FP-03SPECS-REV6-26.doc
DOC document 177 KB Posted
- Attached to
- FOREST-WIDE ROAD MAINTENANCE Federal contract opportunity
- Solicitation number
- AG-8191-S-15-0022
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q A_07-30-2015.docx | DOCX document | |
| Sign_in_sheet.pdf | ||
| Amendment_0001_AG-8191-S-15-0022.pdf | ||
| Drawings.pdf | ||
| FIRE_PLAN.pdf | ||
| Past_Performance_Questionnaire.docx | DOCX document | |
| AG-8191-S-15-0022.pdf | ||
| 02579SEAlcoat-Rev.docx | DOCX document | |
| Wage_Determination.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STAND SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS (FP-03 U.S. CUSTOMARY UNITS) (2003)
The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03 U.S. Customary Units), 2003 are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
The 700-page book entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03 U.S. Customary Units), is available from:
Headquarters Washington DC David K. Green Construction Standards Engineer Internet: David.Green@fhwa.dot.gov Mail: Federal Highway Administration
HFPD-3
400 Seventh Street, SW Washington D.C. 20590 http://www.wfl.fha.dot.gov/design/specs/fp03.htm Applicable sections include (1) Sections designated in the following list and (2) Sections referenced therein.
| Section No. |
| Title |
| 101 |
| Terms, Format, and Definitions |
| 103 |
| Scope of Work |
| 104 |
| Control of Work |
| 105 |
| Control of Material |
| 106 |
| Acceptance of Work |
| 107 |
| Legal Relations and Responsibility to the Public |
| 109 |
| Measurement and Payment |
| 409 |
| Asphalt Surface Treatment |
| 414 |
| Asphalt Pavement Crack and Joint Sealing |
| 430 |
| Asphalt Pavement Patching |
| 634 |
| Permanent pavement Markings |
| 703 |
| Aggregate |
| 712 |
| Joint Material |
FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS TO THE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS
Forest service supplemental specifications (FSSS) may add to, delete from, or modify the Forest Service Standard Specifications (FP-03). FSSS are applicable to this project and are included in full text as an attachment listed in Section J.
FSSS SUPPLEMENTAL
TO FP-03
U.S. CUSTOMARY UNITS
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_04_04_2007
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
409 - Asphalt Surface Treatment
409.02_nat_us_05_12_2004
409.02 Material.
Add the following:
When designated, conform to applicable State department of transportation asphalt cement or emulsified asphalt requirements.
409.06_nat_us_05_12_2004
409.06 Weather.
Delete the first paragraph and replace with the following:
Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60 °F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.
409.06 Date & Time.
Add the following.
Construct fog seal and single-course surface treatments between August1 and September 30, 2015.
409.08_nat_us_06_21_2005
409.07 Production Start-up Procedures for Surface Treatments.
Delete the entire subsection.
409.08 Asphalt Application.
Add the following to the 3rd paragraph:
Ensure the length of spread is no more than what can be covered with aggregate within 1 minute of the asphalt application.
409.10 Fog Seal.
Add the following to the first paragraph:
Dilute by adding an equal amount of water to the emulsified asphalt. Do not cut the emulsified asphalt more than once.
409.11 Single Course Surface Treatments.
Add the following:
Do not permit traffic to travel over any Asphalt Surface Treatment until completion of rolling.
409.10_nat_us_08_12_2004
Delete Table 409-1 and substitute the following:
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment
Table 409-1
Approximate Quantities of Material for
Single-Course Surface Treatment
| Designation |
| ADVANCE \d 3Nominal Maximum Size of Aggregate |
| Aggregate Gradation (1) |
| Estimated Quantity of Aggregate (2) pounds/yd2 |
| Estimated Quantity of Emulsified Asphalt (3) gallons/yd2 |
| Estimated Quantity of Asphalt Binder (3) gallons/yd2 |
| 1A |
| 3/4 inch |
| B |
| 40 – 49 |
| 0.40 – 0.55 |
| 0.27 – 0.38 |
| 1B |
| 1/2 inch |
| C |
| 26 – 29 |
| 0.31 – 0.44 |
| 0.20 – 0.31 |
| 1C |
| 3/8 inch |
| D |
| 22 – 25 |
| 0.30 – 0.45 |
| 0.13 – 0.24 |
| 1D |
| No. 4 |
| E |
| 15 – 20 |
| 0.15 – 0.22 |
| 0.11 – 0.18 |
| 1E |
| Sand |
| F |
| 9 – 15 |
| 0.11 – 0.18 |
| 0.09 – 0.15 |
(1) See Table 703-7 for aggregate gradations.
