amendment3 for Delay of Bids and Summit Pit_operations.docx
DOCX document 12 KB Posted
- Attached to
- Road Construction Federal contract opportunity
- Solicitation number
- AG-82B1-S-10-0288
About this file
Attachment to Amend 003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| amend 004 0288 signed.pdf | ||
| amendment for Blasting amend 004.docx | DOCX document | |
| amend003.0288.signedpdf.pdf | ||
| amend01 signedpdf.pdf | ||
| amend 002 0288.pdf | ||
| Attach Amend 01.docx | DOCX document | |
| amend 002 0288.pdf | ||
| fire precautions.doc | DOC document | |
| AG-82B1-S-10-0288.doc | DOC document | |
| Wage Determination | — | |
| WARREN WAGON SHT 1 - 22.pdf | ||
| FSSS FP-03 WARRENWAGONROAD FINAL.pdf | ||
| Specification change.docx | DOCX document | |
| AG-82B1-S-10-0288.pdf | ||
| FS ARRA SIGN DETAILS 2apr09.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 11, 2010
Warren Wagon Road Project Amendment 003 AG-82B1-S-10- 0288
1. Delay of bid submittals: The Bid submittal date is delayed for one week to May 20, 2010 2:00pm mdt. The reason for this delay is to research the blasting requirements. There will be another amendment in the next few days that will modify the blasting requirements that were added to Section C in amendment 002.
2 Work allowed in Summit Pit:
Section 105.02 and sheet 2 of the drawings . The contract states that the Summit Pit is to be used for the disposal of unsuitable or excess excavated material only. For this amendment, add the following:
“The Summit Pit may be used as a work area to process the excavated material into Riprap and select granular backfill and crushed aggregate (if the contractor is able to produce the crushed rock that meets the specifications from the excavated material). Machinery and sorting equipment may be set up in the Summit Pit only in the existing disturbed area and the existing cleared area at the Summit Pit. Material cannot be borrowed from the Summit Pit. “