Drawings_Signed_-_03062017.pdf

PDF 7 MB Posted

Attached to
US 33 Bypass Revegetation on Wayne NF Federal contract opportunity
Solicitation number
AG-56A1-S-17-0006
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Drawings

View the file

Other files for this federal contract opportunity

Other files attached to US 33 Bypass Revegetation on Wayne NF, newest first.
File Type Posted
Addendum_Specifications_DIVISION_02.pdf PDF
AG-56A1_S-17-0006_Amdmt_0002.pdf PDF
Addendum_Drawings_Sheet_2.pdf PDF
PrebidConferenceNotesFBO.pdf PDF
Addendum_RevisedSchedule_of_Items.docx DOCX document
AG-56A1_S-17-0006_Amdmt_0001.pdf PDF
SF24-Bid_Bond_2016.pdf PDF
AG-56A1-S-17-0006_Solicitation.pdf PDF
Wage_Determination.pdf PDF
Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUANTITIES

NAME OF PROJECT: US-33 BYPASS REVEGETATION, BUTTERFLY BRIDGE ROAD NO.: US-33

ITEM NO. DESCTIPTION PAY UNIT QUANTITY REMARKS

01 Mobilization LUMP SUM ALL Includes all work needed to access site. Cleaning of equipment is required under mobilization.

02 Traffic Control LUMP SUM ALL Includes all labor and materials to comply with ODOT and MUTCD regulations for traffic control, as needed.

Submit a traffic control plan for review and approval prior to beginning of work. See Section 015526 and Sheets 8-10 for additional details.

03 Soil Erosion and Pollution Control LUMP SUM ALL Includes all labor and materials for erosion control and preparation and submittal of approved Erosion Control and Pollution Prevention Plan.

04 Preparatory Grading ACRE 6 Includes preparing Type 1 and Type 2 treatment areas for application of topsoil and/or hydroseeding operations.

Placed Rock Channel Protection (RCP), ODOT Type C TON 500 Includes furnishing and placing RCP (riprap) to construct armored channels.

06 Furnish and Place Topsoil, 6" Depth CUBIC YARD 1000 Includes furnishing and placement of topsoil in the Type 2 Treatment Area.

07 Agricultural Lime TON 30 Includes furnishing and application of agricultural lime in the Type 1 Treatment Areas.

Soil Amendments and Fertilizer, Hydraulic Method (2-step) ACRE 6 Includes furnishing and application of all fertilizers and soil amendments. Soil amendments will vary by treatment area.

09 Seeding, Hydraulic Method (2-step) ACRE 6 Includes application of specified seed in Type 1 and Type 2 Treatment Areas via 2-step hydroseeding method.

Seed will be furnished by the Government and vary by treatment area.

Flexible Growth Medium, Hydraulic Method (2-step) ACRE 6 Includes furnishing and application of Flexible Growth Medium.

11 Straw Wattles, 9" diameter, biodegradable LF 6000 Includes furnishing and installation of straw wattles.

E:

QUANTITIES US-33 BYPASS REVEGETATION

BUTTERFLY BRIDGE

OH 33 WEST

OH 33 EAST

US-33 BYPASS REVEGETATIONEXISTING SITE CONDITIONS BUTTERFLY BRIDGE

TYPE 1 TREATMENT (SLOPE)

TYPE 2 TREATMENT (BRIDGE)

CONSTRUCT RCP CHANNEL

GRADE TO DRAIN

TO CATCH BASIN

OH 33 WEST

OH 33 EAST

LEGEND

NOTES:

(1) Type 1 Treatment (slope) includes prepatory grading, agricultural liime application, RCP channel construction, wattle installation, and application of seed, fertilizer, soil amendments, and flexible growth medium via two-step hydroseeding process. Total Type 1 Treatment Area measures approximately

4.75 acres.

(2) Type 2 Treatment (bridge) includes preparatory grading, placement of topsoil, and application of seed, fertilizer, soil amendments, and flexible growth medium via two-step hydroseeding process. Type 2 Treatment Area measures approximately 1.25 acres.

(3) All hydroseeding activity shall be performed between October 15 and November 15.

(4) See Sheet 7 (General Notes) for additional information and project specifications for detailed requirements.

STRAW WATTLES

EXISTING FENCE

STRAW WATTLE A

E:

SITE PLAN US-33 BYPASS REVEGETATION

VARIES

VARIES

VARIES

TYPE C RCP (ODOT CMS)

1. RCP CHANNEL DIMENSIONS VARY. AVERAGE TOP WIDTH IS APPROXIMATELY 4',

AVERAGE DEPTH IS APPROXIMATELY 2.5'.

2.

1. BEGIN AT THE LOCATION WHERE THE WATTLE IS TO BE INSTALLED BY EXCAVATING A 3" DEEP X 9" WIDE TRENCH ALONG THE CONTOUR OF THE SLOPE. EXCAVATED SOIL SHOULD BE PLACED UPSLOPE FROM THE

ANCHOR TRENCH.

2. PLACE THE WATTLE IN THE TRENCH SO THAT IT CONTOURS TO THE SOIL SURFACE. COMPACT SOIL FROM THE EXCAVATED TRENCH AGAINST THE WATTLE ON THE UPHILL SIDE. ADJACENT WATTLES SHALL BE

OVERLAPPED 24", NOT ABUTTED.

3. SECURE THE WATTLE WITH 24" STAKES EVERY 4' AND WITH A STAKE ON EACH END. STAKES SHOULD BE DRIVEN THROUGH THE MIDDLE OF THE WATTLE LEAVING AT LEAST 2-3" OF STAKE EXTENDING ABOVE THE

WATTLE. STAKES SHOULD BE DRIVEN PERPENDICULAR TO THE SLOPE FACE.

3"

SPACE STAKES 4' ON CENTER

30' SPACING

9"

TOP OF SLOPE

CONTOUR

STRAW

WATTLE

RCP CHANNEL

TOE OF SLOPE

5°

E:

DETAILS US-33 BYPASS REVEGETATION

BUTTERFLY BRIDGE

(B) RCP CHANNEL TYPICAL SECTION

(A) WATTLE INSTALLATION DETAILS (C) WATTLE/ RCP CHANNEL INTEGRATION

FIG. 1: ILLUSTRATION OF SOUTH SLOPE TREATMENT AREA (TYPE 1) FIG. 2: ILLUSTRATION OF NORTH SLOPE TREATMENT AREA (TYPE 1)

FIG. 3: ILLUSTRATION OF GULLEY TO

CONVERT TO RIPRAP CHANNEL

FIG. 3: ILLUSTRATION OF GULLEY TO

CONVERT TO RIPRAP CHANNEL

FIG. 3: ILLUSTRATION BRIDGE TREATMENT

AREA (TYPE 2)

E:

SITE PHOTOS US-33 BYPASS REVEGETATION

2. OSHA Requirements:

Follow Occupational Safety and Health Administration (OSHA) safety regulations or OSHA approved state plan requirements as required.

3. Submittals:

A. Traffic Control:

Traffic control devices for all activities, including full and partial road closure, shall be maintained as needed for safe operations. The Contractor shall submit for approval by the CO, a traffic control plan prior to beginning work. The plan shall conform with Ohio Department of Transportation requirements and the most recent edition of the Manual on Uniform Traffic Control Devices. The Contractor shall provide and maintain all necessary devices and signs.

B. Erosion Control:

Prior to the starting work, submit a written Erosion Control Plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 5 days before intended use. Incorporate all permanent erosion control features into the project at the earliest practical time, as outlined in the approved plan. When erosion control measures are not functioning as intended, immediately take corrective action. Payment for erosion control and the erosion control plan is included in Pay Item 003 .

C. Schedule:

Prior to starting work, submit a detailed schedule that incorporates all work activities and describes the sequencing of work items.

D. Products and Materials:

Submit product and material documentation, as required in the specifications for approval prior to purchasing and/or delivering to the site.

GENERAL NOTES

1. Notifications:

A: The Contractor shall notify the CO at least 14 days prior to the start work date.

B: The Contractor shall notify the CO at least 14 days prior to seeding operations.

4. Preparatory Grading:

Prepare the treatment areas for seeding activities per Section 312219, Preparatory Grading. Includes all work to fill in existing rills and gullies.

6. Armored RCP Channels:

Construct RCP channels at locations shown on the drawings and described in Section 313700, Rock Channel Protection.

7. Topsoil:

Furnish and place topsoil as specified in Section 312219.13, Topsoil. Topsoil shall be placed at a depth of 6" in the Type 2 Treatment Area (Bridge), as shown on Sheet 4.

8. Seeding:

A. Seed mixes for Treatment Types 1 and 2 will be furnished by the Government.

B. Application rates for seed mixes will be provided by the Government.

C. Furnish and apply all soil amendments, fertilizer, seed, and flexible growth medium (FGM) as specified in Sections 312500, 312514.13, 320190.16, and 329200.

D. All seeding shall be performed between October 15 and November 15.

9. Wattles:

Furnish and install straw wattles at locations shown on the drawings and as specified in Section 312219. Wattles shall follow the slope contour and be slightly tapered to drain to RCP channels.

5. Agricultural Lime:

Agricultural lime shall be disced or otherwise incorporated into the top 6" of soil at specified rates in the Type 1 Treatment Areas.

E:

GENERAL NOTES US-33 BYPASS REVEGETATION

E:

ODOT TRAFFIC CONTROL - 1 US-33 BYPASS REVEGETATION

ODOT TRAFFIC CONTROL - 2 US-33 BYPASS REVEGETATION

ODOT TRAFFIC CONTROL - 3 US-33 BYPASS REVEGETATION