Specifications.doc
DOC document 368 KB Posted
- Attached to
- FDR2231 Station 10+00 to Station 188+50
- Solicitation number
- AG-569R-S-09-0010
About this file
J.2 Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_01.doc | DOC document | |
| RFP.doc | DOC document | |
| Updated_Complete_Drawings.pdf | ||
| Contractor_Return.doc | DOC document | |
| wage_decision.htm | HTM file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOREST ROAD 2231 RECONSTRUCTION
(FOREST ROAD 2235 TO FOREST ROAD 2233)
STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-03, AS MODIFIED BY U.S. FOREST SERVICE SPECIAL PROJECT SPECIFICATIONS
4Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work 103 Deletions 104 - Control of Work 104 Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.09 Legal Relationship of the Parties.
107.10 Environmental Protection.
108 - Prosecution and Progress
108.00 Utilities
109 Deletions
109.02 Measurement Terms and Definitions.
152 - Construction Survey and Staking 152.01(c) Material.
152.02 General.
152.03 Survey and Staking Requirements.
152.03 (l) Miscellaneous Survey and Staking.
155 - Schedules for Construction Contracts 155 Delete.
156 - Public Traffic
156.01 Description.
156.03 Accommodating Traffic During Work.
156.04 Maintaining Roadways During Work.
156.08 Traffic and Safety Supervisor.
171 - Weed and Disease Prevention 203 - Removal of Structures and Obstructions
203.01 Description.
203.04 Removing Material.
203.05 Disposing of Material.
203.08 Payment
204 - Excavation and Embankment
204.06 Roadway Excavation
204.09 Preparing Foundation for Embankment Construction.
204.10 Embankment Construction.
204.11 Compaction.
204.13 Sloping, Shaping, and Finishing.
204.13 Sloping, Shaping, and Finishing.
204.14 Disposal of Unsuitable or Excess Material.
208 – Structure Excavation and Backfill for Selected Major Structures
208.05 Channel Preservation.
208.10 Backfill.
208.13 Measurement.
251 – Riprap
251.04 Placed Riprap.
251.08 Measurement.
251.09 Payment.
301 - Untreated Aggregate Courses 301 Title Change.
301.01 Work.
301.02 Material.
301.03 General.
301.04 Mixing and Spreading.
301.05 Compacting
301.06 Surface Tolerance.
301.08(b) Plasticity Index.
301.09 Measurement.
301.10 Payment
402 - Hot Asphalt Concrete Pavement by Hveem or Marshall Mix Design Method
402.03 Composition of Mixture
401.18 Measurement
401.19 Payment
617 - Guardrail
617.01 General.
625 - Turf Establishment
625.02 Material.
625.03 General.
625.08 Application of Mulch.
635 - Temporary Traffic Control
635.03 General.
703 - Aggregate 703.05(b) Subbase or Base Aggregate Table 703-2.
703.05(c) Surface Course Aggregate, Table 703-3.
707 – Metal Pipe
707.00 General
707.06 Aluminum Alloy Structural Plate Structures
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_02_17_2005
101.01 Meaning of Terms.
Add the following:
Delete all references in FP-03 to Transportation Acquisition Regulations (TAR).
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_06_16_2006
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety and replaced with the following:
102.01 Bidding
Bidding contractors should contact Greg Gardner, (906) 474.6442, with the United States Forest Service when preparing their bid to discuss potential borrow and/or waste sites located within the project area.
103 - Scope of Work
103.00_nat_us_02_16_2005
103 Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
104 Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_03_29_2005
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is stricter.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor shall be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
Delete Section 108 in its entirety and replace with the following:
108.00 Utilities
Enbridge (U.S.) Inc. has a buried 30-INCH crude oil pipeline that crosses Forest Road 2231 at Stations 66+00, 150+20, and 168+50. It is not anticipated that roadway construction will impact their facility, however, the contractor shall contact Mike Paradise, PLM Supervisor, at 906.789.1221, Ext.23 a minimum of two weeks prior to working within one hundred feet (100’) of their facilities.
