Construction Specifications.pdf
PDF 116 KB Posted
- Attached to
- Green County Restoration on 3 sites - Emergency Watershed Protection Program - Floodplain Easements
- Solicitation number
- AG-5F48-S-10-0008
About this file
Construction Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Signed Solicitation Amendment 1.pdf | ||
| Drawings-Hafliger 6-7-101.pdf | ||
| General Decision Number WI100019 06-04-2010 WI19.docx | DOCX document | |
| Drawings-Fahrney 6-7-101.pdf | ||
| Solicitation Offer and Award-Standard Form 1442-Section A.pdf | ||
| Price Schedule-Section B.xlsx | XLSX spreadsheet | |
| Solicitation-Sections C through M.docx | DOCX document | |
| Drawings-Babler 6-7-101.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GREEN COUNTY EWP-FPE
WETLAND RESTORATION PROJECTS
APPLICABLE WISCONSIN CONSTRUCTION SPECIFICATIONS
WCS #1. Clearing
WCS #2. Excavation
WCS #3. Earthfill
WCS #7. Mobilization/Demobilization
Note: Where the term Technician is used throughout the solicitation and resultant contract, this term shall mean Contracting Officer's Technical Representative (COTR).
USDA-NRCS-Wisconsin Section IV, Technical Guide 1-1 7/08
WISCONSIN CONSTRUCTION SPECIFICATION
1. CLEARING
1. SCOPE
The work shall consist of the clearing and disposal of trees, snags, logs, brush, shrubs, stumps, and rubbish from the designated areas.
2. MARKING
The limits of the areas to be cleared will be marked by means of stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunks at a height of about 6 feet above the ground surface.
3. PROTECTION OF EXISTING VEGETATION
Trees and other woody vegetation designated to remain undisturbed shall be protected from damage throughout the entire construction period. Any damage resulting from the Contractor's operations or neglect shall be repaired by the Contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the dripline of vegetation designated to remain in place.
Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5-inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.
All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth and/or backfilled as soon as possible to prevent them from drying.
4. CLEARING
Trees, brush, shrubs, stumps, and other woody growth shall be cleared to a height not exceeding 12 inches above the ground surface. Such growth may be cleared by cutting, pulling, grubbing, or other approved methods.
Trees shall be felled in such a manner as to avoid damage to trees that are to be left standing, existing structures, utilities, and with regard for the safety of persons.
7/08 1-2
When the designated areas to be cleared include borrow areas and/or areas upon which improvements are to be constructed, the required grubbing of stumps, roots, and other objectionable material in these areas shall be a part of this specification. The grubbing shall consist of the removal of all stumps, roots of 1 inch in diameter or larger, buried logs, and other objectionable material to a minimum depth of 2 feet below a structure subgrade and 1 foot below an embankment foundation.
5. SITE EROSION CONTROL
Measures shall be installed, or the work performed in a manner that will minimize site erosion, and the production of sediment. Protective measures shall include but are not limited to diversions, waterways, seeding, mulching, sediment basins, and silt fences.
6. DISPOSAL
All materials cleared from the designated areas shall be burned or buried at approved locations or otherwise removed from the site. Buried materials shall be covered with a minimum of 2 feet of earthfill (including any topsoil added for seeding).
The Contractor is responsible for complying with all rules and regulations for disposal at locations away from the construction site or for the burning of cleared materials.
2-1 USDA-NRCS-Wisconsin
7/08
WISCONSIN CONSTRUCTION SPECIFICATION
2. EXCAVATION
1. SCOPE
The work shall consist of the excavation of all materials necessary for the construction of the work.
2. USE OF EXCAVATED MATERIALS
To the extent that they are needed, all suitable materials removed from the specified excavations shall be used in the construction of the required earthfill. The suitability of materials for specific purposes will be determined by the Technician. The Contractor shall not waste or otherwise dispose of suitable excavated materials.
3. DISPOSAL OF WASTE MATERIALS
All surplus or unsuitable excavated materials will be designated as waste and shall be disposed of at the locations shown on the drawings or as approved by the Technician.
Waste materials shall not be placed in wetlands.
Material placed in designated waste disposal areas shall be left in a neat and sightly condition and sloped to provide positive drainage. Compaction of the waste materials will not be required unless specified by the construction plans.
Waste material excavated from channels may be deposited in leveled spoilbanks or areas adjacent to the channel work (if permissible). The shape and slopes of the spoilbanks shall be indicated on the drawings or as approved by the Technician. Spoil piles shall be located a minimum of 12 feet from the top of the channel side slope.
Spoil piles or disposal areas shall be protected to minimize site erosion and the production of sediment. Protective measures may include but are not limited to diversions, seeding, mulching, sediment basins, and silt fences.
4. SPECIAL REQUIREMENTS FOR STRUCTURE AND TRENCH EXCAVATION
The required dimensions and side slopes of all structure and trench excavations shall be as shown on the drawings.
Excavation beyond the limits of the specified lines and grades shall be corrected by filling the resulting voids with approved compacted materials.
Excavation for the installation of pipes shall follow the practices contained in the Occupational Safety and Health Administration (OSHA) Subpart P, Excavation, of 29 CFR 1926.650, .651 and .652.
Side slopes shall be excavated or braced to safeguard the work and workers. When bracing or supporting is required, the width of the excavation shall be adjusted to allow for the space
USDA-NRCS-Wisconsin 2-2
7/08 occupied by the sheeting, bracing, or other supporting installations. The Contractor shall furnish, place, and subsequently remove such supporting installations.
5. REMOVAL OF WATER
The Contractor shall construct and maintain all necessary cofferdams, channels, flumes, pumping equipment, and/or other temporary diversion and protective work for dewatering the various parts of the work. Foundations, cutoff trenches, and other parts of the work shall be maintained free from water as required for constructing each part of the work. After having served their purpose, all cofferdams and other temporary protective works shall be removed, or leveled to give a sightly appearance and so as not to interfere in any way with the operation, usefulness, or stability of the permanent structure.
6. BORROW EXCAVATION
When the quantities of suitable materials obtained from specified excavations are insufficient to construct the specified fill portions of the permanent works, additional materials shall be obtained from the designated borrow areas.
When shown on the drawings, sediment basins, terraces, diversions, or other measures shall be constructed to protect the borrow areas from erosion and retain sediment within the borrow area.
The upper six (6) inches shall be stripped from all borrow areas. This stripping shall be performed immediately prior to use of the borrow material to reduce the time the area is exposed to erosion. For large borrow areas, only a portion of the area should be stripped at a time. This material shall be redistributed over the area from which it came after borrow excavation is completed.
The extent of excavation and the selection of materials from the borrow area shall be as directed by the Technician. On completion of excavation, all borrow pits shall be left in a neat and sightly condition. All borrow areas shall be graded to blend with existing topography and sloped to prevent ponding and provide positive drainage.
WISCONSIN CONSTRUCTION SPECIFICATION
3. EARTHFILL
1. SCOPE
The work shall consist of placing the earthfill required by the drawings. This specification does not apply to the earthfill required for waste storage facilities.
2. MATERIALS
All fill materials shall be obtained from required excavations and designated borrow areas.
The selection, blending, routing, and disposition of materials in the various fills shall be subject to approval by Technician.
Fill materials shall contain no sod, brush, roots, frozen soil, or other perishable materials.
Stones larger than two-thirds of the uncompacted layer thickness shall be removed from the materials prior to compaction of the fill.
3. FOUNDATION PREPARATION
The foundation area shall be cleared of trees, stumps, roots, brush, rubbish, and stones having a maximum dimension greater than six (6) inches. Foundations shall be stripped to remove vegetation and other unsuitable materials or to the depth shown on the drawings, whichever is greater. Topsoil shall be stripped from the foundation area and stockpiled for use as a top dressing for vegetation establishment unless otherwise shown on the drawings.
Earth foundations shall be graded to remove surface irregularities and slopes steeper than 1:1.
The foundation surfaces shall be scarified parallel to the centerline of the fill to a minimum depth of 2 inches. The moisture content of the scarified materials shall be maintained as specified for the earthfill. The surface materials of the foundation shall be compacted and bonded with the first layer of earthfill as specified for subsequent layers of earthfill.
4. PLACEMENT
Fill shall not be placed until the required excavation and preparation of the underlying foundation is completed and inspected and approved by the Technician. No fill shall be placed upon a frozen surface nor shall snow, ice, or frozen material be incorporated in the fill.
Fill shall be placed in approximately horizontal layers beginning at the lowest elevation of the foundation. The thickness of each layer of fill prior to compaction shall be as specified in Table 1. Materials placed by dumping in piles or windrows shall be spread uniformly to not more than the specified layer thickness prior to compaction.
Adjacent to structures, earthfill shall be placed in 4-inch lifts (prior to compaction) in a manner adequate to prevent damage to the structure and to allow the structure to gradually and uniformly assume the backfill loads.
3-1 USDA-NRCS-Wisconsin
6/05
The height of the fill shall be increased at approximately the same rate on all sides of the structure.
Placement of fill adjacent to concrete structures may begin after the concrete has cured for the minimum time specified.
Earthfill in dams, levees, and other structures designed to impound water shall be placed to meet the following additional requirements:
a. The distribution of materials throughout each zone shall be essentially uniform, and the fill shall be free from lenses, pockets, streaks, or layers of material differing substantially in texture, moisture content, or gradation from the surrounding material.
b. The embankment top shall be maintained approximately level during construction except for sectional construction as described in Section 7.
c. Dam embankments shall be constructed in continuous layers from abutment to abutment, except where openings to facilitate construction or to allow passage of stream flow during construction are specified.
d. If the surface of any layer becomes too hard and smooth to achieve a suitable bond with the succeeding layer, it shall be scarified parallel to the axis of the fill to a depth of not less than 2 inches before the next layer is placed.
5. CONTROL OF MOISTURE CONTENT
Fill materials shall have a moisture content sufficient to insure the required compaction.