(2) Aggregate masses are for aggregates having a bulk specific gravity of 2.65, as determined by AASHTO T 84 and
T 85. Make proportionate corrections when the aggregate furnished has a bulk specific gravity above 2.75 or below 2.55.
(3) Adjust the asphalt content for the condition of the road.
409.11_nat_us_12_18_2004
409.13_nat_us_05_13_2004
409.13 Acceptance.
Delete the 2nd paragraph and replace with the following:
Aggregate gradation for asphalt surface treatment will be evaluated under Subsection 106.04.
Table 409-4 Sampling and Testing Requirements.
Delete this section
NO TESTING IS REQUIRED
414 - Asphalt Pavement Crack and Joint Sealing
414.02_nat_us_05_12_2004
414.02 Material.
Add the following:
Backer Rod
712.01(g)
Low-modulus rubberized asphalt
712.01 (a) (7)
414.05_nat_us_05_12_2004
414.05 Crack Cleaning and Sealing.
Delete and replace with:
414.05 Asphalt Pavement Crack Sealing and Filling.
Crack seal and fill only when internal pavement temperatures are between 36 and 68 °F the road surface is dry, there is no frost in the road section, and the weather is not foggy or rainy.
Heat, mix, and apply the crack sealing and filling materials as recommended by the sealant manufacturer. Submit a copy of the manufacture’s recommendations to the CO prior to the start of work.
Prepare cracks between 1/4 inch and 1 inch and apply sealant by one of the following methods:
· Crack Sealing - Rout and clean all cracks between 1/4 inch and 1 inch wide. Rout cracks to produce a reservoir with straight ½ inch vertical walls and a 1 1/2 inch wide flat bottom. Use a low-modulus rubberized asphalt. Completely fill the routed cross section flush with the pavement surface.
· Crack Filling - Clean the crack between 1/4 inch and 1 inch wide. Prepare cracks to a depth of at least three times the crack width. Ensure crack sealing materials penetrates more than twice the crack width.
For cracks between 1/2 inch and 1 inch where sealant penetrates more than two times the crack width, use a backer rod.
For cracks with a width greater than or equal to 1 inch, clean and fill flush to the existing surface with asphalt mix according to Section 401, 402, 403, 404, or 417.
For cracks less than ¼ inch wide, clean and fill with CSS-1, SS-1, or joint sealant. Apply a sealant band less than 2 inches over the crack, such that the crack is centered under the band. Submit a copy of, and adhere to, the manufacture’s recommendations for heating and applying the joint sealant.
Clean cracks with a stream of air to remove all dirt, dust, or deleterious matter adhering to the crack walls or remaining in the crack cavity so that the crack is clean and dry when the sealant is applied. Blow or brush dry material off the pavement surface. Avoid damage to the adjacent pavement.
Use approved methods to protect all seal materials from being picked up by traffic. Treat seal material tracked onto the road surface as directed by the CO.
430 - Asphalt Pavement Patching
430.00_nat_us_07_27_2007
Description
430.01 This work consists of performing full depth patching, patching with geotextiles, skin patching, spray-injection patching, and removal and replacement of asphalt berms.
Material
430.02 Conform to the following Subsections:
| Minor Hot Asphalt Pavement |
| 404.02 |
| Asphalt Binder |
| 702.01 |
| Cutback Asphalt |
| 702.02 |
| Emulsified Asphalt |
| 703.03 |
| Application Temperatures |
| 702.04 |
| Aggregate |
| 703.07 (a) and (b) |
| Choker Aggregate |
| 703.12 |
| Geotextile Type VI |
| 714.01 |
| Sand |
| 703.15 |
Construction
430.03 Composition of Mix (Job-Mix Formula). Furnish Minor Hot Asphalt Pavement as approved by the CO.
430.04 Full Depth Patch.
Remove material to a minimum depth of 4 inches, or as necessary to reach firm support. If firm support for a patch is unavailable, notify the CO prior to placing any material.
