wages.pdf
PDF 139 KB Posted
- Attached to
- Bear Creek Culvert Replacement FR 3517
- Solicitation number
- AG-54B0-S-10-0018
About this file
Wage Rates
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HIF070ENG Specs.pdf | ||
| hubzone_brochure.pdf | ||
| RFP.pdf | ||
| kr_return.pdf | ||
| HIF070ENG_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: MI100090 05/07/2010 MI90
Superseded General Decision Number: MI20080090
State: Michigan
Construction Type: Heavy
County: Chippewa County in Michigan.
HEAVY CONSTRUCTION PROJECTS (does not include airport or bridge construction projects, or sewer or water line work if it is incidental to a highway construction project)
Modification Number Publication Date
0 03/12/2010
1 04/16/2010
2 05/07/2010
BOIL0169-005 07/01/2008
Rates Fringes
BOILERMAKER (Excluding tank building)........................$ 31.953 20.869
BRMI0006-002 05/01/2009
Bricklayer; marble, terrazzo and tile setter..................$ 24.88 14.43
CEMENT MASON/CONCRETE FINISHER...$ 24.88 14.43
Pointer, caulker and cleaner.....$ 24.88 14.43
FOOTNOTES: Stacks: Work on industrial and powerhouse stacks shall receive $2.00 per hour above the journeyman bricklayer rate.
Industrial: Refinishing work on digesters, tanks, lime kilns, chests, boilers, and boiler tubes shall receive $2.00 per hour above the journeyman bricklayer rate.
CARP1510-002 05/01/2009
CARPENTER
(Includes concrete form work).......................$ 26.27 12.18
MILLWRIGHT.......................$ 30.78 12.40
Piledriver.......................$ 26.47 12.18
FOOTNOTES:
Waterfront work on the Great Lakes or connecting water navigable to Lake carriers: $0.20 per hour additional.
Work on industrial construction, defined as industrial manufacturing and processing plants such as ore plants, paper mills, power houses, foundries, saw mills, wood processing plants, or other industrial complexes: $.30 per hour additional.
ELEC0876-004 06/01/2009
LINE CONSTRUCTION
Cable Splicer...............$ 34.87 13.38
Groundman/Truck Driver
Groundman (trucks with winch or boom or dump, other than distribution work).......................$ 21.00 9.95
Light Equipment
Operator/Groundman/Truck
Driver Groundman (winch, A-frame, diggers when used for distribution line truck and used for distribution work.
Distribution truck driver, 5th wheel type trucks, bucket trucks, ladder trucks and all live boom trucks, all equipment 85 hp or under)................$ 22.06 10.21
Lineman/Line Technician.....$ 33.49 13.03
Operator/Groundman
(digger, tractor and setting rig with tracks or rough terrain vehicle, large bombardier, backhoe over 85 hp, hydraulic crane 10 ton or over).......$ 25.18 10.99
FOOTNOTE:
Operators of 5/8 yd. rated capacity backhoe or over, and operators of 25 ton, rated capacity, crane or over, and operators of heavy duty tension or pulling machinery on 345
KV and above, shall receive the line technician rate of pay.
ELEC1070-004 06/01/2009
ELECTRICIAN
Contracts $130,000 and under.......................$ 27.33 15.99+1%
Contracts over $130,000.....$ 29.33 16.05+1%
ENGI0324-012 05/01/2009
OPERATOR: Power Equipment
(Steel Erection)
Compressor, welder and forklift....................$ 24.53 17.55
Crane operator, main boom
& jib 120' or longer........$ 28.28 17.55
Crane operator, main boom
& jib 140' or longer........$ 28.53 17.55
Crane operator, main boom
& jib 220' or longer........$ 28.78 17.55
Mechanic with truck and tools.......................$ 29.28 17.55
Oiler and fireman...........$ 23.23 17.55
Regular operator............$ 27.78 17.55
PREMIUM RATES:
