STATEMENT OF WORK
STATEMENT OF WORK
Killpecker / Deadman – Aggregate Delivery Canyon Lakes Ranger District
14 July 2016
1. Project is located on the Canyon Lakes Ranger District on the Arapaho and
Roosevelt National Forest at the intersection of NFSR 300 (Killpecker Rd) and LCR 86 (Deadman Rd) past Red Feather Lakes CO. Project is for the delivery, dumping and stockpiling of aggregate along with gate installation (Qty 1) for site security.
2. Contractor will be responsible for the purchase, hauling and stockpiling of material from nearby locations. Material will be delivered to an existing pit at the intersection of NFSR 300 and LCR 86. Minor site prep will be needed to establish a good stockpile location.
3. Contractor shall provide an “Earthen” tone aggregate from a nearby pit conforming to specs provided by the government. A sample must be approved before the product can be hauled.
4. Gate will be Government Furnished Material (GFM). Contractor shall be responsible for providing posts, hardware and concrete. Posts shall be 8” round, pressure treated timbers. Signs to be located on the gate are also GFM, but the hardware to hang signs on gate and gate posts shall be provided by the contractor.
All GFM materials will be available for pickup at 300 Hemlock st. Fort Collins CO, 80524. This is an administrative site on the North end of town adjacent to College Ave.