Attachment_A_Specifications.pdf

PDF 2 MB Posted

Attached to
Replace HVAC System Federal contract opportunity
Solicitation number
AG-63A9-S-16-0006
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Attachment A Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Replace HVAC System, newest first.
File Type Posted
MIFC_HVAC_Schedule_of_Items_Rev2.pdf PDF
AG-63A9-S-16-0006_SOL.pdf PDF
Attachment_B_Drawings.pdf PDF
Attachment_C_Wage_Rates.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15031 / MN Interagency Fire Center 00 01 01 - 1

PROJECT TITLE PAGE

SECTION 00 01 01

PROJECT TITLE PAGE

PROJECT MANUAL

FOR

Minnesota Interagency Fire Center

HVAC Modifications 402 Southeast 11th Street

Grand Rapids, Minnesota 55744

ENGINEER:

Foster, Jacobs & Johnson, Inc.

525 Lake Avenue South

Suite 222

Duluth, Minnesota 55802

ARCHITECT:

DSGW Architects

2 West First Street

Suite 201

Duluth, Minnesota 55802

DATE: October 2nd, 2015

END OF SECTION

15031 / MN Interagency Fire Center 00 01 05 - 1

CERTIFICATIONS PAGE

SECTION 00 01 05

CERTIFICATIONS PAGE

I HEREBY CERTIFY THAT THIS SPECIFICATION WAS PREPARED BY ME OR UNDER MY DIRECT

SUPERVISION AND THAT I AM A DULY REGISTERED ENGINEER UNDER THE LAWS OF THE

STATE OF MINNESOTA.

CHARLES JACOBS

Minnesota Registration No: 22089 DATE: October 2nd, 2015

I HEREBY CERTIFY THAT THIS SPECIFICATION WAS PREPARED BY ME OR UNDER MY DIRECT

SUPERVISION AND THAT I AM A DULY REGISTERED ENGINEER UNDER THE LAWS OF THE

STATE OF MINNESOTA.

ROBERT S. JONES

Minnesota Registration No: 25389 DATE: October 2nd, 2015

15031 / MN Interagency Fire Center 00 01 10 - 1

TABLE OF CONTENTS

SECTION 00 01 10

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 00 01 01 - Project Title Page

B. 00 01 05 – Certifications Page

C. 00 01 10 - Table of Contents

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 01 10 00 - Summary

2.06 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

A. 06 10 00 – Rough Carpentry

2.07 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

A. 07 53 00 – Elastomeric Membrane Roofing

2.09 DIVISION 09 -- FINISHES

A. 09 51 00 – Acoustical Ceilings

2.16 DIVISION 22 -- PLUMBING

A. 22 00 01 – General Provisions

B. 22 10 05 - Plumbing Piping

2.17 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

A. 23 00 11 – General Provisions

B. 23 05 93 - Testing, Adjusting, and Balancing for HVAC

C. 23 07 13 - Duct Insulation

D. 23 09 23 – Direct Digital Control System

E. 23 31 00 - HVAC Ducts and Casings

F. 23 33 00 - Air Duct Accessories

G. 23 34 23 - HVAC Power Ventilators

H. 23 36 00 - Air Terminal Units

I. 23 37 00 - Air Outlets and Inlets

J. 23 73 13 – Roof Top Units

K. 23 81 27 - Small Split-System Heating and Cooling

2.18 DIVISION 26 -- ELECTRICAL

A. 26 05 01 - Minor Electrical Demolition

B. 26 05 19 - Low-Voltage Electrical Power Conductors and Cables

C. 26 05 26 - Grounding and Bonding for Electrical Systems

D. 26 05 29 - Hangers and Supports for Electrical Systems

E. 26 05 34 - Conduit

G. 26 05 37 - Boxes

H. 26 05 53 - Identification for Electrical Systems

I. 26 09 23 - Lighting Control Devices

J. 26 24 16 - Panelboards

15031 / MN Interagency Fire Center 00 01 10 - 2

K. 26 27 17 - Equipment Wiring

L. 26 27 26 - Wiring Devices

M. 26 28 13 - Fuses

N. 26 28 18 - Enclosed Switches

O. 26 51 00 - Interior Lighting

15031 / MN Interagency Fire Center 01 10 00 - 1

SUMMARY

SECTION 01 10 00

PART 1 GENERAL

1.01 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price in the Agreement Form.

B. The work of each separate prime contract is identified in this section and on the Drawings.

1.02 PROJECT SCOPE DESCRIPTION

A. The project scope includes selective demolition of the existing ventilation system and replacement with new. This work will entail removal of roof top units, roof cutting and patching, electrical circuit replacement, new electrical panels and a like.

1. Additionally, the ventilation work necessitates ceiling work. As part of the project, ceiling removal will be required. The scope of ceiling removal, reinstallation or replacement is described below.

2. Devices in the ceiling system will either be removed and reinstalled or removed and replaced. This scope expands to include new lighting.

1.03 A PRE-BID MEETING AND TOUR WILL BE HELD AS DESCRIBED IN SOLICITATION

1.04 NO SUBSTITUTIONS WILL BE ALLOWED DURING BIDDING

1.05 BASE BID DESCRIPTION:

A. GENERAL CONSTRUCTION

1. Ceiling removal and reinstallation EXCEPT in room 201.

2. Roof cutting, patching reinforcement, sleepers, curbs EXCEPT as associated with HVAC in room 201.

B. FIRE PROTECTION

1. Protect existing sprinkler heads, remove & reinstall escutcheons EXCEPT in room 201.

C. HVAC

1. Ventilation replacement throughout as shown on drawings EXCEPT in room 201.

D. ELECTRICAL

1. Ceiling device removal and reinstallation including but not limited to lights, speakers, fire alarm, Wi-Fi devices EXCEPT in room 201.