A. Swing boom truck operator over 15 tons-$.50 per hour.
B. Hydraulic crane operator 75 tons and under-$.75 per hour.
C. Hydraulic crane operator over 75 tons-$1.00 per hour.
D. Lattice boom crane operator-$1.50 per hour.
ENGI0324-027 10/01/2009
(Sewer Relining)
GROUP 1.....................$ 28.65 11.64
GROUP 2.....................$ 27.12 11.64
SEWER RELINING CLASSIFICATIONS
GROUP 1: Operation of audio-visual closed circuit TV system, including remote in-ground cutter and other equipment used in connection with the CCTV system
GROUP 2: Operation of hot water heaters and circulation systems, water jetters and vacuum and mechanical debris removal systems
ENGI0326-001 05/01/2009
(Gas Distribution Work)
GROUP 1.....................$ 25.07 17.80
GROUP 2-A...................$ 24.97 17.80
GROUP 2-B...................$ 24.75 17.80
GROUP 3.....................$ 23.97 17.80
GROUP 4.....................$ 23.47 17.80
POWER EQUIPMENT - GAS DISTRIBUTION CLASSIFICATIONS
GROUP 1: Mechanic, crane (over 1/2 yd. capacity), backhoe
(over 1/2 yd. capacity), grader (Caterpillar 12 equivalent or larger)
GROUP 2-A: Trencher(except service), backhoe (1/2 yd.
capacity or less)
GROUP 2-B: Crane (1/2 yd. capacity or less), compressor (2 or more), dozer (D-4 equivalent or larger), endloader (1 yd.
capacity or larger), pump (1 or 2 six-inch or larger), side boom (D-4 equivalent or larger)
GROUP 3: Backfiller, boom truck (powered), concrete saw (20 hp or larger), dozer (less than D-4 equivalent), endloader
(under 1 yd. capacity), farm tractor (with attachments), pump (2-4 under six-inch capacity), side boom tractor (less than D-4 equivalent), tamper (self-propelled), trencher service and grader(maintenance)
GROUP 4: Oiler, grease person, hydrostatic testing operator
ENGI0326-014 05/01/2009
(Includes Underground
Construction)
Crane operator, main boom
& jib 120' or longer........$ 27.88 17.55
Crane operator, main boom
& jib 140' or longer........$ 28.13 17.55
Crane operator, main boom
& jib 220' or longer........$ 28.38 17.55
GROUP 1.....................$ 27.38 17.55
GROUP 2.....................$ 24.13 17.55
GROUP 3.....................$ 23.55 17.55
GROUP 4.....................$ 22.61 17.55
Mechanic with truck and tools.......................$ 28.88 17.55
Swing boom truck operator over 15 tons: $.50 per hour additional. Hydraulic crane operator 75 tons and under:
$.75 per hour additional. Hydraulic crane operator over 75 tons: $1.00 per hour additional. Lattice boom crane operator: $1.50 per hour additional. Crusher pit, shaft and tunnel workers: $2.00 per hour additional. Premium rate:
main boom and jib 300 feet or longer is $1.50 per hour above the 220 ft. boom and jib rate. Premium rate: main boom and jib 400 feet or longer is $3.00 per hour above the
220 ft. boom and jib rate.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Regular equipment operator, crane, dozer, front end loader, job mechanic, pumpcrete and squeezecrete, welder, concrete pump, excavator, milling and pulverizing machines, scraper (self-propelled and tractor drawn), welder
GROUP 2: Air track drill, boom truck (non-swing), concrete mixer, material hoist and tugger, pump 6" and over, beltcrete, sweeping machine, trencher, winches, well points and freeze systems
GROUP 3: Air compressor, conveyor, concrete saw, farm tractor
(without attachments), fork truck, generator, guard post driver, mulching machine, pumps under 6-in., welding machine and grease person
GROUP 4: Oiler, fire tender, heater operator, brock concrete breaker, elevators (other than passenger, end dumps and skid steer
Crane Operator with main boom and jib 300' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 220' of boom and jib wage rate.
