TumbledownRR_sps.doc
DOC document 171 KB Posted
- Attached to
- RECOVERY- Road Reconstruction, Tumbledown Road
- Solicitation number
- AG-82B1-S-09-0124
About this file
Tumble Down Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S- 0124 R TumbledownRR_SectionBC.pdf | ||
| 2of11_TumbledownRR1.pdf | ||
| SF 30 Amend 1 | — | |
| 4of11_TumbledownRR.pdf | ||
| 8of11_TumbledownRR.pdf | ||
| db Idaho wage rates.txt | TXT text file | |
| 11of11_TumbledownRR.pdf | ||
| 0124 Cover Page.pdf | ||
| 3of11_TumbledownRR.pdf | ||
| 1of11_TumbledownRR.pdf | ||
| 2of11_TumbledownRR.pdf | ||
| 6of11_TumbledownRR.pdf | ||
| 7of11_TumbledownRR.pdf | ||
| 9of11_TumbledownRR.pdf | ||
| 5of11_TumbledownRR.pdf | ||
| 10of11_TumbledownRR.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IPNF SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction 101.02
Delete in its entirety and substitute the following:
Pay Items & Pay Units And
AC
Acre
AL.
Aluminum
ASP
Asphalt
AVAIL
Available
BARR
Barrier
BKN
Broken
BST
Bituminous Surface Treatment
CATTLEGD
Cattleguard
CLEAR (CLG)
Clearing
CLEAR/GRUB
Clearing & Grubbing
CMP
Corrugated Metal Pipe
COMP
Compaction
CONC
Concrete
CONST
Construction (Construct)
CTD
Coated (Coating)
CUSH
Cushion
CY (CU YD)
Cubic Yard
CY MI (CYM)
Cubic Yard Mile
DIA
Diameter
DL
Double Lane
DWGS
Drawings
EA
Each
EMB
Embankment
EXC
Excavation F&I Furnish & Install
FDN
Foundation
FT
Foot (Feet)
FUNC
Function
GAL
Gallon
GR.
Grade
GRUB
Grubbing
HDPE
High Density Polyethylene
HOR
Horizontal
HR
Hour
HT
Height I Install
IN
Inches
INCL
Including (Includes)
IND
Individual
JCT
Junction L Logs
LBS
Pounds
LDG
Loading
LF (LIN FT
Linear (lineal) Foot
LS …………………………..
Lump Sum LT ………………………….. Left
MAT'L
Material M Metal
MAX
Maximum
MBF
One Thousand Feet Board Measure
MGALS
One Thousand Gallons
MHD
Method
MI
Mile
MIN
Minimum
MISC
Miscellaneous
MP
Mile Post
MSF
One Thousand Square Feet
OTBC
Open Top Box Culvert P M Placement Method
PVC
Polyvinylchloride
RD
Road
RECOND
Reconditioning
RECONST
Reconstruction (Reconstruct)
REFL
Reflectorized
RT
Right
STMP (STP)
Stump(s)
SB
Self Balance
SEC
Section
SF
Square Foot (Feet)
SL
Single Lane
SLD
Solid
ST
Slash Treatment
STA
Station (100 Feet)
STA YD
Station Yard
STL
Steel
STR (STRUC)
Structural
SY (SQ YD)
Square Yard
SZ
Size T&L Tops & Limbs
TBR
Timber
TH
Thickness
TM
Ton Mile
TO
Turnout
TOL
Turnout Left
TOR
Turnout right
TRS
Trees
UOT
Utilization of timber
VERT
Vertical W Width W/ With W/O Without
X-SEC
Cross Section
YD
Yard
F04 – SPS 101 –1 (07/01/09)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction Section 102 - Definitions Add the following:
"Noxious Weeds or Weeds. Any exotic plant species established or that may be introduced in the State which may render land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the State's Department of Agriculture, or by the County's weed management district, or by other appropriate agencies having jurisdiction, or as listed on the current "All States
Noxious Weed List."
Shop Drawings. Incidental design sheets and/or drawings which the Contractor is required to submit to the Forest
Service. Shop drawings shall conform to the contract requirements, but they are not part of the contract drawings. They may be drawings, diagrams, schedules, performance charts, brochures, and similar data prepared by the Contractor, subcontractor, manufacturer, suppliers, or distributors that illustrate how specific portions of the work are to be fabricated or installed.