1.06 DESCRIPTION OF Optional (alternate) WORK

A. Each option stands on its own and is not dependent on any other optional price or work.

B. Selection of Add Options are at the behest of the U.S. Forest Service applicable

1.07 ADD OPTION (May be referred to as an alternate elsewhere) NO. 1

A. GENERAL CONSTRUCTION

1. Ceiling removal and reinstallation in room 201.

2. Roof cutting, patching, reinforcement, sleepers, curbs associated with HVAC serving room 201.

B. FIRE PROTECTION

1. Protect existing sprinkler heads, remove & reinstall escutcheons in room 201

C. HVAC

1. Ventilation replacement of system serving room 201.

D. ELECTRICAL

15031 / MN Interagency Fire Center 01 10 00 - 2

1. Ceiling device removal and reinstallation including but not limited to lights, speakers, fire alarm, Wi-Fi devices in room 201.

1.08 ADD OPTION (May be referred to as an alternate elsewhere) NO. 2

A. GENERAL CONSTRUCTION

1. Ceiling removal and REPLACEMENT, EXCEPT in room 201.

B. FIRE PROTECTION

1. Same as base bid - no additional work.

C. HVAC

1. Same as base bid - no additional work.

D. ELECTRICAL

1. Lighting replacement EXCEPT in room 201.

1.09 ADD OPTION (May be referred to as an alternate elsewhere) NO.3

A. GENERAL CONSTRUCTION

1. Ceiling removal REPLACEMENT in all areas indicated.

2. Roof cutting, patching, reinforcement, sleepers, curbs associated with HVAC serving room 201.

B. FIRE PROTECTION

1. Protect existing sprinkler heads, remove & reinstall escutcheons in room 201

C. HVAC

1. Ventilation replacement of system serving room 201.

D. ELECTRICAL

1. Ceiling device removal and REPLACEMENT including but not limited to speakers, fire alarm, Wi-Fi devices.

2. REPLACEMENT of lighting throughout, including room 201.

1.10 ADD OPTION (May be referred to as an alternate elsewhere) NO.4

1. Clean ductwork not being replaced as indicated in section 23 01 30.51.

1.11 OPTIONS (ALTERNATES) ARE SELECTED AT THE BEHEST OF THE GOVERNMENT

1.12 DEFINITIONS

1. ENGINER: Foster, Jacobs and Johnson.

2. OWNER: U.S. Department of Agriculture.

3. INSPECTOR: Owners designated representative.

4. CO: Contracting Officer.

5. COR: Contracting Officer Representative.

1.13 THE SUCCESSFUL CONTRACTOR WILL BE RESPONSIBLE FOR ALL WORK AND

MATERIALS. THIS IS A BUY AMERICIAN PROJECT AND ALL MATERIALS SHALL

MEET ALL NAFTA REQUIREMENTS.

1.14 WORK BY OWNER

A. None

15031 / MN Interagency Fire Center 01 10 00 - 3

1.15 OWNER OCCUPANCY

A. Owner intends to continue to occupy adjacent portions of the existing building during the entire construction period.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

1.16 CONTRACTOR USE OF SITE AND PREMISES

A. Arrange use of site and premises to allow:

1. Owner occupancy.

B. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

15075 / MN Inter Agency Fire Center 06 10 00 - 1 ROUGH CARPENTRY Grand Rapids, Minnesota

SECTION 06 10 00

ROUGH CARPENTRY

PART 1 GENERAL

1.01 SECTION INCLUDES

A. All wood support blocking & miscellaneous framing.

1.02 RELATED SECTIONS

A. Section 07 53 00 – Elastomeric Membrane Roofing.

1.03 REFERENCES

A. ASTM A 153 - Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware;

2004.

B. WWPA G-5 - Western Lumber Grading Rules; Western Wood Products Association; 2005.

C. International Building Code and the State of Minnesota Building Code.

1.04 QUALITY ASSURANCE

A. Lumber: Comply with PS 20 and approved grading rules and inspection agencies.

1.05 DELIVERY, STORAGE, AND HANDLING

A. General: Cover wood products to protect against moisture. Support stacked products to prevent deformation and to allow air circulation.

PART 2 PRODUCTS

2.01 GENERAL REQUIREMENTS

A. Lumber fabricated from old growth timber is not permitted.

2.02 DIMENSION LUMBER

A. Grading Agency: Western Wood Products Association (WWPA).

B. Sizes: Nominal sizes as indicated on drawings, S4S.

C. Moisture Content: S-dry or MC19.

D. Miscellaneous Blocking, Furring, and Nailers:

1. Lumber: S4S, No. 2 or Standard Grade.

2. Boards: Standard or No. 3.

3. Species: Spruce Pine Fir, (SPF).

2.03 ACCESSORIES

A. Fasteners and Anchors:

1. Screw Anchors (Steel Stud Framing): Galvanized, #12 round head wood screws, sized to provide minimum 1-1/4” penetration.

2. Anchors: Expansion shield and lag bolt type for anchorage to solid masonry or concrete.

Bolt or ballistic fastener for anchorages to steel.

PART 3 EXECUTION

3.01 INSTALLATION

A. Install framing and blocking as shown on drawings or as required for support of equipment.

1. Set members level and plumb, in correct position.

2. Place horizontal members flat, crown side up.

15075 / MN Inter Agency Fire Center 06 10 00 - 2 ROUGH CARPENTRY Grand Rapids, Minnesota

3. Coordinate curb installation with mechanical contractor.

4. Construct curb members of single pieces.

3.02 FASTENING

A. All fastenings shall be as detailed & as required to meet or exceed the requirements of the International Building Code.

B. Sub-drill wood per fastener manufacturer’s recommendations.

15075 / MN Inter Agency Fire Center 07 53 00 - 1 ELASTOMERIC MEMBRANE ROOFING Grand Rapids, MN

SECTION 07 53 00

ELASTOMERIC MEMBRANE ROOFING

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Cutting and patching of existing roof and new and removed items.