Crane Operator with main boom and jib 400' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 300 foot of boom wage rate ($3.00)
ENGI0326-017 10/01/2009
Power equipment operators -hazardous waste removal:
LEVEL A:
Engineer when operating crane with boom and jib or leads 140' or longer....$ 32.77 17.80
Engineer when operating crane with boom and jib or leads 220' or longer....$ 33.07 17.80
GROUP 1....................$ 30.12 17.80
GROUP 2....................$ 25.72 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 31.09 17.80
LEVEL B AND C:
Engineer when operating crane with boom and jib or leads 140' or longer....$ 31.71 17.80
Engineer when operating crane with boom and jib or leads 220' or longer....$ 32.03 17.80
GROUP 1....................$ 29.17 17.80
GROUP 2....................$ 24.78 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 30.14 17.80
LEVEL D WHEN CAPPING
LANDFILL:
Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.27 17.80
Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.57 17.80
GROUP 1....................$ 27.62 17.80
GROUP 2....................$ 23.23 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator and concrete pump with boom operator, power shovel operator......$ 28.59 17.80
LEVEL D:
Engineer when operating crane with boom and jib or leads 140' or longer....$ 30.52 17.80
Engineer when operating crane with boom and jib or leads 220' or longer....$ 30.82 17.80
GROUP 1....................$ 27.87 17.80
GROUP 2....................$ 23.48 17.80
Regular crane operator, mechanic, dragline operator, boom truck operator, concrete pump with boom operator, power shovel operator............$ 28.84 17.80
HAZARDOUS WASTE REMOVAL CLASSIFICATIONS
GROUP 1: Backhoe, batch plant operator, clamshell, concrete breaker when attached to hoe, concrete cleaning decontamination machine operator, concrete pump, concrete paver, crusher, dozer, elevating grader, endloader, farm tractor (90 h.p. and higher), gradall, grader, heavy equipment robotics operator, loader, pug mill, pumpcrete machines, pump trucks, roller, scraper (self- propelled or tractor drawn), side boom tractor, slip form paver, slope paver, trencher, ultra high pressure waterjet cutting tool system operator, vactors, vacuum blasting machine operator, vertical lifting hoist, vibrating compaction equipment
(self-propelled), well drilling rig and hydro excavator
GROUP 2: Air compressor, concrete breaker when not attached to hoe, elevator, end dumps, equipment decontamination operator, farm tractor (less than 90 h.p), forklift, generator, heater, mulcher, pigs (portable reagent storage tanks), power screens, pumps (water), stationary compressed air plant, sweeper, welding machine and water wagon
IRON0008-009 06/01/2009
Ironworker - pre-engineered metal building erector...........$ 23.70 6.95
IRONWORKER, Reinforcing and
Structural
Contracts $10,000,000 or greater.....................$ 26.13 20.27
Contracts less than
$10,000,000.................$ 23.04 20.27
LABO0005-021 10/01/2008
Laborers - hazardous waste abatement:
Work performed inside the building and up to and including 5 ft. outside the building:
Level A, B or C............$ 22.18 10.35
Work performed in conjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D..............$ 21.18 10.35
Work performed over 5 ft.
outside the building:
Level A, B or C............$ 20.44 9.80
Work performed in onjunction with site preparation not requiring the use of personal protective equipment;
Also, Level D..............$ 19.44 9.80
LABO0259-004 09/01/2009
Laborers - tunnel, shaft and caisson:
GROUP 1.....................$ 21.37 10.95
GROUP 2.....................$ 21.46 10.95
GROUP 3.....................$ 21.56 10.95
GROUP 4.....................$ 21.72 10.95
GROUP 5.....................$ 21.98 10.95
GROUP 6.....................$ 22.29 10.95
GROUP 7.....................$ 14.56 10.95
TUNNEL LABORER CLASSIFICATIONS
GROUP 1: Tunnel, shaft and caisson laborer, dump, shanty, hog house tender, testing (on gas)
GROUP 2: Manhole, headwall, catch basin builder, bricklayer tender, mortar, material mixer, fence erector and guard rail builder
GROUP 3: Air tool operator (jackhammer, bush hammer and grinder), first bottom, second bottom, cage tender, car pusher, carrier, concrete, concrete form, concrete repair, cement invert laborer, cement finisher, concrete shoveler, conveyor, floor, gasoline and electric tool operator, gunite, grout operator, welder, heading dinky person, inside lock tender, pea gravel operator, pump, outside lock tender, scaffold, top signal person, switch person, track, tugger, utility person, vibrator, winch operator, pipe jacking, wagon drill and air track operator and concrete saw operator (under 40 h.p.)
GROUP 4: Tunnel, shaft and caisson mucker, bracer, liner plate, long haul dinky driver and well point
GROUP 5: Tunnel, shaft and caisson miner, drill runner, key board operator, power knife operator, reinforced steel or mesh (e.g. wire mesh, steel mats, dowel bars, etc.)
GROUP 6: Dynamite and powder
GROUP 7: Restoration laborer, seeding, sodding, planting, cutting, mulching and top soil grading; and the restoration of property such as replacing mailboxes, wood chips, planter boxes, flagstones, etc.
SCOPE OF WORK: Tunnel, shaft and caisson work of every type and descripton and all operations incidental thereto, including, but not limited to, shafts and tunnels for sewers, water, subways, transportation, diversion, sewerage, caverns, shelters, aquafers, reservoirs, missile silos and steel sheeting for underground construction.
