1.5. SUBMITTALS

A. Technical Proposal

1. Shop Drawings

a. Submit shop drawings for each proposed model. Indicate standard options and any additional cost options.

b. Drawings must show the exact model floor plan, and the size and location of all vents, screens, doors, etc.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 3

2. Specifications and Installation Manual

a. Provide one copy of the specifications and installation manual for each proposed model.

3. Provide Manufacturer’s Literature for the following:

a. Door, louvered door vent (if applicable), and door hardware

b. Paint - interior

c. Caulk, grout, and adhesive

d. Concrete form liners

e. Concrete color additive and stain including color chips, curing compound and sealer

f. Vents

4. Concrete

a. Submit aggregate test results, concrete mix design including all concrete additives, and name of concrete supplier and aggregate source. All tests must have been completed within 24 months of the submittal of the technical proposal.

B. Post-Award

1. Design calculations and final drawings shall be stamped by a professional engineer and submitted to the Contracting Officer upon request. The professional engineer must be registered in the United States.

2. Concrete Mix Requirements

a. Provide 28-day compressive strength test results within 35 days following manufacturing of the first building upon request.

b. If concrete supplier, aggregate source, or any additives change at any time during manufacturing, submit new concrete information to the

Contracting Officer for approval.

3. Colored and Textured Concrete

a. Submit one colored concrete sample for each color and texture of exterior building surface, accompanied by manufacturer’s literature for color additive and form liner, to the Contracting Officer for approval at least 30 days prior to the first anticipated colored concrete placement.

b. Minimum sample size shall be 12” x 12” x 1”.

c. The Contracting Officer may waive sample requirement if Contractor can show evidence of successful work with same color additive and aggregates as proposed for this project. Evidence must be a completed installation accessible to the Contracting Officer or designated representative at least 30 days before first placement of colored concrete is anticipated.

1.6. DELIVERY AND HANDLING

A. OFFLOADING AND ASSEMBLY

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 4

1. The Contractor is responsible for unloading and assembling all components of the precast concrete utility building.

2. The Contractor shall notify the Ordering Unit Contracting Officer 10 days prior to the anticipated delivery date and 2 days (48 hours) prior to the exact date of delivery.

3. Deliveries shall only be made between the hours of 8:00 a.m. and 4:30 p.m.

(local time), Monday through Friday, unless otherwise approved by the Ordering

Unit Contracting Officer.

1.7. CLOSEOUT SUBMITTALS

A. Operation and Maintenance Manual

1. Provide three copies of the operation and maintenance manual to the Ordering

Unit Contracting Officer at the time of delivery.

2. Operation and Maintenance Manual should include, but not limited to, recommended types of cleaners and cleaning tools that should be used.

1.8. WARRANTY

A. Special Warranty on Building and Accessories: Written warranty, signed by Contractor agreeing to repair or replace building and/or accessories that fail or are damaged within the specified warranty period as a result of normal use and/or typical weather conditions. Items in this item include precast concrete building in its entirety, and all caulking, sealant, grout, adhesive, mortar, primer, paint, penetrating stain, concrete sealer, wall vents, doors, locksets, deadbolts, door louvers, door sweep and door stops.

1. Warranty Period: 3 years from date of Acceptance

PART 2 – PRODUCTS

2.1. PRECAST CONCRETE FORMWORK

A. Forms shall be constructed of plywood, lumber, or steel sheets or plates free of defects, which could cause blemishes. Forms must be removable without injuring the concrete and must be constructed to maintain tolerances between mating surfaces of buildings components.

B. Form liners shall be used to provide the desired exterior appearance.

1. Form liners for all exterior surfaces shall be approved by the Contracting Officer prior to use.

C. Form coating shall be non-staining type that will not leave residual matter on surface of concrete or adversely affect proper bonding of subsequent coatings, caulking, grout, or adhesive applied to concrete surfaces.