American Transmission Company (ATC) has an overhead transmission line that crosses Forest Road 2231 at Station 66+75. It is not anticipated that roadway construction will impact the facility, however the contractor shall abide by the following when working near their facility:
· An OSHA minimum safe working clearance of 12 feet shall be maintained at all times while working under or near the 138,000-volt overhead wires
· Unobstructed access to the easement area shall be maintained at all times, therefore there shall be no storage or staging of any materials, equipment, machinery or spoils piles in the easement at any time
· Excavation shall not take place within twenty-five feet (25’) of any company structure or pole The proposed approximate one and a half feet (1.5’) of fill above the existing grade within this project area is allowed between company structures 20566 and 20567. If there are any substantial changes to the proposed grading plans, contact Aric Patenaude with ATC at 920.609.8595 for approval.
· 109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.00_nat_us_08_05_2005
Description
152.01(c) Material.
Add the following:
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Construction Requirements
152.02 General.
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.03 Survey and Staking Requirements.
(b) Roadway cross-sections.
Replace the first two sentences with the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater that 200 feet take cross-sections at a maximum centerline spacing of 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
· Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
· Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
(e) Centerline reestablishment.
Replace with the following:
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.03 (l) Miscellaneous Survey and Staking.
Add the following:
(13) Erosion Control Measures
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
| Precision Class |
| Minimum Position Closure |
| Angular Accuracy (±) |
| L-Line Tangent Control Pointsa (±) |
| Vertical Closureb (±) |
A
(Bridges)
| 1/10,000 |
| 2 sets, direct/reverse |
10 second rejection limit
| N/A |
| 0.02 ft or |
0.02ft/1000ftc
| B |
| 1/5,000 |
| 2 sets, direct/reverse |
20 second rejection limit
| 0.1 ft |
| 0.02 ft or |
0.02ft/1000ftc
| C |
| 1/1,000 |
| 1 set, direct/reverse |
1 minute rejection limit
| 0.2 ft |
| 0.5ft/1000ftc |
| D |
| 1/300 |
| Foresight and backsight; 15 minute rejection limitc |
| 0.4 ft |
| 1.0ft/1000ftc |
| E |
| 1/100 |
| Foresight and backsight; 30 minute rejection limitc |
| 0.8 ft |
| 1.0ft/1000ftc |
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
Table 152-2 Cross section and slope stake tolerances.
| Item |
| Tolerances |
| A |
| B |
| C |
| D |
| E |
| Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves |
| (±)2o |
| (±)3o |
| (±)3o |
| (±)5o |
| (±)5o |
| Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed |
| 0.5 ft |
| 1.0 ft |
| 2.0 ft |
| 2.0 ft |
| 3.0 ft |
| Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater. |
| 0.1 ft or 0.4% |
| 0.15 ft or 0.6% |
| 0.2 ft or 1.0% |
| 0.2 ft or 1.0% |
| 0.3 ft or 1.0% |
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
| Slope reference stakes and slope stakes. |
| 0.1 ft or 0.4% |
| 0.15 ft or 0.6% |
| 0.2 ft or 1.0% |
| 0.2 ft or 1.0% |
| 0.3 ft or 1.0% |
| Clearing limits |
| 1.0 ft |
| 1.0 ft |
| 1.0 ft |
| 1.5 ft |
| 2.5 ft |
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03_nat_us_02_24_2005
156.01 Description.
Add the following:
During construction, Forest Road 2231 shall be closed to all thru traffic. Prior to closure, notification shall be given to the public and law enforcement personnel about the detour route and how long it will be in place. All traffic control devices shall be placed before construction begins. Barriers and signs should be erected in accordance with the Michigan Manual for Uniform Traffic Control Devices.
156.03 Accommodating Traffic During Work.
Delete the following from the last paragraph:
according to Subsection 106.07(b)
156.04_nat_us_02_24_2005
156.04 Maintaining Roadways During Work.
(a) Add the following:
Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO.
