New Drawing for your information. will be incorporated into any resultant contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PrebidConferenceNotesFBO.pdf | ||
| Addendum_RevisedSchedule_of_Items.docx | DOCX document | |
| Addendum_Specifications_DIVISION_02.pdf | ||
| AG-56A1_S-17-0006_Amdmt_0002.pdf | ||
| AG-56A1_S-17-0006_Amdmt_0001.pdf | ||
| Drawings_Signed_-_03062017.pdf | ||
| Specifications.pdf | ||
| AG-56A1-S-17-0006_Solicitation.pdf | ||
| Wage_Determination.pdf | ||
| SF24-Bid_Bond_2016.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUANTITIES
NAME OF PROJECT: US-33 BYPASS REVEGETATION, BUTTERFLY BRIDGE ROAD NO.: US-33
ITEM NO. DESCTIPTION PAY UNIT QUANTITY REMARKS
01 Mobilization LUMP SUM ALL Includes all work needed to access site. Cleaning of equipment is required under mobilization.
02 Traffic Control LUMP SUM ALL Includes all labor and materials to comply with ODOT and MUTCD regulations for traffic control, as needed.
Submit a traffic control plan for review and approval prior to beginning of work. See Section 015526 and Sheets 8-10 for additional details.
03 Soil Erosion and Pollution Control LUMP SUM ALL Includes all labor and materials for erosion control and preparation and submittal of approved Erosion Control and Pollution Prevention Plan.
04 Preparatory Grading ACRE 6 Includes preparing Type 1 and Type 2 treatment areas for application of topsoil and/or hydroseeding operations.
Placed Rock Channel Protection (RCP), ODOT Type C TON 500 Includes furnishing and placing RCP (riprap) to construct armored channels.
06 Furnish and Place Topsoil, 6" Depth CUBIC YARD 1000 Includes furnishing and placement of topsoil in the Type 2 Treatment Area.
07 Agricultural Lime TON 30 Includes furnishing and application of agricultural lime in the Type 1 Treatment Areas.
Soil Amendments and Fertilizer, Hydraulic Method (2-step) ACRE 6 Includes furnishing and application of all fertilizers and soil amendments. Soil amendments will vary by treatment area.
09 Seeding, Hydraulic Method (2-step) ACRE 6 Includes application of specified seed in Type 1 and Type 2 Treatment Areas via 2-step hydroseeding method.
Seed will be furnished by the Government and vary by treatment area.
Flexible Growth Medium, Hydraulic Method (2-step) ACRE 6 Includes furnishing and application of Flexible Growth Medium.
11 Straw Wattles, 9" diameter, biodegradable LF 6000 Includes furnishing and installation of straw wattles.
12 Existing Conditions LUMP SUM 1 Includes furnishing and installing measures for access through the fence on the north side of the highway, access to the treatment areas on the south side of the highway, and protection of the existing utilities.
Sheet: 1 File: ..\..\Specs\Traffic Control Plan ODOT.pdf Missing or invalid reference
Sheet: 2 File: ..\..\Specs\Traffic Control Plan ODOT.pdf Missing or invalid reference
Sheet: 3 File: ..\..\Specs\Traffic Control Plan ODOT.pdf Missing or invalid reference
OF
SHT.
PROJECT NAME:DRAWING NAME:
QUANTITIES US-33 BYPASS REVEGETATION
BUTTERFLY BRIDGE
Quantities 11x17