1. Use form release agent or coating as recommended by manufacturer of the form liner.

2. Coatings containing mineral oils or other nondrying ingredients are not permitted.

2.2. CONCRETE REINFORCEMENT

A. Reinforcing steel shall meet the requirements of ASTM A615, grade 60.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 5

B. Welded wire fabric shall meet the requirements of ASTM A185.

C. Pre-stress strand, if Contactor elects to use it to facilitate manufacturing, shall meet the requirements of ASTM A416, Grade 270.

D. All reinforcement shall be new, free from dirt, oil, paint, grease, loose mill scale, and loose or thick rust when placed.

2.3. CONCRETE MIX REQUIREMENTS

A. Concrete shall be supplied by a ready-mix or precast concrete products firm regularly engaged in the business.

B. Cement, aggregate, and water shall be proportioned to obtain concrete with good workability.

C. Do not use materials containing frost or lumps of frozen materials.

D. Concrete shall meet the following requirements:

1. Aggregate size shall be Course No. 67 or fine aggregate (see Table 2, ASTM C33, or Table 1, ASTM C33) as approved by Contracting Officer.

2. Minimum cement content: 6.5 sacks per cubic yard.

3. Cement type: ASTM C150 Type II, IIA, III, V (sulfate resistant) or ASTM C-595

Type IP (sulfate resistant).

4. Maximum water-cement ratio: 0.45.

5. Slump: 3 to 5 inches by ASTM C143.

6. Air content: 4.0 to 7.0 percent by ASTM C231.

7. Minimum concrete strength: 4,500 psi at 28 days.

8. Water shall be potable.

9. Admixtures:

a. Air-entrainment, ASTM C260.

b. Water reducing agent, ASTM C494, Type A.

c. Use of other admixtures is subject to approval by the Contracting

Officer.

E. The Contractor shall furnish, with each truckload or batch, a certificate showing:

1. Amount (by weight) – Cement in each load

2. Amount (by weight) – Fine aggregate in each load

3. Amount (by weight) – Coarse aggregate in each load

4. Amount (by weight) – Water in each load

5. Amount (by weight) – Color additive

6. Time of day cement was added to the aggregate and water.

7. Certificates shall be available for each building produced and provided to the

Contracting Officer upon request.

2.4. COLORED CONCRETE

A. The following components shall be precast with integrally colored concrete:

1. Roof panels

2. Wall and screen panels

B. Color additive shall conform to ASTM C979.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 6

1. The same brand and type of color additive shall be used throughout the manufacturing process.

2. All ingredients shall be weighed and be mixed adequately to ensure uniform dispersion of the color.

2.5. CONCRETE PANEL THICKNESS

A. Minimum thickness of concrete panels shall be as indicated.

1. Floor and porch slabs - 5” if reinforcement steel is prestressed or post tensioned or 6” without prestressed or post tensioning reinforcement.

2. Vertical walls and screens - 4” for uniform panels or as shown below for tapered panels.

Top Mid-Height Bottom

3 inches 4 inches 5 inches

3 ½ inches 4 inches 4 ½ inches

3. Roof slab – 5”

2.6. CONCRETE CURING COMPOUND

A. Curing compound shall be colorless, complying with ASTM C-309, type I or I-D.

2.7. STRUCTURAL STEEL

A. Steel angles and plate connectors, ASTM A36

B. Filler metals for welding: ASTM A233, E70XX Series welding electrodes.

2.8. CAULKING, SEALANT, GROUT, ADHESIVE AND MORTAR

A. Caulking and sealant shall remain flexible and non-sag at temperatures from - 50° to +

140° Fahrenheit.

1. Exterior joints at roof ridge, roof/wall connection, and wall panel joints: 100% silicone caulk, clear or colored to match concrete, GE Silicone II, 800-626-2000, or approved equal.

2. Interior joints: Paintable Latex Caulk, GE Speedpaint 35-Year Siliconized Acrylic

Latex caulk, 800-626-2000, or approved equal.

B. Grout shall be non-shrink type and shall match color of surrounding concrete as nearly as possible.

C. Epoxy concrete adhesive shall be two component, rigid, non-sag gel adhesive for bonding to dry or damp surfaces, moisture insensitive. Color to match surrounding concrete as nearly as possible.