B. Elastomeric roofing membrane, ballasted conventional application.

C. Metal deck infill.

D. Insulation.

E. Vapor retarder.

F. Flashings.

G. Roofing stack boots.

1.02 RELATED REQUIREMENTS

A. Section 06 10 00 - Rough Carpentry: Wood support framing and nailers.

1.03 REFERENCE STANDARDS

A. ASTM C1289 - Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board; 2013.

B. ASTM D412 - Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers- Tension; 2006a.

C. ASTM D624 - Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomers; 2000 (Reapproved 2012).

D. ASTM D4637/D4637M - Standard Specification for EPDM Sheet Used in Single-Ply Roof Membrane; 2013.

E. NRCA ML104 - The NRCA Roofing and Waterproofing Manual; National Roofing Contractors Association; Fifth Edition, with interim updates.

F. SPRI RP-4 - Wind Design Standard for Ballasted Single-Ply Roofing Systems; Single Ply Roofing Institute; 2008 (ANSI/SPRI RP-4).

1.04 QUALITY ASSURANCE

A. Perform work in accordance with NRCA Roofing and Waterproofing Manual and membrane manufacturer's instructions.

1.05 PROJECT CONDITIONS

A. Coordinate the work with installation of associated curbs, flashings, etc. installed by other sections as the work of this section proceeds.

1.06 FIELD CONDITIONS

A. Do not apply roofing membrane during unsuitable weather.

B. Do not apply roofing membrane to damp or frozen deck surface or when precipitation is expected or occurring.

C. Do not expose materials vulnerable to water or sun damage in quantities greater than can be weatherproofed the same day.

1.07 WARRANTY

A. Provide two year contractor’s material and labor warranty to cover failure to prevent penetration of water.

15075 / MN Inter Agency Fire Center 07 53 00 - 2 ELASTOMERIC MEMBRANE ROOFING

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. EPDM Membrane Materials:

1. Carlisle Roofing Systems, Inc.

2. Firestone Building Products, LLC

3. GenFlex Roofing Systems, LLC

4. Versico.

5. Johns Manville.

6. Substitutions: See Administrative Requirements.

2.02 ROOFING - BALLASTED APPLICATIONS

A. Elastomeric Membrane Roofing: One ply membrane loose-laid over insulation and vapor retarder with ballast.

B. Roofing Assembly Requirements:

1. Insulation Thickness: As shown on drawings. Verify on drawings if insulation thickness refers to minimum amount of flat insulation or total thickness including tapered insulation.

D. Ballast: Reuse existing.

2.03 ROOFING MEMBRANE AND ASSOCIATED MATERIALS

A. Membrane: Ethylene-propylene-diene-terpolymer (EPDM); non-reinforced; complying with minimum properties of ASTM D 4637.

1. Thickness: 0.045 inch.

2. Color: Black.

B. Seaming Materials: Double faced tape system.

C. Vapor Retarder: Cross laminated polyethylene vapor retarder; compatible with roofing and insulation materials.

1. Tape seams with seaming tape or as furnished bt the vapor retarder manufacturer.

2. ASTM 1745 Class C.

3. Vapor permeability: 0.045 perm inch, measured in accordance with ASTM E 96, Method A.

4. Puncture Resistance: ASTM D1709, Method B - 1.19 lb.

5. Tensile Strength: ASTM E154 - 6960 psi.

6. Vapor as manufactured by the following are considered equal:

a. Reef Industries: Griffolyn Type - 65; phone 800-231-6074.

b. Sto-Cote Products, Inc.: Tu-Tuf; phone 888-786-2683.

c. Barrier-Bac Inc.: Barrier Bac 250, phone 877-237-2841.

d. Stego Industries, LLC: Stego Wrap 10 mil Class C, phone 877-946-0797.

D. Flexible Flashing Material: Same material as membrane;

2.04 INSULATION

A. Polyisocyanurate Board Insulation: (Flat and/or Tapered) Rigid cellular foam, complying with ASTM C 1289, and with the following characteristics:

1. Facing: Fiberglass mat facing each face.

2. Board Size: 48 x 96 inch.

3. Thermal Resistance: R-value of 5.56 per inch.

4. Board Edges: Square.

2.05 BALLAST MATERIALS

A. Aggregate: Salvage and reuse existing.

B. Ballast Underlayment: Polyester felt type.

C. Walkway Pads: 2’ x 3’ x 3/8” flexible rubber pads with manufacturers recommended seaming tape.

15075 / MN Inter Agency Fire Center 07 53 00 - 3 ELASTOMERIC MEMBRANE ROOFING

2.06 ACCESSORIES

A. Metal Roof Decking: Match the profile of the existing, minimum 20 gauge. See plan notes.

B. Stack Boots: Prefabricated flexible boot and collar for pipe stacks through membrane; same material as membrane.

C. Membrane Adhesive: As recommended by membrane manufacturer seams shall be seamed with double faced tape.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that surfaces and site conditions are ready to receive work.

B. Verify deck is supported and secure.

C. Verify deck is clean and smooth, flat, free of depressions, waves, or projections, properly sloped and suitable for installation of roof system.

D. Verify deck surfaces are dry and free of snow or ice.

E. Verify that roof openings, curbs, and penetrations through roof are solidly set, and nailing strips are in place.

3.02 PREPARATION

A. At new roof curbs (and removals) carefully pull back existing ballast rock to expose cut/patch area.

B. At new penetrations cut membrane and insulation to suite new items, install 6x6x12’ wood beams and 2x6 wood flat, built up to the top of the wood beams and suitable to accept new roof curbs, etc as provided by the mechanical contractor.

C. At new and removed existing items install/reinstall insulation so flush with the top of the existing to meet the requirements of 3.02.

3.02 VAPOR RETARDER AND INSULATION - UNDER MEMBRANE

A. Apply vapor retarder to deck surface at infill areas in accordance with manufacturer's instructions.

1. Unroll vapor retarder with the longest dimension of the area to be roofed for that days work with enough left over to provide a lap for the next section to be roofed and pull out the folds to the the full width of the product.

