amendment for Blasting amend 004.docx

DOCX document 39 KB Posted

Attached to
Road Construction Federal contract opportunity
Solicitation number
AG-82B1-S-10-0288
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain

About this file

Amend 004 Attachment --new blasting specification

View the file

Other files for this federal contract opportunity

Other files attached to Road Construction, newest first.
File Type Posted
amend 004 0288 signed.pdf PDF
amendment3 for Delay of Bids and Summit Pit_operations.docx DOCX document
amend003.0288.signedpdf.pdf PDF
amend01 signedpdf.pdf PDF
amend 002 0288.pdf PDF
Attach Amend 01.docx DOCX document
amend 002 0288.pdf PDF
fire precautions.doc DOC document
AG-82B1-S-10-0288.doc DOC document
Wage Determination —
AG-82B1-S-10-0288.pdf PDF
FS ARRA SIGN DETAILS 2apr09.pdf PDF
WARREN WAGON SHT 1 - 22.pdf PDF
FSSS FP-03 WARRENWAGONROAD FINAL.pdf PDF
Specification change.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

May 14, 2010 Solicitation AG-82B1-S-10-0288 Amendment 004, Blasting Requirements

Delete the sentence in the amendment 002 that said “Blasting shall occur in segments 1 and 2 after August 15th and shall occur as two blasts ( one for each segment) to minimize instream disturbance. “

Delete the Forest Service Supplemental Specification 205- Rock Blasting

Insert the following revised Forest Service Supplemental Specification 205 Rock Blasting

Supplemental Sepc revised by Amendment 4, May 14, 2010

Section 205. - Rock Blasting Construction Requirements

205.05 Blasting Plans.

(a) General Blasting Plan. Add the following:

(1) Include provisions in the blasting plan for protecting the Secesh River, the riparian area, and adjacent fisheries during blasting.

Blasting shall occur in segments 1 and 2 after August 15th and may occur in multiple blasts according to the following restrictions.

A series of small blasts are anticipated. Multiple shots ( outside of the given buffer based on shot size ) are allowed as long as they are separated by an eight millisecond or longer delay

205.08 Blasting.

Add the following:

Use appropriate blasting procedures and measures to ensure that material from the blast does not enter the Secesh River.