D. Portland cement mortar shall consist of one part Portland cement, three parts sand, and enough water to make a workable mixture. Bonding agent may be added to mixture in lieu of separate application of adhesive to panel.

2.9. CONCRETE PAINT AND PIGMENTED SEALER

A. Paint, pigmented sealer, and accessory materials shall conform to Federal Specifications or be similar “top-of-the-line” products of the manufacturers listed below. The

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 7

Government reserves the right to reject “top-of-the-line” products, which in its opinion are not comparable to the Federal Specification requirements.

1. Products used shall not contain more than 0.06 percent (six hundredths of one percent) by weight of lead.

B. Exterior concrete surfaces

1. Walls and roof

a. Water-based, acrylic, penetrating pigmented sealer with water repellent properties, same color as the walls or roof, followed by a clear acrylic anti-graffiti sealer.

1) Canyon Tone Stain “W” as manufactured by United Coatings, 800-541-4383, or approved equal.

2. Concrete porch slab

a. Clear acrylic sealer.

2.10. CONCRETE EXTERIOR SURFACE SEALER

A. Weatherproofing sealer

1. Clear, water based penetrating sealer with water repellent and graffiti resistant properties.

a. Acrysheen as manufactured by United Coatings, 800-541-4383, or approved equal.

2.11. WALL VENTS

A. Frames shall be C3 x 4.1 channel steel.

B. Louver shall be equipped with a lever to open and close them.

C. Each vent shall have an exterior non-corrodible stainless steel 24 mesh screen.

1. Mesh wire diameter: 0.014 inches +/- 0.005 inches

2. Mesh opening size: 0.0277 inches

3. Vendors include TWP <twpinc.com> and Grainger <grainger.com>

2.12. STEEL DOORS

A. Doors

1. Flush panel type, 1-3/4-inch thick, minimum 16 gauge prime-coated steel reinforced-core door, with minimum 20 gauge internal stiffeners and fiberglass insulation, 747 Series, as manufactured by Curries Company, 800-377-3948, or approved equal.

B. Door Frames

1. Door frames, shall be knock-down or welded type, single rabbet, minimum 16 gauge galvanized prime-coated steel. Width to suit wall thickness, as manufactured by Curries Company, 800-377-3948, or approved equal.

2. Provide three rubber door silencers on latch side of frame.

C. Door Frame Anchors

1. Provide three anchors per jamb located approximately at same level as hinge locations.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 8

2. Use anchor type suitable for fastening to precast concrete and designed for future removal of frame.

3. Anchors may be omitted if frame is cast in panel.

D. Door Hinges

1. Door hinges shall be 3 per door, 4-1/2” x 4-1/2”, U.S. 26D finish (dull chrome) with adjustable tension (adjusted to a 5 lb maximum pull) and automatic closing as manufactured by the Stanley Company, 800-337-4393, or approved equal.

E. Lockset

1. ANSI A156.2 Series 4000, Grade 1 cylindrical lockset for exterior door.

2. Lever handle inside and outside.

3. Either handle operates latch unless outside handle is locked by push-button inside.

4. Push-button automatically releases when inside lever handle is turned or door is closed.

5. Emergency slot on exterior so door can be unlocked from outside with a coin, screwdriver, etc.

6. Inside lever handle always active.

7. U.S. 26D finish (dull chrome).

8. Model No. 5402LN as manufactured by Yale Security Group, 800-438-1951, or approved equal.

F. Deadbolt

1. Mortised type, operated by key from outside only, which will receive a No.

1152, 1-1/8”, 5-pin cylinder as manufactured by Yale Security Group, 800-438-

1951, or approved equal.

2. If provided by the Forest Service, install Government-provided cylinder.

G. Door sweep shall be provided at bottom of door and shall be an adjustable brush type.

H. Door Stop

1. Door stop shall have a cast metal base, U.S. 26D finish, with convex gray rubber

2 3/8” diameter bumper with a 1” projection, suitable for installation on concrete.