Weed Management District. A weed management district is any area of land identified for the purpose of weed management or control. Such an identified land area may be, but is not limited to one of the following: a project or job site, a
County, two or more Counties, or a National Forest."
R01-85 SPS 102 -1 (4/96)
SPECIAL PROJECT SPECIFICATION
Section 104 - Maintenance for Traffic 104.01
Roads to be Delete the second paragraph and replace with the following:
Constructed
Prior to the Contractor shutting down any operations, the Contractor shall take such precautions as may be necessary to prevent damage to the project, such as approaches, crossings or intersections; and shall make provisions for normal drainage and minimization of erosion.
CONSTRUCTION SIGNING
The contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient signs, and other traffic control devices and shall take necessary precautions for the protection of the work and safety of the public as SHOWN IN THE DRAWINGS.
PAYMENT
104.06 The following shall be added:
Basis
"Payment for construction signing and traffic control under this section shall be considered subsidary to Pay Item 601 - Mobilization and no separate payment will be made."
SPS 104-1 (07/01/09)
Section 106 - Measurement & Payment 106.03
Units of Under "(a) Cubic Yard, " add the following:
Measurement
"(4) Material, Compacted in Place. The measurement computed using measurements of material in the compacted state on the project. Statistically random measurements of length, depth, and width for computation of quantities shall be made along the project when Actual Quantities are shown on the SCHEDULE OF ITEMS."
F04-SPS 106 - 1 (07/01/09)
SECTION 201B - CLEARING AND BRUSHING
DESCRIPTION
201B.01 This work shall consist of removing limbs, residual slash, brush, small trees and
Work shoulder stumps between, or obtruding into, the designated clearing limits. The clearing limits shall be AS SHOWN ON THE DRAWINGS. Clearing areas shall include turnouts.
CONSTRUCTION
201B.02 All brush and small trees (6 inches diameter, or less, at the point of cut) shall be cut off
Clearing & no higher than 4 inches above ground level (6 inches for machine brushing). Should
Brushing rocks or other obstructions be encountered, the cutting height shall be no higher than 6 inches above the obstruction. Limbs overhanging the roadbed shall be removed to a height of 14 feet above the road surface.
201B.03 Windfalls lying within or across the brushing limits shall be cut off at a horizontal
Windfalls distance of 10 feet from the outside edge of each shoulder or at the clearing limit, whichever is least. Cut windfall material shall be disposed of as slash.
201B.04 Stumps in the roadbed or on the fill slope if not grubbed out shall be cut off 12 inches
Stumps below the finished subgrade. Grubbed stumps over 12 inches in diameter are to be reduced to pieces less than 12 inches, measured in any direction across the cut face.
201B.05 No clearing debris shall be deposited in the traveled way and/or ditches of
Road adjoining roads.
Junctions
201B.06 All slash and stumps, or pieces of stumps, shall be scattered outside the clearing limits
Slash without damaging residual trees. Slash shall be defined as any material cut that has a
Treatment length greater than 36 inches with a diameter greater than 3 inches at any point. No material shall be deposited in streams, streambeds, culvert inlets or outlets, or drainage ways.
SPS 201B-1 (07/01/09)
MEASUREMENT
201B.07 The method of measurement, described in Section 106, will be DESIGNATED in the
Method
SCHEDULE OF ITEMS.
Linear measurements will be horizontal along the road centerline.
Quantities will be the number of miles (or stations) and fractions thereof along the road centerline, regardless of the amount of work required.
PAYMENT
201B.08 The accepted quantities will be paid for at the contract unit price for each pay item shown in the SCHEDULE OF ITEMS.
Payment will be made under:
Pay Item
Pay Unit
201B(01) Clearing and Brushing Mile
201B(02) Clearing and Brushing Sta.
SPS 201B-2 (07/01/09)
Section 202 - Removal of Structures and Obstructions
CONSTRUCTION
202.02 Add to this section:
Performance
"All rocks scheduled for removal shall be side cast along adjacent fill slopes and a Min. of 50’ from stream courses.”
SPS 202-1 (07/01/09)
Section 204 - Soil Erosion & Water Pollution Control
DESCRIPTION
204.01
Delete in entirety and substitute the following:
Work
"This work consists of special temporary and/or permanent construction measures as SHOWN ON THE DRAWINGS and/or listed in this specification to control soil erosion and water pollution. Such measures may include (but are not limited to) filter windrows, slash blankets, brush barriers, drainage devices, earth berms, earthen water bars, sediment basins, aggregate base/surfacing, rock ditches, riprap, seeding, mulching, and/or straw bales.
