SPS-INDIAN Creek Specs.docx

DOCX document 96 KB Posted

Attached to
RECOVERY - INDIAN CREEK BRIDGE UPGRADE AND REPLACEMENT
Solicitation number
AG-82B1-S-10-0261
Issued by

About this file

Special Project Specifications

View the file

Other files

File Type Posted
Idaho wage Constr.CONSTR.txt TXT text file
sf1447 S-10-0261.pdf PDF
Indian Creek map drawings.pdf PDF
s-0261 B- M Indian Crek.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents

Table of Contents1
Preface3
101 - Terms, Format, and Definitions4
101.01 Meaning of Terms4
101.03 Abbreviations.4
101.04 Definitions.4
102 - Bid, Award, and Execution of Contract7
102 Bid, Award, and Execution of Contract7
103 - Scope of Work8
Deletions8
104 - Control of Work9
Deletions9
104.06 Use of Roads by Contractor9
105 - Control of Material10
105.02 Material Sources10
106 - Acceptance of Work11
106.07 Delete11
107 - Legal Relations and Responsibility to the Public12
107.05 Responsibility for Damage Claims.12
107.06 Contractor’s Responsibility for Work.12
107.09 Legal Relationship of the Parties.12
107.10 Environmental Protection.12
108 - Prosecution and Progress14
108 Delete.14
109 - Measurement and Payment15
109 Deletions15
109.02 Measurement Terms and Definitions.15
151 - Mobilization16
151.04 Weed Prevention / Weed-Free Equipment16
152 – Construction Survey and Staking17
152.01 (a) Personnel.17
155 - Schedules for Construction Contracts18
155 Delete.18
156 - Public Traffic19
156.03 Accommodating Traffic During Work.19
156.08 Traffic and Safety Supervisor.19
157 - Soil Erosion Control20
157.02 Materials20
157.03 General.20
157.08 Water Crossings.20
203 - Removal of Structures and Obstructions21
203.03 Salvaging Material.21
203.05 Disposing of Material.21
272 - Geocell Abutment Stabilization22
308 - Minor Crushed Aggregate25
553A – Precast Concrete Structures27
555 - Steel Structures30
555.03 General.30
622 - Rental Equipment31
622.02 Rental Equipment31
625 – Turf Establishment32
625.04 Preparing Seedbed.32
625.05 Watering32
625.06 Fertilizing.32
625.07 Seeding.32
625.08 Mulching.33
703 - Aggregate34
703.03 Granular Backfill.34
736 - Geocell35
736.01 Geocell35

Preface Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work Deletions

Delete Sections 104.01, 104.02, and 104.04.

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02 Material Sources

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Crushed Aggregate Source- Government Furnished. Crushed aggregate source is located at the Rombo Pit located approximately 45 miles from the site on Forest Service Road 473 Mile Post 18.8.

Coarse Granular Backfill – Contractor Furnished – There is no available Government source for Coarse Granular Backfill for construction of the geocell abutment stabilization.

Riprap Source – Contractor Furnished – There is no available Government source for riprap for this project.

Waste Site – Government Furnished – A waste site for excess and unsuitable material is located within 5 miles from this project. All waste material shall be spread and wasted as directed by C.O. This site is to be used for the disposal of unsuitable or excess excavated material only. All other materials designated for removal and disposal must be disposed of away from Forest Land as per SPS Section 202.

Materials Stockpile Site- Government Furnished – Prior to the closure of Road 6223 the Contractor will be allowed to stockpile material, except crushed aggregate, but including riprap and bridge components, at the Indian Creek site adjacent to the bridge. Materials must be stockpiled in such a manner as to allow for safe passage of the general public along Road 6223 and to avoid damage to any trees at the bridge site. Reclaim site to original condition or as directed by CO. Provide the CO 72 hours advance notification prior to stockpiling any materials at the bridge site.

Add the following to section (b) Contractor-located sources.

Prior to any pit development or use of materials, the pit site shall be approved by the CO that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

106 - Acceptance of Work

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress 108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

151 - Mobilization

Add the following:

151.04 Weed Prevention / Weed-Free Equipment

In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.

Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.

152 – Construction Survey and Staking

152.01 (a) Personnel.

Add the following.

Conduct all construction staking under the direction of a licensed professional engineer or land surveyor who is closely associated and familiar with construction staking.

155 - Schedules for Construction Contracts 155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic

156.03 Accommodating Traffic During Work.

Delete the first paragraph and replace with the following:

Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635. Submit a traffic control plan for acceptance at least 30 days before intended use.

Add the following project specific requirements:

The Contractor shall provide signs at the intersection of the FDR 6223 and FDR 468 to indicate “Road Closed Ahead” and “Bridge Construction Ahead”.