2. Lap vapor barrier up the edge of intersecting walls and parapets to the height of the roof insulation.

3. Holes or tears in the insulation shall be patched with a section of vapor retarder lapped as recommended by the manufacturer and sealed with sealing tape.

4. All joints shall be sealed with tape or sealant supplied by the manufacturer. Vapor barrier shall be sealed tight to all penetrations through the roof deck.

B. Ensure vapor retarder is clean and dry, continuous, and ready for application of insulation.

C. Lay subsequent layers of insulation with joints staggered minimum 6 inch from joints of preceding layer. Insulation shall be installed in a minimum of 2 layers.

D. Lay boards with edges in moderate contact without forcing. Cut insulation to fit neatly to perimeter blocking and around penetrations through roof.

3.03 MEMBRANE APPLICATION

A. Patch existing membrane at removed items to meet the above requirements.

B. Roll out membrane, free from wrinkles or tears. Place sheet into place without stretching.

C. Overlap edges and ends and seal seams by contact adhesive, minimum 3 inches. Seal permanently waterproof. Apply uniform bead of sealant to joint edge.

D. At intersections with vertical surfaces:

15075 / MN Inter Agency Fire Center 07 53 00 - 4 ELASTOMERIC MEMBRANE ROOFING

1. Extend membrane up a minimum of 10 inches onto vertical surfaces.

2. Fully adhere flexible flashing over membrane and up to reglets.

E. Around roof penetrations, seal flanges and flashings with flexible flashing.

F. Flash new items installed through existing roofing to meet the above requirements.

G. Install walkway pads using sealing tape per manufacturer’s instructions.

3.04 BALLAST INSTALLATION

A. Install new ballast underlayment. Suitably lap joints to prevent spread.

B. Re-spread existing ballast at new/removed items and as otherwise required.

3.05 PROTECTION

A. Protect installed roofing and flashings from construction operations.

B. Where traffic must continue over finished roof membrane, protect surfaces using durable materials.

15075 / MN Inter Agency Fire Center 09 51 00 - 1 ACOUSTICAL CEILINGS

SECTION 09 51 00

ACOUSTICAL CEILINGS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Removal and reinstallation of existing suspended metal grid ceiling system and acoustical units.

B. New suspended metal grid ceiling system and acoustical units per Alternate Bids.

1.02 REFERENCES

A. ASTM C 635 - Standard Specification for the Manufacture, Performance, and Testing of Metal Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings.

B. ASTM C 636 - Standard Practice for Installation of Metal Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels.

C. ASTM E 580 - Standard Practice for Application of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Requiring Seismic Restraint.

D. ASTM E 1264 - Standard Classification for Acoustical Ceiling Products.

1.03 SUBMITTALS

A. Product Data: Provide data on metal grid system components, acoustical units, etc.

B. Manufacturer’s Installation Instructions: Indicate special procedures, perimeter conditions requiring special attention, etc.

1.04 QUALIFICATIONS

A. Grid Manufacturer: Company specializing in manufacturing the Products specified in this section with minimum five years documented experience.

B. Acoustical Unit Manufacturer: Company specializing in manufacturing the Products specified in this section with minimum five years documented experience.

C. Installer: Company with three years minimum documented experience.

1.05 ENVIRONMENTAL REQUIREMENTS

A. Maintain uniform temperature of minimum 60 degrees F and maximum humidity of 40 percent prior to, during, and after acoustical unit installation.

1.06 COORDINATE

A. Coordinate all ceiling work with the mechanical and electrical contractors.

B. Ensure acoustical ceilings are not installed until overhead work is completed, tested and approved.

1.08 EXTRA MATERIALS

A. Base Bid:

1. Furnish 1,200 square feet of new Type 1 Acoustical Units in Base Bid. In areas where replacement acoustical units are required remove the existing tiles for reuse elsewhere and re-tile the entire space with new Type 1 Acoustical Units. (It is assumed that new units will be used in small spaces such as offices, etc. and their removal units would be used as infill in larger areas.)

2. In Alternate Bid #1; carefully remove and care for the existing acoustical units in Conference Room 201 (if existing units are damaged, the entire ceiling must be re-padded to avoid a change of tile color or texture in the room.).

15075 / MN Inter Agency Fire Center 09 51 00 - 2 ACOUSTICAL CEILINGS

3. Under Alternate Bid #2; furnish 2 percent attic stock of new Type 1 acoustical units in original packaging.

4. Under Alternate Bid #3, furnish 4 percent attic stock of new Type 2 acoustical units in original packaging.

PART 2 PRODUCTS

2.01 ACOUSTICAL UNITS

A. Manufacturers:

1. USG Interiors, Inc.: www.usg.com.

2. Substitutions: See General Conditions.

B. Acoustical Units - General: ASTM E 1264, Class A.

C. Acoustical Panels (Type 1): ASTM E 1264 Type III, Painted mineral fiber, conforming to the following:

1. Size: 24 x 48 inches.

2. Thickness: 5/8 inch.

3. Composition: Wet felted mineral fiber.

4. Edge: Square

5. Surface Color: White.

6. Surface Pattern: Fissured.

7. Product: USG, Radar Clima-Plus #2410.

8. Suspension System: Exposed grid.

D. Acoustical Panels (Type 2): ASTM E 1264 Type III, Painted mineral fiber, conforming to the following:

1. Size: 24 x 48 inches.

2. Thickness: 3/4 inch.

3. Composition: Wet felted mineral fiber.

4. Edge: Square

5. Surface Color: White.

6. Surface Pattern: Fine Textured.

7. Product: USG, Eclipse ClimaPlus #78578.

8. Suspension System: Exposed grid.

2.02 SUSPENSION SYSTEM(S)

A. Manufacturers:

1. USG Corporation; Product Donn DX: www.usg.com.

2. Substitutions: See General Conditions.

B. Suspension Systems - General: ASTM C 635; die cut and interlocking components, with stabilizer bars, clips, splices, perimeter moldings, and hold down clips as required.