156.08_nat_us_02_24_2005
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating all construction equipment to remove seeds, plants, and plant fragments from the equipment before all the equipment is used on National Forest System lands.
Material
171.02 Conform to the following Subsection:
Water
725.01
Construction Requirements
171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing. Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment. Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work shall consist of the complete removal and disposal of existing culvert pipes or other structure materials, which are located within the limits of the new embankment including the existing culvert pipe on the North Branch Ogontz River.
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(a) The Contractor shall remove and dispose of all unusable material from government land. All material designated for disposal shall be treated in accordance with current Federal, State and Local regulations governing the handling and disposal of solid waste, demolition materials, and/or hazardous waste.
(e) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
203.08_nat_us_02_24_2005
203.08 Payment
Add the following:
Payment will be made under:
Pay Item
Pay Unit 20301 Removal of Pipe Culverts
Each
20305 Removal of Structure and Obstructions (Sta. 197+96)
LPMS
204 - Excavation and Embankment
204.06_nat_us_03_02_2005
204.06 Roadway Excavation
(a) General.
Add the following:
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
204.06_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Add the following:
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
(a) Sloping.
Add the following:
Slope rounding is not required on tolerance class D through M roads.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Table 204-2 Construction Tolerances
Tolerance Class(a)
| A |
| B |
| C |
| D |
| E |
| F |
| G |
| H |
| I |
| J |
| K |
| L |
| M |
| Roadbed width (ft) |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.5 |
| +1.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
Subgrade elevation
(ft)
| +0.1 |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.5 |
| +2.0 |
| +3.0 |
| +2.0 |
| +3.0 |
| (c) |
| Centerline alignment (ft) |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| `+1.5 |
| +1.5 |
| +2.0 |
| +3.0 |
| +3.0 |
| +5.0 |
| (c) |
| Slopes, excavation, and embankment (% slope(b) |
| +3 |
| +5 |
| +5 |
| +5 |
| +5 |
| +5 |
| +10 |
| +10 |
| +10 |
| +10 |
| +20 |
| +20 |
| +20 |
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.14_nat_us_03_02_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
Table 204-1 Sampling and Testing Requirements
Add the following note to the table:
(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
208 – Structure Excavation and Backfill for Selected Major Structures
208.05 Channel Preservation.
Add the following:
During removal of existing culvert pipes and installation of new structure and all associated embankment work, the Contractor shall install acceptable erosion control devices to separate the areas of excavating from the river channel in accordance with the conditions of the Michigan Department of Environmental Quality permit for this project.
As a minimum, Contractor shall install silt fencing protecting water and drainage from any and all disturbed areas and stockpiles.
Contractor shall provide acceptable erosion control devices in the creek and around any disturbances taking place in the creek.
208.10 Backfill.
Delete and substitute the following:
All backfilling and embankment construction within 25 feet of the structure shall be in accordance with this subsection, excavation for the structure shall extend a sufficient distance from each bulkhead to accommodate construction and shall include removal of the existing roadbed and backfill down to the creek bed for the full width of the roadway and fill slopes. The backwall of the excavation shall be sloped to meet the existing roadbed at a maximum slope of 1 to 1 or as required by OSHA regulations.
Excavated materials deemed suitable by the CO will be stockpiled in an area designated by the CO, and may be used as backfill.
Backfill shall be placed in horizontal layers, not over 12 inches (loose measure), to the subgrade elevation SHOWN ON THE DRAWINGS. Aggregate moisture content shall be approved by the CO before compaction. Each aggregate layer shall be compacted by mechanical compaction means, as approved by the CO.
The Contractor is responsible for the procuring and hauling required fill to meet the plans.
All embankments adjacent to structures shall be constructed in horizontal layers and compacted in accordance with the above paragraphs. Backfill material shall be suitable structural backfill meeting Subsection 704.04 with approval by the CO prior to hauling. It shall be free of excess moisture, muck, frozen material, roots, sod, or other unsuitable material. Backfill shall also be free of rock having its largest dimension greater than 6 inches.
Material, which can be dried, shall not be considered unsuitable based solely on excess moisture. Any granular material procured from Forest Service gravel sources must have a permit procured and paid for.
208.13 Measurement.
Delete and substitute the following:
Use the method of measurement that is DESIGNATED IN THE SCHEDULE OF ITEMS.
Measure structural excavation by the cubic yard that is in place in its original position. Do not include the following volumes in structural excavation:
(a) Material excavated outside limits SHOWN ON THE DRAWINGS. Use these limits to determine pay quantities, regardless of the amount of material excavated inside or outside these limits.
(b) Any material included within the staked limits of the roadway excavation, such as contiguous channel changes and ditches, for which payment is otherwise provided in the contract.
(c) Water or other liquid material.
(d) Material excavated before the survey of elevations and measurements of the original ground.
(e) Material rehandled, except when the contract specifically requires excavation after embankment placement.
(f) Material excavated for footings or foundations below the lowest elevation for such footings or foundations, as shown on the plans.
Measure foundation fill, when DESIGNATED IN THE SCHEDULE OF ITEMS, by the cubic yard in place.
Measure structural backfill, and structural backfill for walls, by the cubic yard in place. Limit the volume of structural backfill measured to that placed inside limits as SHOWN ON THE DRAWINGS. Use these limits to determine pay quantities, regardless of the amount of backfill material placed outside these limits.
251 – Riprap
251.04 Placed Riprap.
Add the following:
This work shall consist of contractor-furnished riprap as Shown in the Drawings. Riprap, Classes 1 and 4 shall be approved by the CO before placement.
Riprap, Class 4, around the North Branch Ogontz River structure and along ditch, will be placed to a depth as shown in the drawings. The final surface of the riprapped areas will be flush with the surrounding fill section. It may be necessary to excavate prior to the placement of the riprap to assure a flush, final surface.
Contractor is responsible for procuring, hauling and placement of riprap.
Riprap shall be naturally appearing rock similar to existing materials near the project site.
251.08 Measurement.
Add the following:
Measure riprap by the contract quantity (CQ).
251.09 Payment.
Delete and substitute:
25100 Placed Riprap, Class 1
CUYD
25101 Placed Riprap, Class 4
CUYD
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses 301.01_nat_us_03_03_2005
301.01 Work.
Add the following:
Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.
301.02_nat_us_05_16_2005
301.02 Material.
Add the following:
All aggregate shall meet the quality requirements of Michigan Department of Transportation 2003 Standard Specifications for Construction, Sections 302 and 902. Gradation used shall be MDOT Class 22A, or equivalent.
301.03_nat_us_09_14_2005
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.
301.04_nat_us_03_03_2005
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.
(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.
(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant. During mixing, add water to provide the necessary moisture content for compacting.
(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
Route and distribute hauling and leveling equipment over the width and length of each layer.
301.05_nat_us_05_17_2005
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travel way.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08_nat_us_03_03_2005
Table 301-1: Add the following:
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Subbase & Base Courses L, M, N, O, P, Q, R |
| Measured and tested conformance (Subsection 106.04) |
| Plastic Limit |
| - |
| AASHTO T 90 |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| Yes |
| 4 Hours |
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Aggregate Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Aggregate Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Additive |
| Measured and tested conformance (Subsection 106.04) |
| Amount of Additive |
| - |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| No |
| 4 Hours |
301.08_nat_us_03_30_2005
301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)”.
301.08_nat_us_03_03_2005
Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Base and Subbase |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| --- |
| Method C |
| --- |
| AASHTO T 99 |
| 1 per type and source of material |
| Source of material |
| Yes |
| Before using in work |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Compaction |
| --- |
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
| Surfacing |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| Before using in work |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
Compaction
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
301.09_nat_us_07_07_2005
301.09 Measurement.
Replace the second paragraph with the following:
Measure aggregate by cubic yard compacted in place when payment is by contract quantities.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
402 - Hot Asphalt Concrete Pavement by Hveem or Marshall Mix Design Method
402.03 Composition of Mixture
Add the following:
(Job-Mix Formula) The pavement mix shall meet the requirements of Michigan Department of Transportation 2003 Standard Specifications for Construction, Sections 501 and 902. Job-Mix Formula shall be MDOT Mixture No. 13A, or equivalent. Air void % target shall be 3%. Asphalt binder shall meet the requirements of Section 904, Performance Grade PG58-28. Bond coat shall be applied before the upper layer of asphalt is placed unless both layers are paved in the same day. Bond coat is incidental to paving and shall be applied as specified in Michigan Department of Transportation 2003 Standard Specifications for Construction, Section 502.
All required time frames as shown in the specifications shall be followed.
1) Pre-paving conference 10 days prior to the beginning of paving operations.
2) Submit written job-mix formulas for approval at least 21 days before production.
3) If job-mix formula is rejected, allow 14 days to evaluate a change.
4) The inspector shall be allowed 48 hours to check the grade prior to paving but after placement of aggregate and compacting.
Provide all required certifications for asphalt and aggregate/binder.
Plant shall be MDOT pre-certified, with plant certification provided.
3 rollers are required at least one of which is to be equipped with pneumatic tires.
On first layer of pavement, joint shall be 6-inch offset from final layer joint, which shall be at the centerline of roadway.
The government may waive some of the required testing if the paving and tests done by the contractor appears to be according to specifications. Cores shall be taken if the government requires it.
No excess material shall be dumped on the project or along the roadway. All such material shall be removed from the project and taken back to the plant.
401.18 Measurement
Add the following:
Measure hot asphalt concrete pavement by the Design Quantity (DQ).
401.19 Payment
Delete And Substitute:
The accepted quantity, measured as provided above, will be paid at the contract price per unit of measurement for the pay item listed below.
40350 State Asphalt Concrete Pavement, TON
MDOT Mixture No. 13A
03SP501 (H)
MICHIGAN
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
MARSHALL HOT MIX ASPHALT MIXTURE
C& T:JMB
C& T:APPR ERJAR08-06-04
FHWAAPPR08-20-04
a. Description. Furnish hot mix asphalt (HMA) mixture, designed using Marshall Mixture Design Methods, according to the requirements of the Standard Specifications for Construction except as modified by this special provision.
b. Mix Design. Submit the mix design for evaluation according to the Department's Hot Mix Asphalt Procedures Manual. Use a 50 blow Marshall hammer when compacting mixtures for developing Marshall mix designs
c. Recycled Mixtures. Substituting reclaimed asphalt pavement (RAP) for a portion of the new material required to produce HMA mixture is allowed provided that the mixture is designed and produced to meet all criteria specified herein. RAP materials must conform to the standard specifications.
d. Materials. Table 1 provides the mix design criteria and volumetric properties. Table 2 provides the required aggregate properties. Use aggregates of the highest quality available to meet the minimum specifications. Use the mixture designation number shown in the contract item name when determining mix design properties from Tables 1 and 2.
e. Measurement and Payment.
Contract Items (Pay Items) Pay Unit
HMA, (type) Ton
C&T:JMB
03SP501 (H)
08-06-04
Table 1: Mix Design Criteria and Volumetric Properties
Mixture No.
| 2C |
| 3C |
| 4C |
| 13A |
| 36A |
| Target Air Void, % (a) |
| 3.0 |
| 4.0 |
| 4.0 |
| 4.0 |
| 4.0 |
| VMA (min) (b) |
| 11.0 |
| 13.0 |
| 14.0 |
| 14.0 |
| 15.0 |
| VFA |
| 65- 78 |
| 65-78 |
| 65-78 |
| 65-78 |
| 65-78 |