LABO0260-008 08/01/2009
Asbestos Laborer
Includes removing and disposing of all insulation materials from walls, ceilings, floors, columns, and all other non-mechanical surfaces; and removal of insulating materials from mechanical systems that are to be demolished;
loading/unloading of bagged and tagged materials at the disposal site (includes lead paint abatement clean-up).........$ 24.23 11.30
LABO0334-002 09/01/2009
Laborers - open cut:
GROUP 1.....................$ 18.45 10.95
GROUP 2.....................$ 18.59 10.95
GROUP 3.....................$ 18.72 10.95
GROUP 4.....................$ 18.77 10.95
GROUP 5.....................$ 18.82 10.95
GROUP 6.....................$ 16.20 10.95
GROUP 7.....................$ 14.31 10.95
LABORER CLASSIFICATIONS
GROUP 1: Construction laborer
GROUP 2: Mortar and material mixer, concrete form person, signal person, well point person, manhole, headwall and catch basin builder, guard rail builder, headwall, seawall, breakwall, dock builder and fence erector
GROUP 3: Air, gasoline and electric tool operator, vibrator operator, driller, pump person, tar kettle operator, bracer, rodder, reinforced steel or mesh person (e.g., wire mesh, steel mats, dowel bars, etc.), welder, pipe jacking and boring person, wagon drill and air track operator and concrete saw operator (under 40 h.p.), windlass and tugger person and directional boring person, cement finisher
GROUP 4: Trench or excavating grade person
GROUP 5: Pipe layer (including crock, metal pipe, multi-plate or other conduits)
GROUP 6: Grouting person, audio-visual television operations and all other operations in connection with closed circuit television inspection, pipe cleaning and pipe relining work, installation and repair of water service pipe appurtenances
GROUP 7: Restoration laborer, seeding, sodding, planting, cutting, mulching and top soil grading; and the restoration of property such as replacing mailboxes, wood chips, planter boxes, flagstones, etc.
SCOPE OF WORK:
Open cut construction work shall be construed to mean work which requires the excavation of earth including industrial, commercial and residential building site excavation and preparation, land balancing, demolition and removal of concrete and underground appurtenances, grading, paving, sewers, utilities and improvements; retention, oxidation, flocculation and irrigation facilities, and also including but not limited to underground piping, conduits, steel sheeting for underground construction, and all work incidental thereto, and general excavation.
Open cut construction work shall not include any structural modifications, alterations, additions and repairs to buildings, or highway work, including roads, streets, bridge construction and parking lots or steel erection work and excavation for the building itself and back filling inside of and within 5 ft. of the building and foundations, footings and piers for the building. Open cut construction work shall not include any work covered under Tunnel, Shaft and Caisson work.
* LABO1076-006 04/01/2010
ALCONA, ALGER, ALLEGAN, ALPENA, ANTRIM, ARENAC, BARAGA, BARRY,
BAY, BENZIE, BERRIEN, BRANCH, CALHOUN, CASS, CHARLEVOIX,
CHEBOYGAN, CHIPPEWA, CLARE, CLINTON, CRAWFORD, DELTA,
DICKINSON, EATON, EMMET, GENESEE, GLADWIN, GOGEBIC, GRAND
TRAVERSE, GRATIOT, HILLSDALE, HOUGHTON, HURON, INGHAM, IONIA,
IOSCO, IRON, ISABELLA, JACKSON, KALAMAZOO, KALKASKA, KENT,
KEWEENAW, LAKE, LAPEER, LEELANAU, LENAWEE, LIVINGSTON, LUCE,
MACKINAC, MACOMB, MANISTEE, MARQUETTE, MASON, MECOSTA,
MENOMINEE, MIDLAND, MISSAUKEE, MONTCALM, MONTMORENCY, MONROE,
MUSKEGON, NEWAYGO, OAKLAND, OCEANA, OGEMAW, ONTONAGON, OSCEOLA,
OSCODA, OTSEGO, OTTAWA, PRESQUE ISLE, ROSCOMMON, SAGINAW, ST.
CLARE, ST. JOSEPH, SANILAC, SCHOOLCRAFT, SHIAWASSEE, TUSCOLA,
VAN BUREN, WASHTENAW, WAYNE AND WEXFORD COUNTIES
LABORER (DISTRIBUTION WORK)
Zone 1......................$ 18.18 11.49
Zone 2......................$ 16.80 11.49
Zone 3......................$ 15.03 11.49
Zone 4......................$ 14.40 11.49
Zone 5......................$ 14.40 11.49
DISTRIBUTION WORK - The construction, installation, treating and reconditioning of distribution pipelines transporting coal, oil gas, or other similar materials, vapors or liquids, including portions of such pipelines within private property boundaries, up to and including the meter settings on residential, commercial, industrial, institutional, private and public structures. All work covering pumping stations and tank farms not covered by the
Building Trades Agreement. Other distribution lines with the exception of sewer, water and cable television are included.
