Prebid Questions and Clarifications.pdf
PDF 13 KB Posted
- Solicitation number
- AG-82B1-S-10-0409
About this file
Prebid Questions and Clarifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| List of Attendees.xlsx | XLSX spreadsheet | |
| Hunter_SPS.docx | DOCX document | |
| SF 1442.PDF | ||
| Hunter_specs.doc | DOC document | |
| AG-82B1-S-10-0409.pdf | ||
| Exp. Qstnr.pdf | ||
| Wage Determination.txt | TXT text file | |
| HUNTER_DRAWINGS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hunter Prebid Meeting –Questions or Points of Clarification
When is the bid opening date? - Bid opening date for this project is July 8, 2010 @ 2:00
PM
Is the liquidated damages clause in this contract? – There are no liquidated damages included.
Do the qualification letters need to be sent in ahead of time or can they accompany the bids? - Complete experience questionnaires with references attached and submit with your bid package.
Pointed out that the contract addresses the fact that there will be approx. 1,200 cys of excess excavation (Project Notes – sheet 4 of 61). Stated that once the construction surveying and staking has been completed that I would like to evaluate the information and see if we couldn’t reduce the volume of excess material.
We talked about the timing of work on this project and I stated that I would like to see the construction surveying and staking completed this year but after that it would be up to the contractor whether they did anything in addition to that this construction season.