This work shall also include special construction methods SHOWN ON THE DRAWINGS to control erosion at control areas."
MATERIALS
204.02
Delete the 2nd paragraph and substitute the following:
Requirements
"All other materials shall meet commercial grade standards and shall be approved before being incorporated into the project."
CONSTRUCTION
204.03
Delete the 2nd paragraph and substitute the following:
Performance
"Erosion control measures shall be incorporated into the project no later than the dates specified in Table 204.1. Variations in this schedule must be approved in writing by the Engineer."
Add the following after the 3rd paragraph:
"The following construction requirements shall apply:
a.- Earthwork. Clearing and grubbing, excavation, borrow and embankment operations shall be scheduled and performed so that grading operations and permanent erosion control measures can follow without interference or be constructed within the time periods listed in Table 204.1.
SPS 204-1(07/01/09)
b.- Wet Conditions. The contractor shall conduct operations so as to minimize erosion and not develop conditions that will cause erosion. Work may continue during wet conditions as long as erosion and rutting is controlled.
c.- End of Construction Season and prior to Move-out. Any rutted areas and other damaged areas shall be smoothed, sloped and graded to drain. All temporary stream course diversion conduits and temporary culverts shall be removed and the stream returned to its natural channel. All erosion control measures required under this specification shall be functional and approved by the Engineer.
MEASUREMENT
204.04
Add the following to the first paragraph:
Method
"Items not shown in the SCHEDULE OF ITEMS will not be measured."
PAYMENT
204.05
Add the following:
Basis
"Other erosion control work required under this specification and not shown in the SCHEDULE OF ITEMS is considered incidental to pay items in the Section listed in Table 204.1."
SPS 204-2 (07/01/09)
TABLE 204.1
Tumbledown Road Reconstruction
| SECTION |
| DURATION |
| DESCRIPTION OF WORK |
| TIMING OF CONSTRUCTION |
| Permanent |
| Culvert Catch Basins and Ditch Transitions |
| Concurrently with culvert installation. |
| 203 |
| Permanent |
| Drainage Dip Locations shown on the drawings. |
Prior to the end of the construction season for all areas roughed to grade.
| Incidental to 203 |
| Temporary |
| Straw Bales/Straw Mulch. As necessary to stabilize eroding areas. |
| Immediately upon discovery of active erosion. |
| 412 |
| Permanent |
| Dust Palliative |
| The Forest Service will be notified 48 hours prior to application. |
| 603 |
| Permanent |
| Culverts |
Live Streams Cross Drains Concurrently with other road work Concurrently with other road work
| 619 |
| Permanent |
| Riprap |
| by the end of construction season Concurrently with other road work |
SPS Table 204-3 (07/01/09)
Section 206A - Excavation for Culverts & Minor Structures
MEASUREMENT
206A.08 Add the following:
Methods
"(c) For gabion structures, measurement will be to the lines and grades as SHOWN ON THE DRAWINGS."
"(d) Excavation for pipe culverts with diameter of 36 inches or smaller and for pipe arches 42 inches by 29 inches or smaller and drop inlets shall not be measured."
PAYMENT
206A.09 After the first sentence, add:
Basis
"Payment for excavation for pipe culverts with diameter of 36 inches or smaller and for pipe arches 42 inches by 29 inches or smaller and drop inlets shall be included as a subsidiary item to Section 603 and Section 604. No separate payment shall be made under this Section or under Section 603, 603A, 603B, or 604."
F04-SPS 206A-1 (07/01/09)
Section 207 - Developing Water Supply & Watering
CONSTRUCTION
207.03 Add the following:
Development of Supply "All activities which may cause siltation or damming of a stream shall be approved
& Access in advance of the work, in writing by the Contracting Officer."
PAYMENT
207.06 Delete the first paragraph and substitute with the following:
Basis
"Payment for Developing Water Supply & Watering shall be included as a subsidiary item to Section 306 & 412. No separate payment shall be made under Section 207."
SPS 207-1 (07/01/09)
Section 306 - Reconditioning Existing Road
DESCRIPTION
306.01 Delete "scarifying and" from the text.
Add: "and catch basins" following "outlets"
CONSTRUCTION
306.02 Delete the first two paragraphs including (a) and (b) of the second paragraph
Performance and replace with the following:
"Scarification of the traveled way and shoulders is not required. Any rock protruding less than two inches may be left in place. Rock protruding in excess of two inches shall be removed or the tops blasted. Resulting holes in the roadway or shoulders shall be backfilled with compacted suitable material."