C. Exposed Steel Suspension System: Formed steel, commercial quality cold rolled; Intermediate-duty.

1. Profile: Tee; 15/16 inch wide face.

2. Construction: Double web.

3. Finish: White painted.

2.03 ACCESSORIES

A. Hanger Wires: Minimum 12 gauge.

B. Support Channels and Hangers: Galvanized steel; size and type to suit application, seismic requirements, and ceiling system flatness requirement specified.

C. Perimeter Moldings: Same material and finish as grid.

1. At Exposed Grid: Provide L-shaped molding for mounting at same elevation as face of grid.

15075 / MN Inter Agency Fire Center 09 51 00 - 3 ACOUSTICAL CEILINGS

D. Touch-up Paint: Type and color to match acoustical and grid units.

E. Wall Top Extensions: 24 gauge prefinished sheet metal formed as detailed. Equal to Firestone

– Una-Clad; Bone White.

PART 3 EXECUTION

3.01 PREPARATION

A. Base Bid and Alternate Bid No. 1: Carefully remove existing acoustical panels and grid as required to carry out new construction and allow their reinstallation. Store in a suitable location to prevent damage to components to be reused.

B. Alternate Bids No’s 2 & 3: Remove existing acoustical ceiling systems in their entirety.

C. Legally dispose of removed materials not to be reinstalled.

3.02 EXAMINATION

A. Verify that layout of hangers will not interfere with other work.

3.03 INSTALLATION - SUSPENSION SYSTEM

A. Install new or reinstalled suspension system in accordance with ASTM C 636, ASTM E 580, and manufacturer's instructions and as supplemented in this section.

1. Main runners shall be installed 48 inches on center along the main runners. Hanger wires shall be wrapped tightly at least three full turns.

2. Main runners shall be interconnected by cross tees 48 inches long to form 2’-0” x 4’-0” modules. Proper length cross tees shall also be installed adjacent to all recessed light fixtures on each side not supported by a main runner.

3. This Contractor shall provide additional tees where required for the installation of lay-in lighting fixtures, which are not of full 2’ x 2’ or 2’ x 4’ dimension. Coordinate with electrical contractor and drawings.

B. Rigidly secure system, including integral mechanical and electrical components, for maximum deflection of 1:360.

C. Install after major above-ceiling work is complete. Coordinate the location of hangers with other work.

D. Hang suspension system independent of walls, columns, ducts, pipes and conduit. Where carrying members are spliced, avoid visible displacement of face plane of adjacent members.

E. Where ducts or other equipment prevent the regular spacing of hangers, reinforce the nearest affected hangers and related carrying channels to span the extra distance.

F. Do not support components on main runners or cross runners if weight causes total dead load to exceed deflection capability.

G. Support fixture loads using supplementary hangers located within 6 inches of each corner, or support components independently.

H. Do not eccentrically load system or induce rotation of runners.

I. Perimeter Molding: Install at intersection of ceiling and vertical surfaces and at junctions with other interruptions.

1. Use longest practical lengths.

2. Overlap and rivet corners.

3.03 INSTALLATION - ACOUSTICAL UNITS

A. Install (reinstall) acoustical units in accordance with manufacturer's instructions.

1. Lay directional patterned units per reflected ceiling plans or as otherwise approved by

Architect.

15075 / MN Inter Agency Fire Center 09 51 00 - 4 ACOUSTICAL CEILINGS

B. Fit acoustical units in place, free from damaged edges or other defects detrimental to appearance and function.

C. Install units after above-ceiling work is complete.

D. Install acoustical units level, in uniform plane, and free from twist, warp, and dents.

E. Cutting Acoustical Units:

1. Make field cut edges of same profile as factory edges.

3.04 ERECTION TOLERANCES

A. Maximum Variation from Flat and Level Surface: 1/8 inch in 10 feet.

B. Maximum Variation from Plumb of Grid Members Caused by Eccentric Loads: 2 degrees.

3.05 SCHEDULE - As Per Drawings

A. Type 1 Panels: All locations except Conference 201.

B. Type 2 Panels: In Conference 201.

15031 / MN Interagency Fire Center 22 00 11 - 1

GENERAL PROVISIONS

SECTION 22 00 11

PART 1 GENERAL

1.01 CONDITIONS OF THE CONTRACT

A. The Conditions of the Construction Contract and applicable provisions of Division l - General Requirements, as well as these General Provisions, shall apply to all Sections of Division 22.

1.02 SCOPE

A. The work to be done under this Division of the Specifications shall include the furnishing of all labor, materials, equipment and services necessary for the proper completion of all of the mechanical work as shown on the drawings and herein specified.

B. In general, this shall include the furnishing and installing of all fire protection, plumbing, heating, refrigeration, ventilation, and temperature control systems, complete with auxiliaries, as may be required to make a complete and properly operating installation.

C. Only such items as are hereinafter specified or indicated on the drawings to be furnished by others, shall be considered to be furnished by others. All other items are to be considered as a part of this Contract, and shall be so bid.

D. The omission of specific reference to any parts necessary to, or reasonably incidental to, a complete installation shall not be construed as releasing the Contractor from furnishing and installing same.

E. Applicable provisions of the following sections shall apply to all sections for Mechanical Work.

1.03 DEFINITIONS

A. Provide: Under this Contract, Contractor shall furnish and install item or items specified.

Contractor shall perform all labor and furnish all materials and equipment necessary to that specified item or system will be complete and operational in every respect.

B. Furnish: Under this Contract, Contractor shall deliver to the site item(s) specified, as well as additional specialized materials and/or accessories necessary for the use and operation of item or items specified.

