Attachment_C_-_FR390_Survey_Data.docx

DOCX document 347 KB Posted

Attached to
FR188, FR390, and FR604 Stabilization Federal contract opportunity
Solicitation number
AG-569R-S-16-0046
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Attachment C - FR390 Survey Data

View the file

Other files for this federal contract opportunity

Other files attached to FR188, FR390, and FR604 Stabilization, newest first.
File Type Posted
Amendment_01.pdf PDF
Attachment_B_-_FR188_Survey_Data.docx DOCX document
Attachment_E_-_Davis_Bacon_Wage_Determination.docx DOCX document
AG-569R-S-16-0046.rtf RTF text file
Attachment_D_-_FR604_Survey_Data.docx DOCX document
Attachment_A_-_Specifications.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C – FR390 Survey Data

AG-569R-S-16-0046

FR 390 ROAD STABLIZATION

CHEQUAMEGON-NICOLET NATIONAL FOREST

GREAT DIVIDE RANGER DISTRICT, ASHLAND COUNTY, WI

Beginning of Project End of Project

General Notes

1) CONSTRUCTION SPECIFICATIONS: Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units, shall apply to this contract.

2) Minor amounts of clearing and grubbing are required at some culvert locations. Limbs, logs, & stumps may be scattered outside the clearing limits.

3) Maintenance for traffic will be the responsibility of the Contractor. Road closures will be accompanied by road detours in accordance with the Manual of Uniform Traffic Control Devices (2003) guidelines. This work shall be considered incidental to Pay Item 15101-Mobilization.

4) Contractor shall not perform wetland removal on these projects during abnormally high flows or abnormally wet periods.

5) All suitable structure excavation shall be used as backfill material for the culverts and washouts. Culverts shall be bedded using suitable material from the excavation.

6) All areas of excavation shall match the existing road template on either side of the crossing being replaced.

7) Erosion control mat shall be placed on slopes, ditches, and shoulders where called for.

8) All disturbed slopes shall be seeded with the seed mix listed below and mulched with straw.

9) Seed mixture: Big Bluestern, 10%; Sideoats Grama, 20%; Canada Wild Rye, 35%; Annual Rye, 10%; Little Bluestern, 10%; Indiangrass, 10%, Purple Prairie Clover, 4%; Black-eyed Susan, 1%. Seeding rate: 30.49 lbs/

10) Ditch checks shall be installed as shown in Figure 1.

NOT TO SCALE

6’

Schedule of Items

Item Number
Description
Method of Meas.
Unit
Quantity
15101
Mobilization
DQ
LS
1
15708
Ditch Checks
DQ
Each
8
15713
Soil erosion and Pollution Control
DQ
LS
1
20418
Drainage Excavation
DQ
CY
300
30326
Road Reconditioning
DQ
Mile
1.98
32211
Agg. Surf., Comp. A, Truck Volume
DQ
CY
1,458.00
32222
Pit-Run Aggregate, Max. size 4", Comp. A, Truck volume
DQ
CY
782
62503
Seeding, Dry Method
DQ
LS
1
62901
Erosion Control Mat, Type ENS-2
DQ
SY
350
63501
Temporary Traffic Control
DQ
LS
1

Station (Miles) Notes

0.0 Intersection with FR 188

.10-.16Washout LT. Place 60 C.Y. of Pit Run. Grade.
.16-.24Ditch RT.
.25-.27Place 30 C.Y. of Pit Run in ditch washout on RT.

.27-.28 Ditch both sides.

.36-.47Ditch LT. Grade.
.50Begin asphaltic pavement.
.64-.70Reestablish ditches and place 50 c.y. of gravel on shoulder.
.73-.89Approaches, bridge, and abutment work listed below: Excavate 300c.y. of gravel deposit along the Southeastern abutment and approach. Excavated material to be placed at sta. 0.89-0.97 as described below. Cut and remove damaged asphalt at bridge corner holes. Fill holes with 24cy of gravel. Place erosion control mat at approaches and wingwalls.
.89End of 20’ width asphaltic pavement.
.89-.9710’x12’x401’ washout area on right hand side. Place all excavated material from the bridge excavation into this area. Place 200 c.y. Pit Run into 3’x6’x401’ hole. Install ditch checks on RT every 50’ starting at pavement end.
.97-1.00Grade, ditch, and shoulder work. Place 56 c.y. Pit Run to stabilize road. Add 30 c.y. gravel to restore road prism.
1.07-1.10Rebuild RT shoulder. Place 24C.Y. of Gravel.

1.10 Existing Large Pipe Arch. Washout RT. Place 24 C.Y, gravel. Place additional 24 C.Y. of gravel for shoulder. Place erosion control mat.

1.13 End of Asphaltic Pavement.

1.14-1.26 Place 180 C.Y. of Pit Run in ditch RT. Grade.

1.26-1.31 Ditch RT.

1.31-1.33 Place 24 C.Y. of gravel.

1.46 Intersection of FR 604.

1.46-1.53 Ditch on LT.

1.58-1.68 Place 230 C.Y. of gravel.

1.61 Place 24 C.Y. of Pit Run to Ditch LT.

1.68 Place and spread 72 C.Y. of Pit Run and 30 C.Y. of gravel at existing culvert. Place erosion control mat.

1.73-1.89 Place 240 C.Y. of gravel. Grade.

1.93 Place and spread 12 C.Y. of gravel at existing culvert.

2.06-2.12 Place 100 C.Y. of gravel. Grade.

2.12-2.19 Ditch on LT. Place erosion control mat.

2.56 Place and spread 12 C.Y. of gravel at existing culvert.

2.57-2.62 Place 90 C.Y. of gravel. Grade.

2.90-2.97 Ditch. Place 120 C.Y. of gravel.

2.99-3.04 Place 90 C.Y. of gravel. Grade.

3.08-3.19 Ditch both sides. Place 160 C.Y. of gravel. Place erosion control mat.

3.23-3.33 Grade.

3.37-3.44 Place 24 C.Y. of gravel. Grade.

3.64-3.68 Place 60 C.Y. of gravel. Grade.

3.82-3.88 Place 100 C.Y. of gravel. Grade.

3.92 Place and spread 12 C.Y. of gravel at existing culvert.

3.99-4.06 Place 150 C.Y. of gravel. Grade.

4.14 Place and spread 12 C.Y. of gravel at existing culvert.

4.21 P.O.E.

image3.PNG image1.PNG image2.emf

TYPICAL ROAD SECTION

CL

0.02 FT/FT 0.02 FT/FT

2:1

2:1 2:1

20.00'

6" (COMPACTED DEPTH)

3/4" MINUS SURFACE

COURSE