306.03
Add the following paragraph:
Miscellaneous
Work Items “Miscellaneous reconditioning work is required on Road 278. This work shall include removal of debris from ditchlines such as logs, rocks woody debris, root wads and slide material as DESIGNATED ON THE GROUND and/or SHOWN ON THE DRAWINGS.
PAYMENT
306.05 Add the following Pay Item:
Pay Item
Pay Unit
306(04) Miscellaneous Reconditioning L.S.
SPS 306-1 (07/01/09)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction Section 412 - Dust Palliative Treatment Delete this entire specification and substitute the following:
DESCRIPTION
412.01 Work This work shall consist of furnishing, sampling and applying dust palliative to a road surface. Road surface preparation requirements are DESIGNATED IN THE SCHEDULE OF ITEMS.
MATERIALS
412.02 Requirements The type of material shall be as shown on the SCHEDULE OF ITEMS and shall meet the specified requirements shown below:
Magnesium or Calcium Chloride Brine Chloride brines shall consist of water and magnesium and/or calcium chloride. The chemical composition, percent by weight brine, shall be as follows:
Chloride Concentration (Sum of Magnesium & Calcium Chloride) Magnesium Chloride product
28.0 % minimum Calcium Chloride products
36.0 % minimum Sulfate
4.3 % maximum Nitrate
5.0 % maximum (Test method R1-412/Cl must be used. It is available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, Montana 59807) The pH shall be between 4.5 and 10.0. The temperature of the material shall be 40oF or above when it is applied.
Calcium Chloride Flake The chemical composition as shown below shall be determined by ASTM E 449-79 on a percent-by-weight basis:
Calcium Chloride (CaCl2) 77% Minimum Total Alkali Chlorides (as NaCl) 3% Maximum Calcium Hydroxide (Ca(OH)2) 0.3% Maximum Particle size shall be as follows: 100% pass the 3/8" screen, 80 to 100% pass the #4 screen, and 0 to 5% pass the #30 screen
R01-85 SPS 412-1 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction Lignin Sulfonate
Lignin Sulfonate shall be the residue produced by the acid-sulfite pulping of wood. The base application shall be ammonium, calcium, or sodium. Lignin sulfonate shall be supplied as a uniform mixture and shall be miscible with an equal weight of water. The undiluted material shall conform to the following requirements:
pH (AASHTO T200)
4.5 minimum
Viscosity at 77 oF (AASHTO T202)
20.5 poise maximum
Total Lignin Solids Concentration 48 Percent Minimum
(Test method R1-412/LS must be used for Total Lignin Solids Concentration. It is available upon request from USDA Forest Service, Regional Materials Testing Laboratory, P.O. Box 7669, Missoula, Montana 59807)
The solids must meet the following requirements:
Lignin Sulfonate 50 percent minimum
Reducing Sugars 25 percent maximum
The temperature of the material during application shall be between 40 and 140oF.
Clarified Dust Oil DO-4
Clarified Dust Oil shall conform to the following requirements:
Flash Point (AASHTO T48) 200oF min.
Kinematic Viscosity @ 100oF (AASHTO T201 20-100 cSt
Water (AASHTO T55) 0.2% maximum
Asphaltenes (ASTM D3279) 0 - 5%
Saturates (R1-412/DO-4) 10% minimum
Volume of Oil Distillate @ 550oF
(AASHTO T59)
5% max.
Viscosity of Residue by Distillation at 100oF (AASHTO T201) 400 cSt max.
Test Method R1-412/DO-4 is available from USDA Forest Service, Regional Materials Laboratory, P.O. Box 7669, Missoula, MT 59807
The material temperature during application shall be above 85oF.
R01-85 SPS 412-2 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction
412.03
Certificate & Sampling
(a) Certification with Shipments. When each load of dust palliative is delivered, the contractor shall furnish the Engineer with one copy of the Bill of Lading and a fully executed Certificate of Compliance containing the applicable information shown in Figure 412-1. A separate Certificate of Compliance will not be required if the standard Bill of Lading contains the applicable information required by the certificate.
