Attachment_1_Schedule.pdf
PDF 123 KB Posted
- Solicitation number
- AG-82AT-S-14-0034
- Issued by
-
Department of Agriculture Forest Service
About this file
Attachment 1 Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign_up_sheet.pdf | ||
| Attachment_4_Map_LeavenworthCreekWatershed.JPG | JPG image | |
| Attachment_2_Statement_of_Work.pdf | ||
| Attachment_3_Maps.pdf | ||
| AG82ATS140034_Part_1_of_2.pdf | ||
| AG-82AT-S-14-0034_Part_2_of_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A. SCHEDULE OF ITEMS – Arapaho and Roosevelt National Forests and Pawnee
National Grassland Argentine Mining District PRP Search
ITEM DESCRIPTION QUANTITY
DELIVERY
DATE
TOTAL
OFFER
1. Waldorf Mine: Phase
1: Investigation
(Items 1-5) and
Discussion of the
Site; Draft Report
Lump Sum
120 days after issuance of
Notice to
Proceed
2. Waldorf Mine Phase
2: History, Documentation
(Items 1-6); Final
Report
Lump Sum
120 days after issuance of notice to proceed.
Option 1.
3. Santiago Mill and
Mine: Phase 1:
Investigation (Items
1-5) and Discussion of the Site; Draft
Report
Lump Sum
120 days after issuance of
4. Santiago Mill and
Mine Phase 2:
History, Documentation
(Items 1-6); Final
Report
Lump Sum
120 days after issuance of
Option 2.
5. Vidler Tunnel Phase
1: Investigation
(Items 1-5) and
Discussion of the
Site; Draft Report
Lump Sum
120 days after issuance of
6. Vidler Tunnel Phase
2: History, Documentation
(Items 1-6); Final
Report
Lump Sum
120 days after issuance of
Total
File details come from the government source that posted it. Updated .