C. Install: Under this Contract, Contractor shall set in position, connect (including sub-assemblies furnished), and adjust for use. Contractor shall furnish miscellaneous specialty items such as hangers, valves, unions, piping, sheet metal, etc., as obviously necessary for a complete and operating installation.

1.04 DRAWINGS

A. In general, the drawings of the Mechanical Systems and Equipment are to scale, however, to determine exact locations of walls and partitions, the Contractor shall consult the Architectural and/or Structural Drawings which are dimensioned. Drawings shall not take precedence over field measurements. Plans of piping and ductwork, although shown on scale drawings, are diagrammatic only. They are intended to indicate the size and/or capacity where stipulated, approximate location and/or direction, and approximate general arrangement of one phase of work to another, but not the exact detail or exact arrangement of construction.

B. If it is found before installation of any or all construction phases, that a more convenient, suitable or workable arrangement of any or all phases of the project would result by varying or altering the arrangement indicated on the drawings, the Architect may require any or all Contractors to change the location or arrangement of their work without additional cost to the Owner. Such rearrangement shall be in accordance with directions from the Architect.

C. Where discrepancies are discovered after certain portions or phases of any Contract have been installed, the Architect reserves the right to have any or all Contractors make minor changes in pipe, duct, fixture or equipment locations or arrangements to avoid conflict with other work at no additional cost to the Owner.

15031 / MN Interagency Fire Center 22 00 11 - 2

D. Because the drawings are to a relatively small scale to show as large a portion as is practical, the fact that only certain features of the system are indicated does not mean that other similar or different features or details will not be required. Contractor shall furnish all incidental labor, materials, or equipment for the systems under his control, so that each system is a complete and operating one unless otherwise specifically stipulated in the detailed body of the Specifications.

E. The Contractor shall be responsible for determining all field measurements before commencing construction, giving due consideration to building design and other equipment to be installed.

Mechanical equipment not dimensioned on the drawings shall be field located, giving due consideration to the work of other trades. The Contractor shall verify all dimensions before proceeding with the work. Where cutting and patching is required, each Contractor shall be responsible for his own work.

F. Dimensions shall not be scaled from the drawings. If the Contractor discovers any discrepancy between actual measurements and those shown on the drawings which prevents good practice, good arrangement, or which is contrary to the intent of the drawings and specifications, he shall notify the Architect before proceeding with the work.

1.05 SITE INSPECTION

A. Before submitting a proposal for the work contemplated in these specifications and accompanying drawings, each bidder shall examine the site and familiarize himself with all the existing conditions and limitations, including the extent of demolition, cutting and patching to be done by the Contractor for Mechanical Work. No extras will be allowed because of the Contractor's misunderstanding as to the amount of work involved, or his lack of knowledge of any condition in connection with the work.

1.06 CODES AND STANDARDS

A. The entire project shall comply with any and all OSHA, Federal, State and local codes, including, but not limited to State Building Code, State Plumbing Code, MnDOT Specifications (utility work), Municipal Requirements (water, sewer and gas piping), National Electrical Code, and the Model Energy Code (insulation).

B. Code requirements shall supersede details shown on the drawings or described in these specifications. Size of all pipe must conform to the requirements of all Codes except where larger sizes are shown on the drawings.

1.07 PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS

A. Where the Bid Documents stipulate a particular Product, substitutions will be considered by the Engineer up to 7 days before receipt of bids.

B. The submission shall provide sufficient information to determine acceptability of such products.

C. When a request to substitute a Product is made, the Engineer may approve the substitution and will issue an Addendum to known bidders.

D. The submission shall provide sufficient information to determine acceptability of such products.

E. Provide Products as specified unless substitutions are submitted in this manner and subsequently accepted.

F. The cost of any changes of other trades as a result of use of the substitution material or equipment must be borne by the Contractor submitting such material or equipment.

G. Email or fax requests for substitution are acceptable, provided they are received in the time period stated.

H. Those vendors wishing written approval shall include a return copy and a self-addressed stamped envelope with their request.

1.08 EQUIPMENT

A. All equipment shall be new and in first-class condition. Equipment shall not be used for purposes other than intended by the manufacturer.

15031 / MN Interagency Fire Center 22 00 11 - 3

B. Manufacturer's nameplate, name or trademark shall be permanently affixed to all equipment and material furnished under this Specification. Nameplate of Subcontractor or distributor will not be acceptable. Nameplate shall be masked prior to any painting. Remove masking after completion.

C. Equipment specified and furnished shall be of a type and manufacturer that has a local representative and a local replacement and service outlet to give complete coverage on parts and service at all times.

1.09 WARRANTY

A. The Contractor shall be held responsible for any and all defects in equipment and workmanship which appear for one (1) full year after the date of Substantial Completion. All such defects must be repaired or defective equipment promptly replaced by the Contractor at no expense to the Owner.

1.10 INSPECTIONS AND FEES

A. The Contractor shall obtain all permits and licenses required in connection with the work under Division 22. Cost for such shall be paid by the Contractor.

B. When application for utility service is the Owner's responsibility, the Contractor shall be responsible for all phases of the installation other than the application itself and shall coordinate the utility's work with his installation.

1.11 SUBMITTALS

A. Drawing Plan Backgrounds Available

1. Electronic drawing files may be available to the contractor for the purpose of preparing shop drawings or submittals. Files provided by the Engineer are generally available at a nominal fee of $100 per drawing file. Drawings requiring extensive modification for retransmit all will have an additional time and material charge for labor or expenses incurred.

B. List of Suppliers & Subcontractors:

1. The Contractor shall submit a list of suppliers, Subcontractors, and manufacturers for equipment installed under Division 22 for approval. Contractor shall make such submittal within 15 days after Notice to Proceed, prior to ordering any equipment. Approval of such list does not relieve the Contractor from submittal of shop drawings, nor shall it constitute final approval should the shop drawings be found not in agreement with the Specifications.

2. If a list of materials is not submitted, it shall be assumed that the Contractor has waived his option of equipment selection in favor of selection by the Architect.