PART 3 – EXECUTION

3.1. SITE PREPARATION

A. Materials:

1. Bedding material to be sand or 3/8” minus crushed or screened aggregate.

B. Location: It is the responsibility of the contractor to:

1. Provide exact location by stakes or other approved method.

2. Provide clear and level site free of overhead and/or underground obstructions.

3. Provide access to the site for truck delivery and sufficient area for the crane to install and the equipment to perform the contract requirements.

C. Grading and Compaction:

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 9

1. The back of the building should be slightly higher than the front to allow water to freely drain out of the room.

2. Compact the natural ground with a minimum of three passes with a whacker-type mechanical compactor or equivalent.

3. Install sand or aggregate bedding material for leveling course. Compact leveling course with one pass with a whacker-type mechanical tamper or equivalent.

Grade leveling course so there will be no high spots in the middle. Compact with a second pass with a whacker or approved equivalent tamper.

4. Backfill around structure. Use excavated material for backfill except that rocks larger than six inches of the exterior vault walls.

3.2. CONCRETE FORMWORK

A. Support and brace forms sufficiently to prevent distortion of forms due to pressure of the concrete during concrete placement, vibrating of concrete, and curing.

B. Vertical grooves in form liner pattern shall be continuous except for openings for doors, windows, and vents.

1. Horizontal butt joints between form liner panels will not be allowed.

2. Vertical butt joints between form liner panels shall be made at vertical groove in liner pattern except at outside corners.

3. Vertical grooves in form liner pattern shall be arranged so that there is equal space between vertical window or doorframe edges and the adjacent vertical grooves at each opening.

C. Form ties will not be allowed.

D. Remove all snow, ice, dirt, sawdust, shavings, or other debris within the forms before placing concrete.

3.3. REMOVAL OF FORMS

A. Contractor shall assume all responsibility for determining when to remove the concrete components from the forms without causing structural damage to the components.

Buildings constructed with damaged components will be rejected.

3.4. REUSE AND COATING OF FORMS AND FORM LINERS

A. Thoroughly clean forms and form liners before each use.

B. Apply form coating and form release agent on all forms and form liners in accordance with the manufacturer’s recommendations.

3.5. CONCRETE REINFORCEMENT

A. Detail reinforcement in accordance with ACI 318.

B. Steel reinforcement shall be centered in the cross-section area of the walls and shall have at least one inch of concrete cover on the under surface of roof and floor. Provide diagonal reinforcement at openings.

C. Accurately place and adequately support steel reinforcing or strand in final position prior to starting placement of concrete. The maximum allowable variation for center-to-center spacing of reinforcing steel is ½ inch.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 10

D. Use full lengths of reinforcing steel whenever possible and keep the number of splices to a minimum. When splices are necessary on long runs, splices shall be alternated from opposite sides of the component for adjacent steel bars. Lap bars No. 4 or smaller, a minimum of 12 inches. Lap bars larger than No. 4, a minimum of 24 bar diameters.

E. Bend bars cold unless otherwise approved by the Contracting Officer. No bars partially embedded in concrete shall be field bent except as approved by the Contracting Officer.

3.6. COLD WEATHER CONCRETE

A. Cold weather concrete placement shall be in accordance with ACI 306.

B. Do not place concrete if ambient temperature is expected to be below 35°F during the curing period unless heating is provided to maintain the concrete surface temperature of at least 45°F.

3.7. HOT WEATHER CONCRETE

A. The temperature of the concrete shall not exceed 80°F at time of placement, and when the ambient temperature reaches 90°F, the concrete shall be protected with moist covering or other methods approved by the Contracting Officer.

3.8. MIXING AND DELIVERY OF READY MIX CONCRETE

A. Mixing and delivery shall be accomplished in accordance with ASTM C94, sections 9, 10, and 11 as appropriate for manufacturer.

B. Aggregate and water will be adjusted to compensate for differences in the saturated surface-dry condition.

3.9. PLACING AND CONSOLIDATING CONCRETE

A. The Contracting Officer must be given the opportunity to inspect forms after placement of reinforcing steel in forms and before placement of concrete, when requested.