(b) Sampling. Sampling of dust palliative may be required to validate certifications furnished by the contractor. When sampling is directed by the Government, the actual samples shall be obtained by the contractor. The Engineer will be given the opportunity to witness sampling. All liquid delivery equipment shall be constructed to permit sampling in conformance with AASHTO T40 test procedure.
CERTIFICATE OF COMPLIANCE
Consignee Destination Transportation ID (Truck No., etc) Date Percent Concentration by Weight:
Magnesium Chloride: ..... % Calcium Chloride : ..... % Lignin Sulfonate: ..... % Net Weight Total Shipment Net Gallons @ 60oF Specific Gravity @ 60oF This shipment of .............. identified above and covered by this Certificate of Compliance complies with Forest Service Specifications applicable to Contract Number __________________.
Producer Signed
(Producer's Representative) Figure 412 - 1. -- Sample Certificate of Compliance
CONSTRUCTION
412.04 Weater Limitations All dust abatement materials shall be applied only when the surface to be treated contains appropriate moisture to get adequate penetration and absorption of dust abatement materials. Application during a light rain is acceptable provided the material penetrates the road surface, and does not flow to low areas or off the road surface.
R01-85 SPS 412-3 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction Chloride brines and Lignin materials shall be applied only when the temperature is 40oF or higher and the ground is not frozen.
To accelerate the penetration and absorption of calcium chloride flake materials, the road surface may be dampened prior to or after the flake application.
Clarified Dust Oil shall be applied only when the road surface and atmospheric temperature is 50oF or more and rising or above 60oF and falling.
412.05 Equipment The distribution equipment shall be so designed, equipped, maintained, and operated such that the dust abatement material may be applied uniformly on variable widths of surface. Application shall be at readily determined and controlled rates from 0.10 to 0.50 gallons per square yard with uniform pressure and application. The allowable variation from the specified application rate shall not exceed 10% of the specified rate for individual distributor loads, and 2% of the specified rate for the entire project.
For liquid products the following requirements shall apply: (1) The spray pattern from each nozzle on the spray bar shall be uniform across the spray bar; (2) Distribution equipment shall include accurate volume measuring devices or a calibrated tank, a thermometer for measuring temperatures of tank contents, and a hose and nozzle attachment for applying material to areas inaccessible to the spray bar.
Calcium Chloride Flake shall be spread with equipment that evenly distributes the material across the required road width. The weight of flake in distribution vehicles trucks shall be accurately determined prior to application. The relative weight of material placed shall be easily determined during application.
412.06 Preparation
of Road Surface One or more of the following preparation and application methods shall be followed as DESIGNATED IN THE SCHEDULE OF ITEMS.
Method 1. Apply the dust palliative directly to the previously prepared surface.
For Method 2 and 3 the road surface shall be processed by blading below the elevation of raveling, wash boarding, and pot holes. The top two inches of surfacing material shall have moisture content greater than 5 percent. After processing, the surface shall be shaped by blading to the required cross section SHOWN ON THE DRAWINGS. The prepared surface shall be approved in writing by the Engineer prior to treatment.
R01-85 SPS 412-4 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction Method 2. A layer of loose cushion material approximately 1 inch in depth shall be developed for the full width of traveled way and kept in as loose a condition as possible prior to applying dust palliative. After the dust palliative has penetrated and pickup of material will not occur, the surface shall be compacted as SHOWN ON THE DRAWINGS, or compacted over the full treated width with either roller(s) or loaded truck(s).
If the one-inch layer of cushion material becomes compacted by traffic prior to treatment, a one-inch thickness shall be cut from the surface and bladed into a berm on the shoulder. Just prior to applying the dust palliative, the material in the berm shall be bladed to a uniform depth across the full width of the previously watered surface. The loose material shall have a moisture content greater than 5 percent just prior to applying dust palliative. After application, compact as specified above.
Method 3. Approximately 1 inch of the surface material shall be bladed into a berm on the shoulder. The initial application shall then be made on the existing surface. As soon as practical, but no more than 1 hour after application, the material in the berm(s) shall be bladed to a uniform depth across the previously treated surface and watered, if necessary, to meet the 5 percent minimum moisture content. The second application shall then be applied. Compaction shall be performed as specified in Method 2.