C. Cost Breakdown:

1. Before submittal of the first Request for Payment, the Contractor shall submit to the

Architect, an itemized cost breakdown, including separation of labor and material, for work under Division 22. The breakdown shall be divided in such detail as requested to aid in approval of Payment Requests based on work completed. Breakdown shall include, but not be limited to:

a. Special Mechanical Conditions (Bonds, Mobilization, etc.)

b. Insulation

c. Plumbing

D. Shop Drawings:

1. See Division 1 for submittals procedures. This section supplements the requirements of

Division 1. In case of differences, the greater requirement applies.

2. Shop drawings shall be submitted for all major equipment under each Section of this

Specification.

3. Shop drawings must first be checked by the Contractor for capacities and space conformance, and so stamped prior to submittal to the Architect.

4. Submit either electronic shop drawings in PDF file format or a minimum of eight (8) hard copies of shop drawings.

15031 / MN Interagency Fire Center 22 00 11 - 4

E. Test and Balance Reports:

1. Tabulated data shall be submitted to the Architect, certifying that all applicable tests have been made, and that heating and ventilating systems have been balanced as specified.

F. Systems Manuals (O&M's):

1. The Contractor Shall provide an electronic copy in Adobe PDF Portfolio format. The

Portfolio shall contain:

a. Shop Drawings of all major mechanical components.

b. Parts lists for the same components.

c. Manufacturer's operating, maintenance and cleaning instructions.

d. List of materials recommended for maintenance.

e. Name and address of authorized service organization and parts depot.

f. A description of how the components of a given HVAC system interact within the large system. For example, circulating pumps, boilers, unit heaters are part of the "heating system".

g. A description of normal operating conditions for the system and its components.

h. A description of common symptoms of a malfunctioning system and likely causes.

i. File volume sizes should be restricted to 30Mb. Multiple volumes may be required.

2. The Systems manual shall have an electronic index and be broken up by individual systems such as "heating", "shop exhaust", "kitchen ventilation and exhaust", "chilled water", "administration ventilation".

3. In addition to the electronic version, the Contractor shall prepare two (2) hard copies of all systems manual. Information shall be submitted neatly folded to approximately 8-1/2" x 11" size and shall be bound in indexed looseleaf binders of adequate size to contain the material. Upon completion of these portfolios, the Contractor shall turn over the same to the Architect for approval and delivery to the Owner.

4. Where indicated in the Specifications, the Contractor shall provide the services of a factory trained representative to instruct the Owner's authorized personnel in the operation, control and maintenance of equipment.

G. Record Drawings:

1. The Contractor shall keep a complete set of all mechanical drawings in his job site office for purposes of showing "As-Built" installation of mechanical systems and equipment.

2. This set of drawings shall be used for no other purpose. Where any material, equipment or system components are installed different from that shown on the Drawings, such differences shall be clearly and neatly shown on this set of drawings using ink, or indelible pencil. The change notations shall be kept up-to-date on a daily basis for the duration of the project.

3. A complete set of these drawings shall be scanned at a resolution of 600dpi in color and saved in a Adobe PDF portfolio format with index to each sheet by name and burned to a non-volatile media. The electronic copy of the as-built drawings shall be transmitted to the Architect. After review and approval by the Architect, the as-built drawings will be turned over to the Owner.

1.12 HAZARDOUS MATERIALS - ASBESTOS

A. Where the Contractor connects to existing piping suspected to be covered with asbestos containing materials, the Owner will be responsible for removal of the existing pipe covering at the point of connection. The Contractor shall be responsible for re-insulating said portion of the existing pipe.

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION

3.01 WORKMANSHIP

A. Workmanship shall be first-class in every respect. Standard accepted practice in the various trades shall be considered as minimum. The Architect reserves the right to reject any

15031 / MN Interagency Fire Center 22 00 11 - 5 workmanship not in accordance with the specifications, either before or after installation of equipment.

3.02 COORDINATION

A. The Contractor shall coordinate locations and arrangements of his equipment with other Contractors and subcontractors working on the project. Before starting work, the Contractor shall examine the Architectural, Structural and Electrical drawings and specifications, as well as shop and vendor drawings, for all divisions, to ascertain locations, levels, arrangements and dimensions of other work and shall confer and cooperate with all other Contractors or subcontractors to avoid all interferences. He shall also provide Contractors for other trades with information regarding locations, arrangements and dimensions of his equipment. He shall also coordinate his own cutting and patching requirements with those of other Contractors, so that it will not be necessary for any Contractor to remove or re-do work improperly scheduled.

B. In cases of interferences between various items of equipment or between equipment and building members, if simplified construction is made possible by the relocation of certain equipment, changes in arrangements may be made only if authorized by the A/E.

C. Interferences between the work of different divisions which cannot be resolved by the parties involved shall be submitted to the Architect who shall decide upon final location and arrangement without respect to which work was installed first.

3.03 JOB INSPECTION

A. Periodic job site observations will be made throughout the construction to review applications for payment, observe methods and materials of construction, and review requirements of the Bid Documents.

B. Contractor shall notify the Architect, or authority having jurisdiction, and arrange for observation of installation prior to backfill or concealing of systems. Contractor shall, to the maximum practical extent, schedule work to allow for the observation of systems' installation in groups rather than individually.

C. Upon completion of all work, and submittal and approval of Test Reports, Systems Manuals and Record Drawings, the Contractor shall notify the A/E and shall make arrangements for a Substantial Completion inspection.

D. After the inspection is made, the Contractor will receive a list of items requiring adjustment, correction, replacement or completion.

E. The Contractor shall promptly comply completely with all the listed requirements. Should the Contractor fail to perform promptly, the Architect reserves the right to have the work completed by others and the cost deducted from the contract price.

3.04 INSTRUCTION

A. Complete operating instructions composed of charts, diagrams, installation instructions, service instructions and wiring diagrams, shall be prepared for each system and its components requiring adjustment or maintenance. Instructions shall be filed with the Systems Manuals and in specific cases, framed and mounted near the equipment for reference.