Trim or mill the edges of the prepared hole to form a vertical face in un-fractured asphalt surfacing. Make the prepared hole rectangular, and clean it of all loose material. When the hole is dry, apply emulsified asphalt to the bottom and faces of the hole. Barricade prepared sites. Patch the sites immediately after the emulsified asphalt breaks. Place the asphalt concrete mixture in layers not exceeding 4 inches. Thoroughly compact each layer with hand or mechanical tampers or rollers. For hot asphalt concrete mixtures, compact the mix while it is above 230 °F.
Compact the finished surface with a steel-wheel roller or vibratory plate compactor. Ensure that the compacted patch is approximately 1/8 to 1/4 inches above the level of the adjacent pavement. Seal the edges of the completed patch with emulsified asphalt, and blot with fine sand.
430.05 Patching with Geotextile. (Deleted)
430.06 Skin Patches. Prepare the surface on which the skin patch is placed by cleaning the surface, removing vegetation, and filling all cracks more than 1/4 inch wide with an approved crack-filling material. Remove excess crack-filling material. (At Granite Basin only: Mill edges to a depth of 1”.) Spray the surface with emulsified asphalt.
430.07 Spray-Injection Patching. (Deleted)
430.08 Asphalt Berm. (Deleted)
430.09 Waste Material. Dispose of all materials removed from potholes and patches and dispose of off Forest Service land.
430.10 Acceptance. Asphalt concrete mixtures will be evaluated under Subsections 106.02 and 106.03.
Measurement
430.11 Measure the Section 430 items listed in the bid schedule according to Subsection 109.02.
Payment
430.12 The accepted quantities will be paid at the contract unit price per unit of measurement for Section 430 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05
703 - Aggregate
703.05_nat_us_12_07_2006
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation
Table 703-2
(2) Liquid limit, AASHTO T 89
25 max.
(3) Plastic limit, AASHTO T 90
Nonplastic
(4) Los Angeles abrasion, AASHTO T 96
40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210
35 min.
(7) Durability index (fine), AASHTO T 210
(8) Fractured faces, ASTM D 5821
50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation
Table 703-3
(2) Liquid limit, AASHTO T 89
35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12%
2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96
40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210
(7) Durability index (fine), AASHTO T 210
(8) Fractured faces, ASTM D 5821
75% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradtion
Table 703-16
(2) Plastic Index, AASHTO T 90
Less than 9
(3) Los Angeles abrasion, AASHTO T 96
55% max.
(4) Free from organic matter and lumps or balls of clay.
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following:
Table 703-2
Target Value Ranges for Subbase and Base Gradation
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
| Grading Designation |
| E (Base) |
| 62 – 90 (6) |
| 36 – 74 (6) |
| 12 – 26 (4) |
| 4.0 – 7.0 (3) |
( ) The value in the parentheses is the allowable deviation (() from the target values..
D (Base)
| 100 |
| 86 – 100 (6) |
| 51 – 82 (6) |
| 36 – 64 (6) |
| 12 – 26 (4) |
| 4.0 – 7.0 (3) |
C (Base)
| 80 – 100 (6) |
| 64 – 94 (6) |
| 40 – 69 (6) |
| 31 – 54 (6) |
4.0 –7.0 (3)
B (Subbase)
| 100 |
| 97 – 100 |
40 – 60 (8)
4.0 – 12.0 (4)
| A (Subbase) |
| 100 |
| 97 – 100 |
65 – 79 (6)
45 – 59 (7)
| 28 – 42 (6) |
| 9 – 17 (4) |
| 4.0 – 8.0 (3) |
| Sieve Size |
| 2½ inch |
| 2 inch |
| 1½ inch |
| 1 inch |
| 3/4 inch |
| 1/2 inch |
| 3/8 inch |
| No. 4 |
| No. 40 |
| No. 200 |
Delete Table 703-3 and replace with the following:
Table 703-3
Target Value Ranges for Surface Gradation
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
| Grading Designation |
| U |
| 71 – 90 (6) |
| 50 – 68 (7) |
| 34 – 51 (6) |
| 19 – 30 (5) |
| 8.0 – 15.0 (4) |
( ) The value in the parentheses is the allowable deviation (() from the target values.