B. Concrete shall be discharged as soon as possible after mixing and time shall not exceed

30 minutes.

C. Avoid segregation. Place in layers not more than 24 inches deep. Do not move concrete with vibrators or tampers.

D. Consolidate concrete with suitable mechanical vibrators operating within the concrete or attached to steel forms. Vibrate at any point sufficiently to accomplish compaction, but do not prolong to a point where segregation occurs.

E. Floor of building shall be one-piece to prevent separation of panels as a result of freeze/thaw.

3.10. FINISHING CONCRETE

A. Interior Floor and Exterior Slab: Strike flush to within 1/8-inch variation in 6 feet. Float and trowel slabs smooth until no marks remain. Apply a final light broom finish to interior and exterior slabs. Slope interior floor to drain toward door way. Slope shall not exceed 2%.

B. Interior Wall Surfaces, Interior Screen Wall Surfaces, and Ceiling:

1. Finish shall be that provided by smooth steel form, or smooth trowel finish with no trowel marks.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 11

2. All lifting points on screens shall be on panel edge. Plug with bolts or caulking after erection.

C. Exterior Textured Surfaces:

1. Building Walls and Exterior Screen Walls

a. Finish shall be as indicated on the delivery order using an approved form liner.

2. Roof Panels

a. All exterior surfaces of the roof panels shall be as indicated on the delivery order using an approved form liner. The underside of the overhang shall have a smooth finish.

D. Cracks and Patching:

1. Cracks in concrete components caused by contractor fabrication, shrinkage during curing, handling, shipping, and installation shall be cause for rejection if the Government determines that the crack affects the serviceability or structural integrity of the component.

2. Fill small holes, depressions, and air or rock pockets in all surfaces with non-shrink Portland cement based patching material while concrete is still green and within one day of form removal. Patch shall match the color, finish, and texture of surrounding surface.

3. Patching will not be allowed on any component with holes, ships, or exposed reinforcement totaling more than 18 cubic inches or with any defects more than

2 inches deep. Those components will be rejected and must be replaced at

Contractor’s expense.

3.11. CURING AND HARDENING CONCRETE

A. Keep all concrete surfaces wet for at least six days after being placed. Acceptable methods include ponding, wet burlap, curing paper, plastic sheets, and membrane curing compound. Other methods are subject to the approval of the Contracting

Officer.

3.12. STRUCTURAL JOINTS

A. Joining details other than those described below will not be allowed unless approved by the Contracting Officer prior to manufacture of the buildings.

B. Wall components shall be joined together with epoxy concrete adhesive and two welded plate pairs at each joint. Each weld plate shall be a minimum of 6 inches long and located one pair in the top quarter and one pair in the bottom quarter of the seam.

Weld plates shall be anchored into concrete panels and welded together with a continuous weld. Welds shall be thoroughly cleaned prior to application of caulk or paint. Adhesive shall be applied for the entire length of the seam. Seal interior seams with paintable caulk. Seal exterior joints with caulk to match building color or clear.

Linseed oil shall be applied under silicone sealant on brown integrally colored components only, where such treatment is necessary to prevent brown color from appearing pinkish.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 12

C. Walls and roof shall be joined with weld plates, minimum 2 ½” x 5” at each building corner. Where the Contracting Officer determines that the joint between wall panels and the joint between walls and roof shall be gas-tight, seal with silicone caulk. Where the joint between the walls and roof is not true enough to prevent point loading, the joint shall be grouted with approved rigid non-shrink grout that distributes the weight of the roof evenly around the perimeter of the building walls.

D. The joint between the floor slab and walls shall be joined together with epoxy concrete adhesive and two weld plates pair for each wall component, one near each end of each wall panel, or each corner on each side, whichever is greater. Each weld plate shall be a minimum of 6 inches long. Weld plates shall be anchored into concrete panels and welded together with a continuous weld. Adhesive shall be applied for the entire length of the seam. Grout formed keyway to provide smooth cove between walls and floor.