The Contractor shall provide one American Recovery and Reinvestment Act sign, posted at the beginning of Road 6223. This sign shall be the size for slow-moving traffic.

The Contractor will be allowed to close Road No. 6223 at Indian Creek Bridge to thru traffic for two weeks after August 3. All in stream work must be accomplished from July 1 to August 15th It is the responsibility of the Contractor to schedule delivery of materials, equipment and all necessary supplies to the site, to ensure that the bridge can be substantially completed within the specified contract time. The Contractor shall give the CO at least two weeks advanced written notice prior to any road closure. The Contractor shall be responsible for providing, installing, maintaining, and removal of warning signs and barricades required for the road closure period in accordance with MUTCD as submitted and approved in the traffic control plan.

Delete the following from the last sentence of the last paragraph:

according to Subsection 106.07(b)

156.08 Traffic and Safety Supervisor.

Delete this subsection in its entirety.

157 - Soil Erosion Control

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

157.03 General.

Delete the first two paragraphs and replace with the following:

Submit an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction in accordance with the plans and storm water permits. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the CO for approval.

Reflect in the Erosion Control Plan special concerns and measures necessary to protect resources and government improvements. Include:

(a) The construction activities and sequence of implementation relating to specific erosion control measures.

(b) The location and type of permanent controls to be implemented during construction.

(c) The location and type of temporary controls to be implemented during construction.

(d) For work in stream channels with running water a detailed dewatering plan.

(e) For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.

(f) Description of the monitoring plan.

Add the following to the third paragraph:

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.

157.08 Water Crossings.

At any channel crossing where there is running water, dewater by rerouting water flow around the site before and during excavation and embankment operations.

203 - Removal of Structures and Obstructions

203.03 Salvaging Material.

Add the following to the last paragraph:

There is no salvage of materials on this project.

203.05 Disposing of Material.

Modify this subsection as follows:

(a) Remove from project. Add the following:

All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

(e) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes or scatter as directed by the CO to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets. All slash material not suitable for embankment slopes shall be disposed off Forest Service Lands in accordance with all local, state and federal requirements or as approved by the CO.

272 - Geocell Abutment Stabilization Description

272.01 This work consists of constructing geocell abutment stabilization at each abutment using a cellular confinement system such as Presto Geoweb Cellular Confinement System or Webtec TerraCell in accordance with the plans and manufacturers recommendations.

Materials

272.02 Requirements. Ensure that material conforms to specifications in the following subsections:

Granular Backfill Type (a)703.03
Geotextile, Type II (A, B, C)714.01
Geocell736

Construction Requirements

272.03 General. Perform the work specified in Section 208 or 209. Use ditches, grading or similar methods to prevent surface runoff that may occur during inclement weather from ponding in the foundation excavation.

272.04 Storage and Handling of Material. During shipment and storage, wrap geotextile materials in heavy-duty protective covering. Protect the material from mud, soil, dust, debris and sunlight prior to installation.

272.05 Geotextile Installation. Place the geotextile according to Section 207. Have the surface approved by the CO prior to placing geotextile.

Sew or overlap adjacent strips a minimum of 12” at joints. Insert securing pins through both strips of overlapped geotextile at minimum intervals of 3 feet, but no closer than 2 inches to each edge, to prevent the geotextile from being displaced.

Have the installed geotextile approved by the CO prior to setting the geocells.

272.06 Geocell Installation. Furnish the CO with product literature and certification as required in Section 106.03 for review and approval 7 days prior to installation. When requested by the CO, furnish a sample of the geocell from each lot for verification testing.

Place the geocell sections directly on the prepared subgrade. Expand the geocell sections into position at the grades and lines as shown on the plans. Hold the expanded geocell sections with suitable “stretcher frames”, steel stakes driven inside selected outer cell walls, or other similar methods as allowed by the manufacturer prior to filling. Ensure that the individual cells have expanded to the minimum dimensions required by the manufacturer. If necessary field cut sections as per the manufacturer’s recommendations to the lines shown on the plans.

Connect geocell panels in accordance with the manufacturer’s recommendations.

272.07 Infill Placement. Furnish the CO with the manufacturer’s specific recommendations for backfilling 7 days prior to placement of the geocells.

Place coarse granular backfill meeting Subsection 703.03 into the expanded cells with equipment appropriate for the site conditions such as a backhoe or a front-end loader. Do not drop infill material more than 3 feet to avoid damage or displacement of the cell walls.