B. The Contractor shall instruct the Owner's personnel in the operation and maintenance procedures of all systems and components. This instruction shall be completed on-site with the equipment in question and with the aid of the approved Systems Manuals. Coordinate instruction with the Owner.

C. Video document the instruction session, index and save in digital format (avi, mpg, m1v, mp2, mpeg)

D. The Contractor shall provide the Architect with written documentation with the Owner's Representative signature that they have received instruction to his satisfaction in the operation of all systems. This documentation shall be received and acknowledged by the Architect before final inspection (and warranted period) shall be be completed.

15031 / MN Interagency Fire Center 22 00 11 - 6

3.05 REMODELING

A. Relocation of existing equipment and piping systems, which of necessity must provide continuous uninterrupted service, shall be accomplished in the least possible time. Work shall be scheduled so as to minimize down time for the respective systems involved. This will require for existing services being revamped and/or relocated, that all interconnecting portions of these systems shall be installed as complete as practicable prior to actual shutdown for final connections.

B. Locate existing piping and make connection where required and/or where shown on the drawings. Do not cut into existing services without first ascertaining to the satisfaction of the Owner and Engineer that the pipe involved is the desired service. In any area where work performed under Division 22 is the only work involved, restore the area to its original condition upon completion of the work.

C. All existing services and equipment shall be maintained unless otherwise indicated on the drawings.

D. Work that interrupts any service (this includes cutting into existing lines for new connection), shall be performed at times (usually nights or weekends) to cause least interference to the normal operation of the building. Anticipate scheduling work at periods which will result in additional construction costs, such as nights or weekends, and include cost in the proposal.

E. The Owner shall be fully informed in advance of any shut-off which will occur and which will be affected for a specific period of time. Only after the Owner is fully informed and has agreed to the schedule of cut-offs, can the work then proceed accordingly.

F. Provide temporary bracing, shoring, underpinning and support during demolition, cutting, remodeling and related new construction as necessary for the execution of the Work and the protection of persons and property.

G. Provide protective coverings and enclosures necessary to prevent damage to existing work to remain. Protect temporary openings in exterior walls and roofs so as to prevent damage from water and the elements and prevent excessive heat loss from the existing building.

H. Demolish and remove existing construction to be removed. Where new Work is to be installed in or adjacent to existing construction or existing work is to be replaced, remove or cut the existing construction to the extent necessary to install or join the new Work to the existing construction as necessary to complete the Work of the Project.

I. Clean demolition areas and remove debris, waste and rubbish from the building at the conclusion of each day's work. Transport debris and rubbish in such a manner as to prevent the spread of dust. Remove debris, waste and rubbish promptly from the site. Do not burn debris, waste and rubbish on the site.

J. Owner shall have first rights to salvage existing equipment not indicated to be reused. All existing materials not designated to be reused or to remain the property of the Owner, shall become the property of the Contractor and shall be removed from the site.

K. Existing materials indicated on the drawings to be reused shall be stored on the site and protected until reuse.

L. All cutting and patching of existing construction shall be by the Contractor requiring same.

M. Prior to making any cuts, verify exact locations and sizes with the Architect to confirm that no structural members will be cut. Where required, Contractor shall provide reinforcing lintels, angles, supports, etc., as necessary to maintain structural integrity at penetrations of existing partitions, slabs, etc.

N. Patch existing construction to match. All painting shall comply with the specifications laid out in the General Contractor's portion of the specifications. Examine existing surfaces where existing surfaces are to be patched before proceeding with the work. Report all conditions where existing materials, colors, and finishes cannot be matched to the Engineer, and do not proceed until the Engineer has issued instructions. Existing construction that has been damaged as a result of the work shall be repaired to an extent and as required to match

15031 / MN Interagency Fire Center 22 00 11 - 7 adjacent undamaged construction. Contractor shall notify Architect when patching is complete and receive Architect's approval of patching and finish

O. Where duct and/or piping is removed from existing partitions which are to remain, it is this Contractor's responsibility to patch voids to match existing construction.

15031 / MN Interagency Fire Center 22 10 05 - 1

PLUMBING PIPING

SECTION 22 10 05

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Pipe, pipe fittings, valves, and connections for piping systems.

1. Gas.

2. Flanges, unions, and couplings.

3. Pipe hangers and supports.

1.02 REFERENCE STANDARDS

A. ASME B16.3 - Malleable Iron Threaded Fittings: Classes 150 and 300; The American Society of Mechanical Engineers; 2011.

B. ASME B31.1 - Power Piping; The American Society of Mechanical Engineers; 2014

(ANSI/ASME B31.1).

C. ASME B31.9 - Building Services Piping; The American Society of Mechanical Engineers; 2014

(ANSI/ASME B31.9).

D. ASME BPVC-IX - Boiler and Pressure Vessel Code, Section IX - Welding, Brazing, and Fusing Qualifications; The American Society of Mechanical Engineers; 2013.

E. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless; 2012.

F. ASTM A123/A123M - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products; 2013.

G. ASTM A234/A234M - Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service; 2013.

H. MSS SP-58 - Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application, and Installation; Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.; 2009.

I. MSS SP-110 - Ball Valves Threaded, Socket-Welding, Solder Joint, Grooved and Flared Ends;

Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.; 2010.

J. NFPA 54 - National Fuel Gas Code; National Fire Protection Association; 2012.

K. NSF 61 - Drinking Water System Components - Health Effects; 2014.

L. NSF 372 - Drinking Water System Components - Lead Content; 2011.

1.03 SUBMITTALS

A. See Division 01 - Administrative Requirements, for submittal procedures as well as General Provisions for this Division.

1.04 QUALITY ASSURANCE

A. Perform work in accordance with applicable codes.

B. Valves: Manufacturer's name and pressure rating marked on valve…