3.13. PAINTING AND STAINING

A. Apply materials in strict accordance with manufacturer’s recommendations.

B. Examine work to ensure all surfaces are properly prepared to receive finish.

1. Allow a minimum of 14 days curing time for concrete before paints are applied to concrete. Allow longer curing time when recommended by paint manufacturer.

2. If needed to insure uniform application, prepare concrete surface for application of paints by acid etching with a 30 percent solution of hydrochloric acid. Flush with water and allow to thoroughly dry.

C. Painting shall NOT be done under the following condition:

1. Outside in cold, frosty, foggy, or damp weather.

2. In winter, unless temperature is 50°F or over and surfaces are dry and hard.

3. In dusty areas.

D. Apply coats, additional to those shown in the Schedule of Finishes, when undercoats or other conditions show through final coat of paint, until paint film is of uniform finish, color, and appearance.

E. Gray concrete epoxy paint on the floor shall also cover the cove at the junction between wall and floor. The line between the gray floor and the white wall shall be straight and parallel to the floor.

F. Schedule of Finishes:

1. Metalwork: Steel doors, door vents and frames, window frames and roof posts.

a. One coat metal primer.

b. Two coats enamel.

2. Interior concrete surfaces

a. Walls and ceiling of building: 1 coat latex block filler and minimum 2 coats paint/pigmented sealer. Pigmented sealer shall be followed by 1 coat of clear sealer.

b. Interior floor: Primer coat and minimum 2 coats of epoxy paint.

3. Exterior slab: 1 coat of clear penetrating sealer.

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 13

4. Exterior surfaces of building walls, roof, and screens, which will not be painted:

2 coats stain followed by 1 coat sealer.

a. Seal colored concrete as recommended by the manufacturer of the concrete color, if different from above.

G. Cleanup: Repair all defects and remove all paint spatters, etc.

H. Protect interior painted surfaces from direct exposure to sunlight and weather during manufacture, assembly, and installation.

3.14. METAL DOORS AND FRAMES

A. Install steel door and frame in accordance with manufacturer’s recommendations. Fit-door accurately in frame. Mount louvers on door, if required, with cadmium-or zinc-plated corrosion resistant Phillips head metal screws

B. Install hardware in accordance with hardware manufacturer’s instructions after finish paintwork is completed. Install a sweep on bottom of door and adjust so it contacts the floor when door is closed. Install door bumper on vestibule wall to meet door handle.

C. Adjust hinge tension after building is installed so that the maximum force necessary for pushing or pulling the door open is 5 pounds and the door takes at least three seconds to move from 70 degrees open to within three inches of the latch. Verify smooth operations of door and hardware. Adjust as necessary to provide smooth operation and required hinge tension.

END OF SECTION 13 3460

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 13 3460 - 14

Division 22 Plumbing

GRAND MESA VISITOR CENTER WATER SYSTEM IMPROVEMENTS 22 0500 - 1

BASIC PLUMBING MATERIALS AND METHODS

Section 22 0500 – BASIC PLUMBING MATERIALS AND METHODS

PART 1 – GENERAL

1.1. SUMMARY

A. This Section includes the following basic mechanical materials and methods to complement other Division 22 Sections.

1. Piping materials and installation instructions common to most piping systems.

2. Installation requirements common to equipment specification sections.

B. Pipe and pipe fitting materials are specified in Section 22 1100 Treatment Building

Plumbing.

1.2. QUALITY ASSURANCE

A. Comply with ASME A13.1 for lettering size, length of color field, colors, and viewing angles of identification devices.

B. Equipment Selection: Equipment of higher electrical characteristics, physical dimensions, capacities, and ratings may be furnished provided such proposed equipment is approved by Contracting Officer (CO) and connecting mechanical and electrical services, circuit breakers, conduit, motors, bases, and equipment spaces are increased. If minimum energy ratings or efficiencies of equipment are specified, equipment must meet design and commissioning requirements

1.3. DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and prevent entrance of dirt, debris, and moisture.

B. Protect stored pipes…