When kneaded in the hand, the soil will form a ball which does not readily separate and will not extrude out of the hand when squeezed tightly. The adequacy of the moisture content will be determined by the Technician.
Fill material or the top surface of the preceding layer of compacted fill that becomes too dry to permit suitable bond shall either be removed or scarified and wetted by sprinkling to an acceptable moisture content prior to placement of the next layer of fill.
Fill material that is too wet when deposited or the top surface of the preceding layer of compacted fill that becomes too wet shall be either removed or allowed to dry to an acceptable moisture content before compaction or placing additional layers of fill.
6. COMPACTION
The Contractor shall furnish and operate the types and kinds of equipment necessary to compact the fill materials.
Unless otherwise specified on the plans or approved by the Technician, compaction requirements for each layer of fill material are as shown in Table 1.
Each pass shall consist of at least one complete coverage by the wheel, track, or roller over the entire surface of the fill layer in a direction parallel to the main axis of the fill.
USDA-NRCS-Wisconsin 3-2 Section IV, Technical Guide 6/05
Adjacent to structures or in confined areas, compaction of the fill shall be accomplished by means of manually directed power tampers or plate vibrators or hand tamping, unless otherwise specified. The Technician shall determine if adequate compaction is being achieved. Heavy equipment shall not be operated within 2 feet of any structure.
Compaction by means of drop weights operating from a crane or hoist of any type will not be permitted.
7. SPECIAL REQUIREMENTS FOR SECTIONAL CONSTRUCTION OF EMBANKMENTS
When sectional (or phase) construction of embankments is authorized, the work shall be accomplished in the following manner:
Each section of the embankment that is constructed in the first phase shall be so placed that a slope not steeper than 3 feet horizontal to 1 foot vertical is maintained at the end of the embankment section adjacent to the gap in construction or closure section.
Prior to placement of the closure sections, the surfaces of completed fills and excavations that will be in contact with the closure shall be stripped of all loose material, scarified, moistened, and recompacted as necessary.
3-3 USDA-NRCS-Wisconsin
6/05
USDA-NRCS-Wisconsin 3-4
6/05
Table 1 - Equipment Compaction Requirements
Equipment Type Applicable Soils1 Maximum
Fill Height2
(feet)
Layer Thickness3
(inches)
Minimum Passes4
Sheepsfoot roller (10,000 lb. min. operating weight)
ML, MH, CL, CH
or
SM, SC, GM, GC
with >20% fines
None 9 1
Vibratory tamping roller (9,000 lb. min. operating weight)
SM, SC, GM, GC None 9 2
Rubber-tired scraper (fully loaded)
GM, GC, SM, SC,
ML, MH, CL, CH 20 9 1
Rubber-tired front end loader (fully loaded)
GM, GC, SM, SC,
ML, MH, CL, CH 20 6 1
Track-type crawler (standard tracks)
GM, GC, SM, SC,
ML, CL 10** 6 2
30,000 lb. min. SP, SW, GP, GW 6** 12 4
CL, ML, SC, SM 15## 3 2
less than 30,000 lb.
GM, GC, GP, GW,
SM, SC, SP, SW,
ML, CL
6** 6 2
Farm tractor (2,400 lb. min.)
GM, GC, SM, SC,
ML, MH, CL, CH 15 6 2
Steel drum vibratory roller (10,000 lb. min.) SP, SW, GP, GW None** 12 2
1 Unified Soil Classification System.
2 Measured from the top of the fill to the lowest point along the centerline of the fill.
3 Prior to Compaction.
4 The Technician shall determine if adequate compaction is being achieved. Additional passes may be required.
** The fill shall not have a permanent body of water stored against it.
## This method may only be used for embankments that will not have the potential for a permanent body of water stored against it that is greater than 1/4 acre in surface area or more than 6 feet deep.
7-1 5/08
WISCONSIN CONSTRUCTION SPECIFICATION
7. MOBILIZATION AND DEMOBILIZATION
1. SCOPE
The work consists of the mobilization and demobilization of the Contractor's forces and equipment necessary for performing the work required.
2. EQUIPMENT AND MATERIAL
Mobilization shall include:
• All activities and associated costs for transportation of the Contractor's personnel, equipment, and operating supplies to the site;
• Establishment of offices, buildings, and other necessary general facilities for the Contractor's operations at the site
• Premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable
• Construction and maintenance of haul roads and equipment parking areas
• Other job related items
Demobilization shall include:
• All activities and costs for transportation of personnel, equipment, and supplies not utilized in the project from the site
• Disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site.
• Repair of access roads, temporary haul roads, and equipment parking areas leaving the project site in the same or better condition than at the start of the project.
• General cleanup and house keeping needed to restore a neat and orderly project site.
Access to the site, equipment parking, and staging areas are limited to that shown on the drawings or as approved by the technician.
| Crawfish South Specifications 6-9-10 1 |
| Construction_Specs |
| 001 |
| 002 |
| 003 |
| 007 |