Overfill the geocell cells and level to a minimum of 2 inches above the top of the cell walls. A front-end loader may be used to place the infill provided that it only traffics above geocell sections that have been filled and covered with the minimum 2 inches of additional material. Compact the infill material with a vibratory plate compacter. Operate compaction equipment over the full width of the geocell. Make at least three complete passes or until visible deformation of the infill ceases. Grade the surface to be ½ inch above the top of the cells. Ensure that the cell walls are not exposed after fine grading is completed.

Use the geocell manufacturer’s specific recommendations for backfilling if they are more stringent than stated above.

272.08 Acceptance. Geotextile will be evaluated under Subsections 106.02 and 714.01.

Material for geocell will be evaluated under Subsections 106.2 and 106.03.

Granular backfill material will be evaluated under Section 106.02 and 106.04.

Measurement

272.09 Method. Measure the items listed in the bid schedule according to Subsection 109.02 and the following.

Measure geocell by the square yard in place, exclusive of wastage.

Payment

272.10 Basis. The accepted quantities will be paid for at the contract price per unit of measurement for the Section 272 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

The cost for furnishing and placing the granular backfill required in Sections 207, 208, and 209 for geocell infill is incidental to this pay item and no separate payment will be made.

The cost for furnishing and placing geotextile for the geocell installation is incidental to this pay item and no separate payment will be made.

308 - Minor Crushed Aggregate Delete section 308 in its entirety and replace with the following:

Description

308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.

Material

308.02 Conform to the following Subsections:

Crushed aggregate703.06
Water725.01

Construction Requirements

308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.

308.04 Placing Crushed Aggregate.

(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.

Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.

(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.

308.05 Compacting and Finishing Crushed Aggregate.

(a) Roadway aggregate. Compact using the methods below, specified in the Schedule of Items.

(1) Method 1. Operate equipment over the full width of spread aggregate.

(2) Method 2. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at a moisture content suitable for compaction.

(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.

308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03. Furnish a production certification including gradation and quality properties for each source.

Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and 106.04. Method 2 compaction will be evaluated under Section 106.04.

Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.

Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.

Measurement

308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Measure crushed aggregate by the cubic yard in-place on the road.

Measure width horizontally to include the top of aggregate width including designed widenings. Measure the length horizontally along the centerline of the roadway.

Payment

308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

553A – Precast Concrete Structures Description

553A.01 Work. Construct precast concrete members. In addition, manufacture, test materials for, transport, store, and install all precast concrete portions except piling, and perform all necessary grouting, welding, or other connections. Furnish precast concrete members complete and in place, including all concrete reinforcing steel and incidentals connected therewith.

Materials

553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:

High-Strength Nonshrink Grout ……………………………… 725.40
Mortar ………………………………………………………… 725.40
Reinforcing Steel ……………………………………………… 709.01
Sealants, Fillers, Seals, & Sleeves …………………………….. 712.01
Structural Concrete ……………………………………………. 552
Structural Steel ………………………………………………… 717.01

Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN ON THE DRAWINGS. Precast concrete members must be manufactured by a plant certified by the Prestressed Concrete Institute (PCI). Submit a copy of the transmittal letter of the latest PCI inspection with the shop drawings.

In lieu of PCI certification, Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the concrete members are constructed in accordance to the specification and shall include but not limited to:

a) Shop drawing review.

b) Concrete member dimensions.

c) Concrete mix design.

d) Aggregate sources and test results.

e) Steel reinforcing placement.

f) Concrete curing and strength test results.

g) Concrete material certifications.

h) Placement mixing, delivery and sampling.

Certification of the above shall be received by the CO prior to shipment and installation at the job site.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

Construction

553A.03 Performance. Construct precast concrete structural members in accordance with the following sections and subsections, as applicable:

Reinforcing Steel ………………………………………………... 554
Storing, Transporting, & Erecting ………………………………. 553.08
Structural Concrete ……………………………………………… 552

Submit four sets of shop drawings to the CO for approval, including the concrete mix design for each class of concrete proposed for use, a minimum of 21 days before fabrication of the precast member(s).

553A.04 Casting Yard. The precasting of concrete structural members may only be done at a casting yard of a PCI Certified plant.

553A.05 Handling, Transporting, & Erecting. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.

553A.06 Acceptance. Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement, and reinforcing steel.

Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.

Construction of precast concrete members will be evaluated under Subsections 106.02 and 106.04.

Reinforcing steel will be evaluated under Section 554.

Falsework and forms will be evaluated under Section 562.

Measurement 553A.07 Measure the Section 553A items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.

Payment 553A.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 553A pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

555 - Steel Structures

555.03 General.

Add the following:

In lieu of AISC Simple Steel Bridge Structures certification, Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the steel members are fabricated in accordance to the specifications and shall include but not limited to:

a) Shop drawing review.

b) Material mill certifications.

c) Welding - qualifications of personnel.

d) Welding.

e) Fabrication.

Certification of the above shall be received by the CO prior to shipment and installation at the job site.

622 - Rental Equipment

622.02 Rental Equipment

Delete the first two sentences of the first paragraph and add the following:

Provide equipment of the type listed in the Schedule of Items. Provide equipment of at least the minimum size needed to efficiently perform the work. Submit the model number of the equipment to the CO for approval before delivery to the project site. Equipment shall be no more than 15 years old and shall be reasonably free of leaks and other mechanical deficiencies.

625 – Turf Establishment

625.04 Preparing Seedbed.

Delete entire subsection.

625.05 Watering

Delete entire subsection.

625.06 Fertilizing.

Delete entire section and replace with the following:

Apply fertilizer having a chemical analysis as listed below by the following method.

(a) Dry Method. Apply the fertilizer with approved power driven seeders, drills, fertilizer spreaders or other mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.

Fertilizer. The fertilizer shall be a slow release organic fertilizer applied at the manufacturer’s recommended rate with an N-P-K formulation of:

NutrientPercent
Nitrogen, N . . . . . . . . . . . . .6-8 %
Phosphorus, P205 . . . . . . . . .2-4 %
Potassium, K . . . . . . . . . . . . .3-4 %

625.07 Seeding.

(a) Dry method. Delete the third sentence.

Add the following after subsection (b).

Seed Mix. Furnish and apply the following kinds and amounts pure live seed:

Common Name
Scientific Name
Pure live Seed Lbs./Acre
Bromar Mountain Brome
Bomus Marginatus
10
Pryor Slender Wheatgrass
Elumus Trachcaulus
8
Canbar Canby’s Bluegrass
Poa Canbyi
2

Total 20*

*Minimum seeding rates: Seed at a rate of 60 pure live seed/square foot. When broadcast seeding on crusted soils, harsh sites, or in competition with noxious weeds, higher seeding rates are recommended.

Seed Certification Certified, blue-tagged seed shall be used where a name variety or cultivar is specified. Blue tags that are removed to mix or spread the seed will be saved and provided to the Forest.

All seed purchased will be certified free of seeds from weeds listed on the current "All States Noxious Weeds List."

Pounds of seed to be furnished per acre shall be obtained by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

Example: (5 lbs. pure live seed/acre) = 6.55 lbs.

(0.90 x 0.85) commercial seed/acre where: purity = 90%; germination = 85%.

625.08 Mulching.

Delete the entire subsection and replace with the following:

Mulching:

Mulch material shall be weed free straw and shall be applied at a uniform rate to adequately cover the seed. The weed free straw shall be from a grain crop such as barley straw, wheat straw or oat straw.

Mulch will be applied in a one-step operation with the seed at the rate of 1 Ton per Acre.

703 - Aggregate

703.03 Granular Backfill.

Add the following:

(c) Course Granular Backfill. Furnish backfill material that consists of clean, hard durable particles or fragments of crushed stone, crushed slag or crushed gravel meeting the gradation shown below.

Sieve Size
Percent Passing
1 inch
100
¾ inch
75 to 100
No. 4
0 to 60
No. 40
0 to 50
No. 200
0 to 5

736 - Geocell

736.01 Geocell.

Furnish geocell material consisting of sheet strips fabricated from high-density polyethylene (H.D.P.E.), connected in series at off-set, full-depth ultrasonic seams aligned perpendicular to the longitudinal axis of the strips. When expanded, the interconnected strips form the walls of a flexible, three-dimensional cellular confinement structure into which the specified infill material is placed.

736.02 Requirements. Furnish geocells consisting of polyethylene material treated to resist ultraviolet degradation and conforming to the requirements shown in table 736-1.

Table 736-1 – requirements for geocells.

Density
ASTM D 1505
0.935 to 0.965 g/cm3 (58.4 to 60.2 pounds per cubic foot).
Environmental Stress Crack Resistance
ASTM D 1693
3000 hour
Strip Sheet Thickness
ASTM D 5199
1.27 mm (50 mil), minus 5 percent, plus 10 percent. Determine thickness in the flat before any surface texturing or other surface disruption.
Short-term peel strength
U.S. Army Corps of Engineers Technical Report GL-86-19, Appendix A
2000 N (450 pound) minimum for 203 mm (8.0 inch) depth cell
Seam Hang Strength
101.6 mm (4”) weld joint supporting load of 72.5 kg (160 pounds)

or

101.6 mm (4”) weld joint supporting load of 72.5 kg (160 pounds) while undergoing temperature change from 23O C to 54O C (74O F to 130O F) on 1 hour cycles.

30 days minimum

7 days minimum image1.png

File details come from the government source that posted it. Updated .