Question and Answer

Lost Creek Culvert Replacement

1. Is there a bid guarantee required for this project or only Performance and Payment Bonds if awarded?

Answer: A bid guarantee is not required for this project. Please refer to the clause 52.228-13 located in Section I for additional information regarding Alternative Payment Protections.