412.07 Application Dust palliative application rates and width of road surface to be covered shall be as of Dust SHOWN ON THE DRAWINGS. For liquid products the rate is expressed as gallons Palliative per square yard and for Calcium Chloride Flake, the rate is expressed in pounds per square yard. If the actual application rate is less than specified, the dust abatement material left over will be applied at locations and application rates designated by the Engineer. If the application rate used by the contractor is greater than specified and additional material is required to complete the project coverage, the additional material shall be furnished and applied at the Contractor's expense.
The Engineer may field test Chloride brines and Lignin materials prior to application to make sure that the products meet the minimum concentrations specified. Acceptance of the material will be based on the concentration shown on the manufacturer's certificate, or on results of laboratory quality assurance tests done by the Forest Service on samples taken from distribution or hauling vehicles.
Uniform distribution shall be obtained at all points. For liquid products the spray pattern from each nozzle on the spray bar shall be uniform across the spray bar. For flake products, the coverage will be uniform on the road surface. Overlapping or skipping between spread sections shall be corrected. Accidental spillage and area with excess dust palliative that are hazardous to traffic shall be covered with additional road surfacing material at the contractor's expense. The surface of adjacent structures
R01-85 SPS 412-5 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction and trees shall be protected from spattering or marring. Dust palliative material shall be discharged only in approved areas, and shall not be allowed to flow into ditches or stream courses.
412.08 Maintenance & Opening Traffic The treated road surface shall be open to traffic within two hours following treatment.
Traffic control and the prevention of vehicle undercoating is the contractor's responsibility. If dust abatement material is picked up by vehicles, the contractor shall apply road surfacing blotter material, and if necessary apply more dust abatement material to repair the damage. No compensation will be made for blotter or the additional dust abatement material to correct these problems. Reductions in payment may be made where traffic control and repair of the treated surface are not adequate.
MEASUREMENT
412.09 Method The method of measurement, as described in Section 106, will be DESIGNATED in the SCHEDULE OF ITEMS.
PAYMENT
412.10 Basis The accepted quantities will be paid for at the contract unit price for the pay item shown in the SCHEDULE OF ITEMS, with the following exceptions:
If laboratory quality assurance tests indicate that the minimum Calcium or Magnesium Chloride concentrations applied to the road surface were not as specified in Section 412.02, the Forest Service may reduce payment by multiplying the pay factor as calculated below, times the contract unit price for Item 412(07), 412(08), 412(13), 412(14), Item 412(15) or Item 412(16), times the accepted quantity. No payment will be made for brine concentrations below 20 percent.
Magnesium Chloride Brine Pay Factor =
1.0 - (28% - Concentration Applied)
(8%) Calcium Chloride Brine Pay Factor =
1.0 - (36% - Concentration Applied)
(16%) If laboratory quality assurance tests indicate that the minimum Lignin concentrations
R01-85 SPS 412-6 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction were not as specified in Section 412.02, the Forest Service may reduce payment by multiplying the pay factor as calculated below times the contract unit price for Item
412(09) or Item 412(10), times the accepted quantity. No payment will be made for concentrations below 24 percent.
Lignin Pay Factor = 1.0 - (48% - % Concentration Applied)
(24%) If laboratory quality assurance tests on Clarified Dust Oil indicate that the maximum limits for viscosities, or asphaltenes were exceeded, the Forest Service may reduce payment by multiplying the lowest pay factor as determined below, times the contract unit price for Item 412(05) or Item 412(06), times the accepted quantity.
Original Kinematic Viscosity Pay Factor = 100/Original Viscosity Asphaltene Pay Factor = (5 percent)/(percent Asphaltenes) Residue Viscosity Pay Factor = 400/Residue Viscosity When each hauling/distribution vehicle cannot be readily weighed to determine quantities, the actual weight of material in full vehicles shall be determined at the start of the project. Thereafter, the number of vehicle loads applied to the road surface can be used for quantity determination, provided each load is full, each load is completely emptied on the project, and material lost from the load is deducted. The Engineer may direct the additional check weighing of loaded and empty vehicles at any time.
Pay Item Pay Unit 412(05) Clarified Dust Oil DO-4
Preparation Method
_______TON
412(06) Clarified Dust Oil DO-4
Preparation Method
_______GAL
412(07) Magnesium Chloride Brine
@ 28% minimum Concentration Preparation Method
_______TON
412(08) Magnesium Chloride Brine
@ 28% minimum Concentration Preparation Method
_______GAL
412(09) Lignin Sulfonate Solution
@ 48% minimum Concentration Preparation Method
_______TON
412(10) Lignin Sulfonate Solution
@ 48% minimum Concentration Preparation Method
_______GAL
R01-85 SPS 412-7 (1/95)
REGIONAL SPECIAL PROJECT SPECIFICATION
Tumbledown Road Reconstruction 412(13) Calcium Chloride Brine @
36% minimum Concentration Preparation Method
_______TON
412(14) Calcium Chloride Brine @
36% minimum Concentration Preparation Method
_______GAL
412(15) Magnesium Chloride Brine
@ 28% minimum Concentration or Calcium Chloride
Brine @ 36% minimum Concentration, or
Preparation Method _______L.S.