Underground Duct Layer Pay: $.40 per hour above the base pay rate.
Zone 1-Macomb,Oakland and Wayne
Zone 2-Monroe and Washtenaw
Zone 3-Bay, Genesee, Lapeer, Midland, Saginaw, Sanilac, Shiawassee and St. Clair
Zone 4-Alger, Baraga, Chippewa, Delta, Dickinson,Gogebic, Houghton, Iron, Keweenaw, Luce, Mackinaw, Marquette, Menominee, Ontonagon and Schoolcraft
Zone 5-Remaining counties in Michigan
LABO1329-002 05/01/2009
Laborers:
Commercial Construction
GROUP 1....................$ 20.12 11.00
GROUP 2....................$ 20.52 11.00
GROUP 3....................$ 20.87 11.00
GROUP 4....................$ 18.17 11.00
GROUP 5....................$ 22.17 11.00
Industrial Construction
GROUP 1....................$ 21.78 11.00
GROUP 2....................$ 22.18 11.00
GROUP 3....................$ 22.53 11.00
GROUP 4....................$ 18.37 11.00
GROUP 5....................$ 23.83 11.00
FOOTNOTE: Work on waterfront work (working over water) on the
Great Lakes or connecting waters navigable to lake carriers: $0.75 per hour additional.
LABORER CLASSIFICATIONS
GROUP 1: All construction laborers on building and heavy construction work, storm and sanitary sewers, tool crib attendant, Civil Engineer helper, rodman, oxi-gun operator, workers using propane or acetylene cutting torch, motor-driven buggies, chipping hammers, tamping machines, green cutting (whether run by air, electric or gas), sandblasters, mason tenders, Mortar mixer, material mixer
(whether done by hand or machine), vibrator operator, concrete mixer, laborer with concrete crew, mixer to pour, including pour from trucks
GROUP 2: Cement gun nozzle operator, blaster, miner, driller, buster operator, layer of all non-metallic pipe
GROUP 3: Caisson worker and airtrack
GROUP 4: Watchman, Fire watch and Hole watch
GROUP 5: Digester, tanks & kilns
PLUM0111-012 07/06/2009
PIPEFITTER.......................$ 29.61 18.00
PLUM0190-006 05/01/2008
Gas Distribution Pipeline
Welding in conjunction with gas distribution pipeline work...............$ 27.63 15.64
All other work..............$ 20.26 9.90
SHEE0007-019 06/01/2008
SHEET METAL WORKER...............$ 27.96 17.04
SUMI2000-008 05/05/2000
BUILDING CONSTRUCTION
Tank Builder................$ 19.50 1.04
LABORER: Chain Saw..............$ 14.29
Landscape Laborer................$ 13.20 4.01
Truck drivers:
Boom Truck..................$ 17.40 5.52
Truck Driver - 2 axle.......$ 16.41 4.30
Truck driver - 3 axle.......$ 16.83 7.44
WELL DRILLER (water well)........$ 27.59 .13
Marble, terrazzo & tile finishers: $0.25 per hour above the laborer's rate. Same fringe benefit package as the bricklayer.
Stacks: Work on industrial and powerhouse stacks shall receive $2.00 per hour above the journeyman bricklayer rate.
Industrial: Refinishing work on digesters, tanks, lime kilns, chests, boilers, and boiler tubes shall receive $2.00 per hour above the journeyman bricklayer rate.
* TEAM0247-011 04/01/2010
TRUCK DRIVER (Underground construction)
GROUP 1.....................$ 21.82 a
GROUP 2.....................$ 21.96 a
GROUP 3.....................$ 22.15 a
PAID HOLIDAYS: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.
SCOPE OF WORK: Excavation, site preparation, land balancing, grading, sewers, utilities and improvements; also including, but not limited to, tunnels, underground piping, retention, oxidation, flocculation facilities, conduits, general excavation and steel sheeting for underground construction. Underground construction work shall not include any structural modifications, alterations, additions and repairs to buildings or highway work, including roads, streets, bridge construction and parking lots or steel erection.
FOOTNOTE:
a. $327.95 per week+$46.20 per day.
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Truck driver on all trucks (EXCEPT dump trucks of 8 cubic yards capacity or over, pole trailers, semis, low boys, Euclid, double bottom and fuel trucks)
GROUP 2: Truck driver on dump trucks of 8 cubic yards capacity or over, pole trailers, semis and fuel trucks
GROUP 3: Truck driver on low boy, Euclid and double bottom
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .