Revised_Schedule_of_Items.docx

DOCX document 30 KB Posted

Attached to
Dam Improvements on Hoosier NF Federal contract opportunity
Solicitation number
AG-52B1-S-17-0023
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Revised Schedule of Items to be used to submit your offer.

View the file

Other files for this federal contract opportunity

Other files attached to Dam Improvements on Hoosier NF, newest first.
File Type Posted
PreQuoteQuestions2017.docx DOCX document
PreQuoteAttendanceList.pdf PDF
Amendment1_SF30.pdf PDF
J2_MapDrawingsExhibitA_B.pdf PDF
J1_SpecialProjectSpecifications.doc DOC document
J3_WaterbarTrailCrossSectionDrawings.pdf PDF
J4_Photos.pdf PDF
J5_WageDetermination.pdf PDF
RFQ_AG52B1S170023.rtf RTF text file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

PAGE OF PAGES

(THIS IS NOT AN ORDER)
THIS RFQ
|X|
IS
|_|
IS NOT A SMALL BUSINESS SET- ASIDE
1
35
1. REQUEST NO.
2. DATE ISSUED
3. REQUISITION/PURCHASE REQUEST NO.
4. CERT. FOR NAT.DEF.
RATING
AG-52B1-S-17-0023
04/10/2017
851240
UNDER BDSA REG. 2

AND/OR DMS REG. 1

5a. ISSUED BY
6. DELIVER BY (Date)
USDA FS, Attn: Melissa Johnson, 4 Farm Colony Drive, Warren, PA 16365
See Section F
5b. FOR INFORMATION CALL (NO COLLECT CALLS)
7. DELIVERY
|_|
FOB DESTINATION
NAME
TELEPHONE NUMBER
|_|
OTHER (See Schedule)
Melissa Johnson
AREA CODE
NUMBER
9. DESTINATION
melissaajohnson@fs.fed.us
814
728-6241
a. NAME OF CONSIGNEE
8. TO:
Hoosier National Forest
a. NAME
b. COMPANY
b. STREET ADDRESS

248 15th St

c. STREET ADDRESS
c. CITY
Tell City
d. CITY
e. STATE
f. ZIP CODE
d. STATE
e. ZIP CODE
IN
47586
10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5A ON OR BEFORE CLOSE OF BUSINESS
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A. This request does not commit the Government to pay any costs incurred in the preparation of the
05/05/2017 at 4:30 PM ET
submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(a)
(b)
(c)
(d)
(e)
(f)
Hoosier National Forest

Tell City Ranger District Indian Lake and Celina Lake Dam Improvements Project

Enter pricing on schedule of items in section B

Submit the completed SF-18, Section B, and Section K as your offer.
.
This project is 100% set-aside for small businesses
Offers can be emailed to melissaajohnson@fs.fed.us or

Hardcopy mailed to address in block 5a. No faxes. note that time for submission is Eastern time. You should request confirmation of all emailed offers. Note two a’s in email address.

a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS (%)
c. 30 CALENDAR DAYS (%)
d. CALENDAR DAYS

12. DISCOUNT FOR PROMPT PAYMENT

NUMBER
PERCENTAGE
NOTE: Additional provisions and representations
|X|
are
|_|
are not attached.
13. NAME AND ADDRESS OF QUOTER
14. SIGNATURE OF PERSON AUTHORIZED TO
15. DATE OF
a. NAME OF QUOTER
SIGN QUOTATION
QUOTATION
b. STREET ADDRESS
16. SIGNER
a. NAME (Type or print)
b. TELEPHONE

c. COUNTY

AREA CODE

d. CITY
e. STATE
f. ZIP CODE
c. TITLE (Type or Print)
NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121
STANDARD FORM 18 (Rev. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

Construction RFQ

AG-52B1-S-17-0023

Indian and Celina Lake Dam Imp

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

Schedule of Items (Revision 1) Base Item Work “Indian Lake Rip Rap Placement”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Riprap installation, including dam work
1
Lump Sum
Lump Sum
$
$
2
Aggregate (18” Riprap)
840
Design Quantity
Tons
$
$
3
Aggregate (INDOT #53)
100
Design Quantity
Tons
$
$
4
Geotextile Fabric
950
Design Quantity
Yards
$
$
5
Seeding and Mulching
1
Design Quantity
Acre
$
$
6
Mobilization*
1
Lump Sum
Lump Sum
$
$

Base Work Items Cost……………………………….…………………………………$___________ Optional Work Items One or more of the following optional bid items may be awarded depending on pricing and funding available for the project.

Optional Work Item 1 “Indian Lake Slump Repair”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Slump excavation and repair
1
Lump Sum
Lump Sum
$
$
2
Aggregate (INDOT #7)
150
Design Quantity
Tons
$
$
3
Aggregate (INDOT #1)
150
Design Quantity
Tons
$
$
4
Geotextile Fabric
350
Design Quantity
Yards
$
$
5
Seeding and Mulching
.2
Design Quantity
Acre
$
$

Optional Work Item 1 Cost…..……………….…………………………………$___________

Optional Work Item 2 “Indian Lake Trail Repair”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Trail Grading Repair
1
Lump Sum
Lump Sum
$
$
2
Aggregate (INDOT #73)
21
Design Quantity
Tons
$
$

Optional Work Item 2 Cost……………………………………………………………$___________

Optional Work Item 3 “Celina Lake Pool Rip Rap”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Riprap installation, including dam work
1
Lump Sum
Lump Sum
$
$
2
Aggregate (18” Riprap)
190
Design Quantity
Tons
$
$
3
Geotextile Fabric
250
Design Quantity
Yards
$
$
4
Seeding and Mulching
.25
Design Quantity
Acre
$
$

Optional Work Item 3 Cost…………………………………………………………$___________

Optional Work Item 4 “Celina Lake Slump Repair”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Slump excavation and repair, Dam repair work
1
Lump Sum
Lump Sum
$
$
2
Aggregate (INDOT #7)
325
Design Quantity
Tons
$
$
3
Aggregate (INDOT #1)
325
Design Quantity
Tons
$
$
4
Aggregate (INDOT #53)
100
Design Quantity
Tons
$
$
5
Geotextile Fabric
730
Design Quantity
Yards
$
$
6
Seeding and Mulching
0.3
Design Quantity
Acre
$
$
7
Mobilization
1
Lump Sum
Lump Sum
$
$

Optional Work Items 4 Cost……………………………….…………………………$___________

Optional Work Item 5 “Celina Lake Rip Rap above Pool”

Line Item
Title
Quantity
Method of Measure
Unit
Unit Price
Total Price
1
Riprap installation, including dam work
1
Lump Sum
Lump Sum
$
$
2
Aggregate (18” Riprap)
170
Design Quantity
Tons
$
$
3
Geotextile Fabric
375
Design Quantity
Yards
$
$
4
Seeding and Mulching
.25
Design Quantity
Acre
$
$

Optional Work Items 5 Cost…………………………………………………………$___________

Base Item Project Total$___________
Optional Work Items Total$___________
Total All Items$___________
Bond/ILC cost per $1000*$___________

NOTES:

a. * Assume a decision to exercise options will be made prior to demobilization from base item work. If not, re-mobilization will be negotiated and handled as a contract modification. There is a requirement for payment protections (Irrevocable Letter of Credit (ILC) or payment bond) if award is over $35,000. The payment bond or ILC will be for 100% of the award price. Don’t include bond costs in mobilization line, include it as a price per $1000 as shown above. See Section I for additional information. There is no bid guarantee required.

b. Contractor must be registered www.sam.gov to be considered. THIS IS A FREE REGISTRATION.

c. There is a pre-bid meeting at the Tell City Ranger District Office on April 20, 2017 at 1 PM CT. The address is 248 15th St, Tell City, IN 47586.

e. Award will be made to one contractor. You must submit pricing for all items, including all optional items.