If the plasticity index (PI) is greater than 0, the TV range for the No. 200 sieve size is 8-12 (4).
T
71 – 91 (6)
| 43 – 60 (7) |
| 30 – 46 (6) |
| 16 – 28 (5) |
| 8.0 – 15.0 (4) |
| S |
| 100 |
| 72 – 92 (6) |
| 51 – 71 (6) |
| 36 – 53 (7) |
| 26 – 40 (6) |
| 14 – 25 (5) |
| 8.0 – 15.0 (4) |
H
97 - 100
| 80 – 92 (6) |
| 58 – 70 (7) |
| 28 – 40 (6) |
| 16 – 26 (5) |
| 9.0 – 14.0 (4) |
G
| 100 |
| 97 - 100 |
| 70 – 80 (6) |
| 51 – 63 (7) |
| 28 – 39 (6) |
| 19 – 27 (5) |
| 10.0 – 16.0 (4) |
| F |
| 100( |
| 97-100 |
| 76-89 (6) |
| 56-68 (6) |
| 43-53 (7) |
| 23-32 (6) |
| 15-23 (5) |
| 10.0-16.0 (4) |
| Sieve Size |
| 1 1/2 inch |
| 1 inch |
| 3/4 inch |
| 1/2 inch |
| 3/8 inch |
| No. 4 |
| No. 8 |
| No. 16 |
| No. 40 |
| No. 200 |
Add Table 703-16:
Table 703-16
Gradation Requirements for Screened Aggregate
| Sieve Size |
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
Grading Designation
| L |
| M |
| N |
| O |
| P |
| Q |
| R |
| 6 inch |
| 100 |
| 100 |
4 inch
| 100 |
| 100 |
3 inch
| 100 |
| 100 |
2 inch
No. 4
15-45
15-45
15-45
703.06_nat_us_03_02_2005
703.10(e) Flakiness Index.
Delete and replace with the following:
Flakiness Index, FLH T 508
30% max.
703.10(i) Adherent Coating.
Add the following:
Adherent coating on the aggregate, FLH T 512
0.5% max.
703.07_nat_us_03_02_2005
Table 703-2 Correction
Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
Table 703-2 Correction
Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
703.10_nat_us_03_02_2005
Delete Table 703-7 and substitute the following:
Table 703-7 Target Value Ranges
Table 703‑7
Target Value Ranges for
Single and Multiple Course Surface Treatment Aggregate Gradation
| Sieve |
| Percent by Mass Passing Designated Sieve |
(AASHTO T 27 & T 11)
Size
Grading Designation
| A |
| B |
| C |
| D |
| E |
| F |
| 1½ inch |
| 100(1) |
| 1 inch |
| 90-100(3) |
| 100(1) |
| ¾ inch |
| 0-35(5) |
| 90-100(3) |
| 100(1) |
| ½ inch |
| 0-8(3) |
| 0-35(5) |
| 90-100(3) |
| 100(1) |
| ⅜ inch |
| — |
| 0-12(3) |
| 0-35(5) |
| 85-100(3) |
| 100(1) |
| 100(1) |
| No. 4 |
| — |
| — |
| 0-12(3) |
| 0-35(5) |
| 85-100(3) |
| 85-100(1) |
| No. 8 |
| — |
| — |
| — |
| 0-8(3) |
| 0-23(4) |
| — |
| No. 200 |
| 0-1(1) |
| 0-1(1) |
| 0-1(1) |
| 0-1(1) |
| 0-1(1) |
| 0-10(1) |
ADVANCE \d 4(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation (() from the target values.
712 - Joint Material
712.01_nat_us_03_02_2005
712.01 Sealants, Fillers, Seals, and Sleeves.
(a) Joint sealants and crack fillers.
Add the following:
(7) Low-Modulus Rubberized Asphalt. Conform to ASTM D 3405 and the following.
| Cone Penetration, 75oF |
| 100-150 |
| Cone Penetration, -0oF |
| 25 minimum |
Flow, 140oF, 5h
3/8 in. maximum
| Resilience |
| 30-60% |
| Bond, -20oF, 200% extension |
| Pass 3 Cycles |
| Recommended Pour Temperature |
| 380oF |
| Safe Heating Temperature |
| 410oF |
| Asphalt Compatibility |
| Pass |