412(16) Calcium Chloride Flake
@ 77% minimum Pellet 94% Concentration
Preparation Method
________TON
R01-85 SPS 412-8 (1/95)
Section 601 - Mobilization
DESCRIPTION
601.01
Replace the first sentence with the following:
Work
“This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project work site.”
Add the following to this subsection:
“Preparatory work shall also include cleaning of all equipment used at the project site. The contractor(s) is required to clean all construction equipment prior to entry on the project site. This cleaning shall remove all dirt; seeds, vegetative matter, or other debris that may carry noxious weed seeds into the area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of equipment shall be treated the same as the initial move-in. Truck beds and dump boxes hauling to the project site must also be cleaned prior to entering the work area.
Prior to initial move-in, the contractor shall make all construction equipment available for inspection by the Contracting Officer at an agreed upon location. Contractor shall provide the Contracting Officer at least 24 hours advance notification when equipment is ready for inspection. Service vehicles, pickup trucks, cars and other similar vehicles are not considered construction equipment.
Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required.”
SPS 601 - 1 (07/01/09)
Section 603 - Metal Pipe
DESCRIPTION
603.01
Add the following:
Work
"The material thickness, corrugation dimensions, and other criteria for corrugated galvanized steel and corrugated aluminum alloy pipe specified in Section 707 and meeting the requirements of AASHTO M 36 and M 196, as applicable, provide certain strength characteristics. Reinforced concrete or polyethylene pipe meeting these strength characteristics may be substituted for the listed material. Substituted material shall meet the requirements of Section 603A or 603B, as appropriate."
MATERIALS
603.02
Delete the second sentence, last paragraph, and add:
Requirements
"Pipe should not be ordered until culvert locations are DESIGNATED ON THE GROUND and the correct lengths are determined."
CONSTRUCTION
603.06
Joining
Replace the last sentence in the first paragraph with the following:
Pipes
"Dimple bands shall not be used unless approved by the Engineer in writing."
603.08
At the end of the first paragraph, after "method A or B," add:
Backfilling
"or C"
After Method B, add:
"Method C - Compaction shall be obtained by a minimum of two passes with a mechanical tamper, approved by the Engineer, for each 6-inch layer (loose thickness) of backfill unless otherwise SHOWN ON THE DRAWINGS."
F04-SPS 603(1)-1 (07/01/09)
REGIONAL SPECIAL PROJECT SPECIFICATION
Section 619 - Riprap
MATERIALS
619.02
Hand-placed, Machine-placed, and Dumped Riprap
Delete the Durability Absorption Ration Chart and formula and the second paragraph.
PAYMENT
619.21
Basis
Add the following:
"The cost of excavation and embankment required for placement of riprap is incidental to this pay item and no separate payment will be made."
R01-85 SPS 619-1 (8/90)
Section 619 – Riprap
RIPRAP
CLASS
STONE
WEIGHT
IN LBS
| % SMALLER THAN THE GIVEN |
| 1. 2. & 3. EQUIVALENT CUBIC SIZE |
INCHES
BETWEEN
EQUIVALENT
CUBIC SIZE
MM
REMARKS
<---weight Size------------------------------------------------------>
| V |
| 250 |
<10
<10
1.Size developed from weight using specific gravity of 2.71 and unit weight of 169 #/cubic ft. and then rounded to nearest inch.
| VI |
| 400 |
<10 <10 2.To determine weight of non cubic rocks - use the following formula:
X=WxDxLx .0978 #/Cubic Inch
VII
<10
<10 X = Stone Weight (lbs) W = Width D = Depth L = Length Example:
27"x21"x18"x.0978=998lbs
VIII
<10
<10 This would place the stone at 998 lbs in the maximum size for Class VIII, 30% between 800# and 1600#.
| IX |
| 2700 |
<10
<10
R01-85 SPS 619-2 (8/90)